UM 2005 Distribution System Planning Webinar #10 OPUC Policies - - PowerPoint PPT Presentation

um 2005
SMART_READER_LITE
LIVE PREVIEW

UM 2005 Distribution System Planning Webinar #10 OPUC Policies - - PowerPoint PPT Presentation

UM 2005 Distribution System Planning Webinar #10 OPUC Policies and Practices 6/11/2020 1 About Todays Webinar This webinar is a Special Public Meeting Todays session is being recorded and will be a matter of public record If


slide-1
SLIDE 1

UM 2005 Distribution System Planning

Webinar #10 OPUC Policies and Practices 6/11/2020

1

slide-2
SLIDE 2
  • This webinar is a Special Public Meeting
  • Today’s session is being recorded and will be a matter of public record
  • If you are considering sharing or discussing any confidential information

please keep in mind it will become public

2

About Today’s Webinar

slide-3
SLIDE 3

1. Welcome - Nick Sayen, OPUC Staff 2. Zoom logistics and participation - Katie Wu, Gridworks 3. Agenda, Desired Outcomes and Review - Nick Sayen 4. Integrated Resource Plan - Rose Anderson, OPUC Staff 5. Transportation Electrification Plan - Eric Shierman, OPUC Staff 6. Public Purpose Charge - Anna Kim, OPUC Staff 7. Next Steps - Nick Sayen

4

Agenda

slide-4
SLIDE 4

5

Desired Outcomes

  • Present areas of OPUC policy and practice likely to intersect with DSP
  • Focus on most relevant regulatory practices, not exhaustive
  • Goal: prompt thinking and dialogue to continue throughout

investigation

  • Not recommendations or proposals
slide-5
SLIDE 5

Integrated Resource Plan

Rose Anderson, OPUC Staff

6

slide-6
SLIDE 6

Load Forecasting System Assessment Grid Needs Assessment Solution Identification Project Design and Construction System Monitoring and Control

Distributed Generation Interconnection

Potential Points of Intersection

Figure adapted from: GridLab (2019) Integrated Distribution System Planning: A Path Forward

Integrated Resource Plans

7

Energy Efficiency and Demand Response Programs

slide-7
SLIDE 7
  • Utility files 20-year plan pursuant to OPUC’s IRP Guidelines
  • IRP seeks to meet forecast needs of customers
  • Distribution system not often a major focus
  • Goal: Best combination of cost and risk for utility and customers

8

Integrated Resource Plan (IRP) Overview

slide-8
SLIDE 8
  • Current inputs to the IRP
  • Load forecast:
  • Electric Vehicle (EV) forecast
  • Distributed Energy Resources (DER) forecast
  • Energy Efficiency (EE) acquisition (sometimes)
  • System topology (high-level)
  • Policy
  • Information on new and existing resources

9

Integrated Resource Plan

slide-9
SLIDE 9

10

Integrated Resource Plan

  • Current outputs from the IRP
  • Resource acquisition:
  • Generation and transmission
  • Demand response (DR)
  • Efficiency
  • Other plans:
  • Other means of reducing cost and risk (e.g., retiring or selling assets)
  • Studies
  • Stakeholder processes
slide-10
SLIDE 10

11

IRP and DSP Inputs and Outputs

  • IRP inputs (high-level):
  • Load forecast
  • EV forecast
  • DER forecast
  • Potential DSP outputs (locational):
  • Efficiency and DR acquisition
  • Utilization of DER services (DSP)
  • Distribution upgrades
  • Non-Wires Solutions
  • Potential DSP inputs (locational):
  • Load forecast
  • EV forecast
  • DER forecast
  • IRP outputs (high-level):
  • Efficiency and DR acquisition
  • Utility-scale generation
  • Transmission upgrades
  • Non-Wires Solutions

Inputs/outputs of IRP and DSP potentially similar:

slide-11
SLIDE 11

For data in both IRP and DSP:

  • Top-down approach?
  • High-level, allocate by location
  • IRP informs DSP
  • Bottom-up approach?
  • Locational detail, aggregate up
  • DSP informs IRP
  • Consistent methodologies and assumptions
  • Resource plan from each process can inform the other
  • Implementation should be informed by stakeholders and utilities

12

Flow of Information: Top-down or Bottom-up?

slide-12
SLIDE 12

Thank you! Rose Anderson, Senior Economist rose.anderson@puc.state.or.us 503-378-8718

13

Questions and Discussion

slide-13
SLIDE 13

Transportation Electrification Plan

Eric Shierman, OPUC Staff

14

slide-14
SLIDE 14
  • Section 20 of SB 1547
  • Order No. 19-134 (AR 609) established the plan guidelines as OAR

860-087-0020

  • Condition of the transportation electrification market
  • Summary of the electric company’s programs
  • How the programs accelerate transportation electrification
  • Supporting data
  • Company’s impact on market competition
  • System impacts
  • Carbon reduction

