Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
Agenda Leftfield Introduction MSBA feasibility study deliverables - - PowerPoint PPT Presentation
Agenda Leftfield Introduction MSBA feasibility study deliverables - - PowerPoint PPT Presentation
Elbridge Gerry Feasibility Study May 11, 2017 Gerry School Building Committee Meeting Agenda Leftfield Introduction MSBA feasibility study deliverables Review conceptual feasibility schedule MSBA designer selection process Review designer
Who We Are
SERVICES PROVIDED: Owner Representation Clerk of the Works Cost Management and Reporting Construction Administration Audit Services Estimating Services MEP Expertise DEPTH OF OUR FIRM: 1 Principal 7 Project Managers 5 Clerks 2 MEP Specialists 1 Administrator
Firm Overview
- LEFTFIELD
is a full service Owner’s Project Management Firm; having been in business for 10 years
- LEFTFIELD’s staff has completed over $1 Billion in
Public Construction in Massachusetts
- LEFTFIELD’s staff has worked with the MSBA since its
inception
- LEFTFIELD’s staff has completed over $1 Billion in
MSBA K‐12 projects in Massachusetts
- LEFTFIELD has significant experience and success
managing complex construction logistics and phased construction projects on occupied sites
Who We Are
Public Clients
Who We Are
Current MSBA Work
$176M Billerica Memorial H.S. Billerica, Massachusetts 400,000 SF Durfee High School Fall River, Massachusetts Garfield K‐8 School Revere, Massachusetts Carver Middle/High School Carver, Massachusetts Springfield ARP Projects (6) Balliet Middle School
Who We Are
Prior MSBA Work
Wayland High School; 200,000 SF; $70.8M; Delivered ahead of schedule; $3.4M under budget Concord‐Carlisle Regional High School; 235,000 SF; $92.6M; Delivered on schedule; $2M under budget Salem High School; 430,000 Square Foot; $67.3m; Occupied, Phased Renovation; Delivered on schedule and under budget
Who We Are
HIGHER ED ‐ PUBLIC
$25M Mainstage Theater Salem State University $62M Isenberg School UMass Amherst Fox Hall Elevator Addition and Modernization UMass Lowell
Your Team
Team Organizational Chart
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Feasibility Study Deliverables – Process
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
Conceptual Schedule
COMPLETED ONGOING
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Modules
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Designer Selection Process
1. Introduction 2. Designer Selection Panel 3. Public Notice 4. Master File Brochure and Application 5. Selection Criteria 6. Selection Process 7. Award of Contract 8. RFS overview 9. Schedule of tasks/activities
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Designer Selection Process Introduction
- A designer selection process adopted by the MSBA to serve as
an exemption from the jurisdiction of the Commonwealth Designer Selection Board.
- Process required for projects with an estimated construction
value to be equal or greater than $5mm.
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Designer Selection Process
Designer Selection Panel (DSP)
- Composed of 13 members appointed by the Executive Director of the
MSBA with varying areas of expertise, plus….
- 3 members proposed by the respective city/town/district, etc.
- 1 member shall be designated by the school committee.
- 1 member shall be the superintendent of schools.
- 1 member shall be the CEO of the city/Town.
- Min. of 9 members shall constitute a quorum.
- Meetings are open to the public and are typically held every two weeks.
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Designer Selection Process
Public Notice
- Contracts for designer services shall be advertised in a local newspaper
and the Central Register at least two weeks before filing deadlines. Master File Brochure and Application
- Prior to filing on any project Designers are required to file a Master File
Brochure to the DSP and update on an annual basis.
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Designer Selection Process
Selection Criteria
- Qualified Designer within the meaning of M.G.L. Ch. 7C, section 44.
- MCPPO certified.
- Must agree to contract with MBE/WBE businesses at a min. of 17.9% of the
contract value.
- Prior and past experience/performance.
- Workload.
- Qualifications of personnel / consultants assigned to the project.
- Financial stability.
- Geographical proximity of the firm.
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Designer Selection Process
Selection Process
- The 3 member District DSP participants or any of the MSBA appointed DSP
members shall not rank or pre‐rank applicants. Rankings shall only occur by vote
- f the DSP or after interviews (if required by the DSP).
- Rankings (points assigned) are done via ballot form at the DSP meetings. Example:
number one choice shall receive 3pts, number two choice shall receive 2pts., etc.
- Ballots are collected and tallied. Total points are read aloud.
Continued…….
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Designer Selection Process
Selection Process – Continued Selection Process Options
- DSP may request interviews with highest point total applicants. After
interviews are completed, the DPS shall rank the firms in order of qualifications.
- If the DSP choses not to conduct interviews, then the DSP shall rank the 3
highest point total firms in order of qualifications.
- In the event of ties, the chairperson of the DSP shall determine a procedure
to break such tie.
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Designer Selection Process
Award of Contract
- Contract is subject to the approval of the MSBA.
- If the Applicant (Marblehead) choses not to proceed with the highest ranked
designer a written justification shall be issued to the DSP and the applicant shall not proceed until they have received written approval to proceed from the Executive Director. Additional information on the MSBA selection process can be found at: http://www.massschoolbuildings.org/building/team/dsp
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
MSBA Designer Selection Process
RFS overview
- Standard MSBA RFS (Request For Services) shall be utilized.
- Edits to the RFS shall be reviewed and approved by the MSBA prior to
public advertising.
- Sample edits:
- Project background data.
- Specific project goals can be defined.
- Scopes of services can be refined.
- Project specific schedule milestones.
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
Draft Designer Procurement Schedule
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
Options – Project Understanding
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
Options – Project Understanding
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
Preliminary Option List
Elbridge Gerry Feasibility Study May 11, 2017 – Gerry School Building Committee Meeting
Beacon/Green Site – Options 7 | 12 Coffin Site – Options 6 | 11