Integrated Regional Resource Plan Inaugural Local Advisory Committee - - PowerPoint PPT Presentation

integrated regional resource plan
SMART_READER_LITE
LIVE PREVIEW

Integrated Regional Resource Plan Inaugural Local Advisory Committee - - PowerPoint PPT Presentation

GREENSTONE-MARATHON Integrated Regional Resource Plan Inaugural Local Advisory Committee Meeting June 29, 2015 Presentation Outline Introduction to the Ontario Electricity Sector Electricity planning in Northwestern Ontario Summary


slide-1
SLIDE 1

GREENSTONE-MARATHON Integrated Regional Resource Plan

Inaugural Local Advisory Committee Meeting June 29, 2015

slide-2
SLIDE 2
  • Introduction to the Ontario Electricity Sector
  • Electricity planning in Northwestern Ontario
  • Summary of findings from the Greenstone-Marathon Integrated

Regional Resource Plan (IRRP)

  • Community engagement
  • Next steps
  • Discussion of long-term needs and community priorities

Presentation Outline

2

slide-3
SLIDE 3

3

IESO - Who We Are and What We Do

The Independent Electricity System Operator (IESO) works at the heart of Ontario's power system – ensuring there is enough power to meet the province's energy needs in real time while also planning and securing energy and its delivery for the future. It does this by:

  • Planning
  • Ensuring supply
  • Operating the grid
  • Engaging communities
  • Promoting conservation

The IESO and the former Ontario Power Authority (OPA) merged on January 1, 2015 under the name Independent Electricity System Operator

slide-4
SLIDE 4

Key Participants in Ontario’s Electricity Sector

4

Ontario Energy Board

Ontario Electricity Customers

Regulation Generation Distribution Transmission System Operation, Planning and Procurement

Hydro One, GLP, Five Nations and others LDCs, Hydro One Distribution and other distribution utilities OPG and other generators Ministry of Energy

slide-5
SLIDE 5

5

ELECTRICITY PLANNING IN NORTHWEST ONTARIO

slide-6
SLIDE 6

The Three Levels of Electricity Planning

slide-7
SLIDE 7

7

Background – Bulk System Planning

slide-8
SLIDE 8
  • A process for identifying and meeting local electricity needs; objective of

maintaining a safe and reliable electricity supply

  • It is the link between provincial bulk system planning (led by the IESO) and

local distribution system planning (led by LDCs)

  • Operates in the context of existing criteria and frameworks

– Applies the IESO’s reliability standards – Aligns with planning policies – Accounts for local interests

  • Integrated approach: looks at conservation, generation, wires and other

innovative solutions

  • A Working Group has been established to develop regional plans – for

Greenstone-Marathon this includes the IESO and Hydro One Networks Inc.

What is Regional Planning?

8

slide-9
SLIDE 9
  • Engagement meetings in Thunder

Bay in fall 2014 to kick-off scoping process for: – Thunder Bay – West of Thunder Bay – Greenstone-Marathon

  • Following a public comment period,

the final Scoping Report was posted in January 2015 and the IRRP process begun for the three planning areas

9

Background – Integrated Regional Resource Planning

slide-10
SLIDE 10

10

The IRRP Process

Municipalities and First Nations and Métis communities engaged at various points in the process Electricity Demand Forecast Electricity Needs & Timing Solution Options Near-Term Investments & Longer-term Roadmap

Process Outcomes

Data Gathering

Data includes:

  • Area electricity demand
  • Local community growth
  • Local economic

development

  • Electricity infrastructure

equipment

Technical Study

Assess system capability against planning standard:

  • Maintain sufficient supply to

meet future growth

  • Minimize customer

interruptions during power

  • utage

Options

Consider solutions that integrate the followings:

  • Conservation and

distributed generation

  • Local generation
  • Infrastructure expansion

Actions

Actions include:

  • Initiate regulatory

process for near-term projects

  • Monitor the growth and

update the plan for the long term

slide-11
SLIDE 11

11

GREENSTONE-MARATHON INTERIM IRRP (PRESENT-5 YEARS)