15

Transportation Electrification (TE) Plan Overview

slide-15
SLIDE 15

Load Forecasting System Assessment Grid Needs Assessment Solution Identification Project Design and Construction System Monitoring and Control

Distributed Generation Interconnection

Potential Points of Intersection

Transportation Electrification Plans

16

Energy Efficiency and Demand Response Programs

Figure adapted from: GridLab (2019) Integrated Distribution System Planning: A Path Forward

slide-16
SLIDE 16
  • IRP analogy: load forecast
  • Power flow study
  • PGE: “PGE did not conduct power flow analyses to determine EV hosting capacity or estimate locational
  • value. Such analyses will be done in concert with other new loads coming to the system through the

course of the DRP (the guidelines of which are being established through Docket No. UM 2005). Through that plan, we aim to identify where system constraints may exist and what strategic deployments of DERs could mitigate those constraints.” TE Plan, September 30, 2019

  • PacifiCorp: “To study potential impacts of higher levels of residential electric vehicle adoption,

sensitivities representing electric vehicle market share of 12% and 14% by 2025 were analyzed. After adjusting the baseline to reflect the impacts of potential new electric vehicle adoption, power flow analysis was performed using time series analysis and peak feeder loading to evaluate the impacts of increased adoption on existing equipment, devices, and voltage delivery.” Attachment 5, Potential System Impact Study, September 2018, TE Plan, February 3, 2020

  • What other stakeholder interests would a general power flow study help inform?
  • Is power flow modeling to DSP what capacity expansion modeling is to the IRP?

18

Which TE Plan elements should inform a future DSP?

slide-17
SLIDE 17

Thank you! Eric Shierman, Utility Analyst eric.shierman@state.or.us (503) 378-6638

19

Questions and Discussion

slide-18
SLIDE 18

Public Purpose Charge

Anna Kim, OPUC Staff

20

slide-19
SLIDE 19

Load Forecasting System Assessment Grid Needs Assessment Solution Identification Project Design and Construction System Monitoring and Control

Public Purpose Charge Distributed Generation Interconnection

Potential Points of Intersection

Public Purpose Charge

21

Energy Efficiency and Demand Response Programs

slide-20
SLIDE 20
  • Public Purpose Charge is paid for by ratepayers
  • Public Purpose Charge pays for:
  • Energy efficiency in schools (ODOE)
  • Low income weatherization (OHCS)
  • Self-directed energy efficiency for large customers (ODOE/Energy Trust)
  • Energy efficiency (Energy Trust)
  • “Above-market costs” of renewables (Energy Trust)
  • These services have cost-effectiveness requirements that can, in the

future, incorporate locational values

22

Public Purpose Charge: A Resource for DSP

slide-21
SLIDE 21

It’s more than a non-wires alternative! How can public purpose funds best support distribution planning? Who can we partner with? How can we be more proactive and less reactive? Here’s some data that could be helpful:

23

Points of Interaction with DSP

  • Billing analysis
  • Participant information (solar, storage,

new buildings, etc.)

  • Baseline equipment information
  • Related market research
  • Energy burden
slide-22
SLIDE 22

How do we identify the best opportunities for leveraging investments between public purpose funds and distribution system planning? We have set up processes to combine funds and handle attribution both between different public purpose charge categories and with other funding sources

  • There are opportunities to pair public purpose funds with other funds

to support DSP projects

  • As planning horizons and interest grows, there will be choices about

where to invest, and how to invest in those locations

24

Points of Interaction with DSP

slide-23
SLIDE 23

25

Proactive Example

Planning

“We need a substation--now!”

NEED!

Building

slide-24
SLIDE 24

26

Proactive Example

NEED!

Planning

“We need a substation--now!”

NEED!

“What are the options?”

EE+DR, solar+storage, batteries? microgrid? Substation? Who wants to partner with us?

Building Planning Building

slide-25
SLIDE 25
  • How can we best use public purpose funds to support distribution

system planning?

  • What new opportunities are available to pair public purpose funds with
  • ther funds for DSP?
  • In the future, if there is a lot of interest in DSP-related investments,

how do we prioritize project locations and project types?

27

Discussion

slide-26
SLIDE 26

Thank you! Anna Kim, Senior Utility Analyst anna.kim@puc.state.or.us 503-378-6360

28

Keep the Ideas Coming

slide-27
SLIDE 27

Shared understanding

  • f the baseline

Shared understanding

  • f opportunities/best

practices from elsewhere Special Public Meeting Draft recommendation Public comment Workshop on revised recommendation Final recommendation Public Meeting

29

Next Steps

slide-28
SLIDE 28

30

Next Steps

slide-29
SLIDE 29

31

THANK YOU!

Nick Sayen, Senior Utility Analyst Energy Resources & Planning nick.sayen@state.or.us