Landmark Preservation Committee Design Presentation 10 July 2018 119-121 2nd Avenue New York, NY Nexus Building Development Group Morris Adjmi Architects www.ma.com SITE St. Mark's Pl 36 131 122 118 45 49 85 91 129 11 E 7 St 84


slide-1
SLIDE 1

119-121 2nd Avenue New York, NY Nexus Building Development Group 10 July 2018

Landmark Preservation Committee Design Presentation

Morris Adjmi Architects www.ma.com

slide-2
SLIDE 2

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

2 East Village / Lower East Side Historic District

36 131 45 46 84 85 49 116 11 239 226 301 300 340 91 122 129 122 445 207 210 57 54 86 91 7 57 30 64 50 4 3 3 9 26 36 95 101 52 80 43 77 32 34 118 341 405 94

2 Av 1 Av E 4 St Av A E 7 St E 6 St E 3 St E 2 St E 5 St

  • St. Mark's Pl

Bowery 3 Av

¯

250 Feet

NoHo Historic District Extension NoHo East Historic District

SITE

VIEW OF SITE LOOKING WEST FROM 2ND AVENUE

50’- 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50’- ’- ’- ’-

EAST VILLAGE / LOWER EAST SIDE HISTORIC DISTRICT MAP

slide-3
SLIDE 3

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

3 1940s Photos

slide-4
SLIDE 4

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

4 1980s Tax Photos

slide-5
SLIDE 5

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

5 Site - Existing Conditions

E A S T 7 T H S T R E E T S T . M A R K ’ S P L A C E E A S T 6 T H S T R E E T 2 N D A V E N U E

N

6 3 2 4 5 6 1 1 2 3 5 7 8 7 8 4

slide-6
SLIDE 6

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

6 East Village / Lower East Side Historic District References - Facade

3 6 131 4 5 4 6 8 4 8 5 4 9 116 1 1 2 3 9 2 2 6 3 1 3 3 4 9 1 122 1 2 9 1 2 2 4 4 5 2 7 2 1 5 7 5 4 8 6 9 1 7 5 7 3 6 4 5 4 3 3 9 2 6 3 6 95 101 5 2 8 4 3 7 7 3 2 3 4 118 3 4 1 4 5 9 4

2 A v 1 A v E 4 S t A v A E 7 S t E 6 S t E 3 S t E 2 S t E 5 S t S t . M a r k ' s P l

rce: MapPLUTO, Edition 09v1, 2009. Author: Landmarks Preservation Commission, JM. Date: October 9, 2012

¯

250 Feet

  • Ho Historic

rict Extension

  • Ho East
  • ric District

1 3 2 4 5 6 1 3 2

87 2nd Avenue

4 5 6

131 2nd Avenue 104 2nd Avenue 88 2nd Avenue 69 2nd Avenue 50 2nd Avenue

1

KEY

2 3 4 5 6

N

slide-7
SLIDE 7

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

7 East Village / Lower East Side Historic District References - Masonry Details

slide-8
SLIDE 8

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

8 East Village / Lower East Side Historic District References - Storefront

slide-9
SLIDE 9

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

9 East Village / Lower East Side Historic District - Cornice

slide-10
SLIDE 10

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

10 Project Overview - Proposed

EAST 7TH STREET 2ND AVENUE

N

slide-11
SLIDE 11

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

11 Detail Rendering

EAST 7TH STREET 2ND AVENUE

N

slide-12
SLIDE 12

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

12

EAST 7TH STREET 2ND AVENUE

7th Street Rendering

N

slide-13
SLIDE 13

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

13 Street Scape - 7th Street

Lot 43

#29 East 7th Street

Lot 42

#31 East 7th Street

Lot 41

#33 East 7th Street

Lot 40

#35 East 7th Street

Lot 39

#37 East 7th Street

Lot 38

#39 East 7th Street

Lot 36

#41 East 7th Street

Lot 34/35

#119-121 2nd Avenue HT: 60’ FL: 5 HT: 45’ FL: 4 HT: 53’ FL: 4 HT: 55’ FL: 4 HT: 40’ FL: 3 1/2 HT: 55’ FL: 4 HT: 71’ FL: 6

Lot 30

#129 2nd Avenue

Lot 28

#131 2nd Avenue

Lot 31

#127 2nd Avenue

Lot 32R

#125 2nd Avenue

Lot 33

#123 2nd Avenue

Lot 34/35

#119-121 2nd Avenue HT: 71’ FL: 6 HT: 71’ FL: 6 HT: 71’ FL: 6 HT: 77’-5” FL: 7 77’-7” PROPOSED BUILDING HEIGHT (VACANT)

BUILDING BEYOND

Lot #

#117 2nd Avenue

Lot #

#115 2nd Avenue

Lot #

#113 2nd Avenue HT: 56’ FL: 4 HT: 46’ FL: 3 HT: 89’ FL: 5

2ND AVENUE

NOT IN EAST VILLAGE / L.E.S. HISTORIC DISTRICT

  • ST. MARK’S PL.

EAST 7TH

SCALE: 1” = 30’

BUILDING BEYOND

69’-0” PROPOSED CORNICE HEIGHT 99’-4” PROPOSED BULKHEAD LEVEL

*Note: Building Heights Measured At Cornice

77’-4” PROPOSED BUILDING HEIGHT 69’-0” PROPOSED CORNICE HEIGHT 99’-4” PROPOSED BULKHEAD LEVEL

slide-14
SLIDE 14

Morris Adjmi Architects www.ma.com

14

SCALE: 3/32” = 1’-0” 119-121 2nd Avenue Nexus Building Development 10 July 2018

East Elevation - 2nd Avenue

EAST 7TH

slide-15
SLIDE 15

Morris Adjmi Architects www.ma.com

15

SCALE: 3/32” = 1’-0” 119-121 2nd Avenue Nexus Building Development 10 July 2018

South Elevation - 7th Street

2ND AVENUE

slide-16
SLIDE 16

N

1 2 3 4 5 6 8 7

7TH STREET 6TH STREET 5TH STREET 4TH STREET

  • ST. MARK’S PL.

9TH STREET 2ND AVENUE

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

16 Street Views Studies - Key Map

slide-17
SLIDE 17

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

17 Street View Study - Proposed Building Massing

2 1

slide-18
SLIDE 18

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

18 Street View Study - Proposed Building Massing

3 4 5

slide-19
SLIDE 19

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

19 Street View Study - Proposed Building Massing

6 7

slide-20
SLIDE 20

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

20 Street View Study - Proposed Building Massing

8

slide-21
SLIDE 21

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

21 Detail Elevation - Typical Storefront

  • SCALE: 3/8” = 1’-0”
slide-22
SLIDE 22

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

22 Detail Elevation - Typical Residential Floor

  • SCALE: 3/8” = 1’-0”
slide-23
SLIDE 23

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

23 Detail Elevation - 6th Floor

  • SCALE: 3/8” = 1’-0”
slide-24
SLIDE 24

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

24 Detail Elevation - Penthouse

  • SCALE: 3/8” = 1’-0”
slide-25
SLIDE 25

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

25 Detail Elevation - Residential Entrance

  • SCALE: 3/8” = 1’-0”
slide-26
SLIDE 26

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

26 Storefront Signage

1ST FLOOR

  • 4 7/8"

2ND FLOOR 13'-7 1/8" PRE-FINISHED PTD.

  • MTL. STOREFRONT

SIGNAGE BAND

1'-6" MAX. 4" MAX. 2'-0" 1'-6" 7'-11" MIN. 10'-0" 2'-0" 10'-0"

BRACKET SIGNAGE BRACKET SIGNAGE SIMULATED DIVIDED LIGHTS WITH LEAD CAMING 1ST FLOOR

  • 4 7/8"

2ND FLOOR 13'-7 1/8"

U/S OF SLAB 13'-4" 2'-0" MAX. 1'-6" 2'-0" MAX. 10'-0" MIN. 1'-6" 10'-0" MIN.

PRE-FINISHED PTD.

  • MTL. STOREFRONT

SIGNAGE BAND BRACKET SIGNAGE SIMULATED DIVIDED LIGHTS WITH LEAD CAMING 2ND FLOOR 13'-7 1/8"

MAX. 1'-6" 4"

METAL HANGER ROD BY FUTURE TENANT METAL ANGLE SIGNAGE SUPPORT SIGNAGE BY FUTURE TENANT SIMULATED DIVIDED LIGHTS LEAD CAMING STRIP ON INTERIOR AND EXTERIOR PANE INTERNAL SIMULATED DIVIDED LIGHT BAR ETCHED FINISH ON INSIDE FACE OF EXTERIOR PANE 1/8" = 1'-0"

1

7TH STREET (SOUTH) STOREFRONT ELEVATION

1/8" = 1'-0"

2 2ND AVENUE (EAST) ELEVATION

1" = 1'-0"

3 COMMERCIAL SIGNAGE

slide-27
SLIDE 27

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

27 Detail Views

RESIDENTIAL ENTRANCE CORNER WINDOW AT STOREFRONT

slide-28
SLIDE 28

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

28 Detail Views

CORNER WINDOW AT TYPICAL RESIDENTIAL FLOOR CORNER WINDOW AT CORNICE

slide-29
SLIDE 29

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

29 Floor Plans

  • 1ST FLOOR

2ND FLOOR 3RD FLOOR SCALE: 3/64” = 1’-0” RETAIL 01 RETAIL 02

RES. LOBBY

  • 4TH AND 5TH FLOOR
slide-30
SLIDE 30

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

30 Floor Plans

  • 6TH FLOOR

7TH FLOOR

HT: 77' - 2" HT: 68' - 7" HT: 64' - 7" HT: 76' - 6" HT: 13' - 7" HT: 85' - 6" HT: 89' - 2" HT: 98' - 6" HT: 17' - 1" HT: 27' - 1" HT: 86' - 4" HT: 85' - 6" HT: 65' - 0" HT: 69' - 0" HT: 77' - 7" HT: 76' - 11" HT: 99' - 4" HT: 89' - 7"

SCALE: 3/64” = 1’-0” ROOF PLAN

slide-31
SLIDE 31

119-121 2nd Avenue Nexus Building Development 10 July 2018 Morris Adjmi Architects www.ma.com

31 Building Material - Proposed

CAST STONE: WINDOW SURROUNDS,

  • BANDING. COLOR: CORINTHAN CAST

STONE INC. - LS17C CORRUGATED ZINC: PENTHOUSE AND BULKEAD FACADE. COLOR: PRE-WEATHERED VM ZINC - QUARTZ ZINC PAINTED METAL: STOREFRONT, WINDOW FRAMES, RESIDENTIAL ENTRANCE, CORNICE AND GUARDRAIL. ALL PAINTED METAL TO BE PPG -DURANAR STAUB GRAY. GREY BRICK: BASE, BODY AND FRIEZE, RESIDENTIAL ENTRY COLOR: GLEN GERY - OYSTER GREY PERFORATED METAL PANEL: 1” SQUARE OPENING AT 2”

  • SPACING. PANEL COLOR TO BE

PPG - DURANAR STAUB GRAY