11

slide-12
SLIDE 12
  • An IRRP is being developed to provide recommendations to

municipalities, First Nation communities, Métis community councils, and industry stakeholders related to what the most economic and technically feasible electricity solutions are for the region

  • An Interim IRRP report has been developed with community input

to facilitate decision making related to electricity supply for near- term industrial and community developments in the area

  • The medium and long term plan will also be developed with

community input and informed by this LAC

Introduction to the Greenstone-Marathon IRRP

12

slide-13
SLIDE 13

13

Local Electricity System

slide-14
SLIDE 14
  • Mining development
  • Gas to oil pipeline conversion project
  • Recovery of forestry industry
  • Growth in communities

14

Drivers

slide-15
SLIDE 15
  • Greenstone sub-system:

– Industrial customers drive the need for additional capacity requirements in the near term

  • North Shore sub-system:

– Existing system expected to be adequate to supply all forecasted demand scenarios (see Appendix A)

  • Marathon Area sub-system:

– Existing system expected to be adequate to supply all forecasted demand scenarios (see Appendix B) – Confirmed by System Impact Assessment for Marathon PGM- Cu project

15

Near-term (present-5 years) Needs

slide-16
SLIDE 16

Scenario A

  • LDC demand growth

(including two sawmill re- starts) from existing stations

  • No large industrial

projects materialize Scenario B

  • LDC demand growth

(including two sawmill re- starts) from existing stations

  • Geraldton area mining

project:

  • phase 1 mine (2018)
  • phase 2 mine (2020)

Scenario C

  • LDC demand growth

(including two sawmill re- starts) from existing stations

  • Geraldton area mining

project:

  • phase 1 mine (2018)
  • phase 2 mine (2020)
  • Pipeline conversion

project:

  • 4 oil pumping

stations (2020)

16

Near-term (present-5 years) Needs: Greenstone Subsystem Forecast Scenarios

The Greenstone-Marathon IRRP working group does not consider these forecast scenarios to be of greater or lesser likelihood.

slide-17
SLIDE 17

17

Near-term (present-5 years) Needs: Greenstone Sub-system

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 2015 2016 2017 2018 2019 2020 Demand [MW] Year

Greenstone Sub-system Forecast Scenarios

Scenario C Scenario B Scenario A Load Meeting Capability

Scenario A: Existing System is sufficient Scenario B: approx. 30 MW incremental LMC required Scenario C: approx. 90 MW incremental LMC required

LMC: Load Meeting Capability

slide-18
SLIDE 18

Greenstone-Marathon IRRP: Engagements prior to developing near-term plan

18

Date Engagement October 2014 Series of engagement meetings in Thunder Bay January 2015 Posting of Scoping Process Outcome Report and Terms of Reference April 2015 Municipal meetings in Marathon and Geraldton May 2015 First Nation meetings

slide-19
SLIDE 19

Scenario B – Alternatives Analysis

Alternative NPV Cost ($ millions) Option B1

1) Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) 2) Install customer-generation (2x10 MW) at customer mine site

55 Option B2

1) Customer self-generation (off-grid)

200 Option B3

1) Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) 2) Replace existing line with higher capacity line

40

19

Notes:

  • 1. Scenario A does not require the development of alternatives because the existing system is

capable of supplying growth while meeting all planning criteria

  • 2. Maps of alternatives are included in Appendix C
slide-20
SLIDE 20

Scenario C – Alternatives Analysis

Alternative NPV Cost ($ millions) Option C1

1) Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) 2) New 230 kV Line to Longlac 3) Off-grid gas generation for two pumping stations

170 Option C2

1) Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) 2) New 230 kV Line to Longlac 3) New 115 kV line Manitouwadge-Longlac

165 Option C3

1) Grid-connected gas-fired generating plant (6x18 MW) 2) New 115 kV line Manitouwadge-Longlac

350 Option C4

1) Customer self-generation (off-grid) at mine 2) Customer self-generation (off-grid) at four pumping stations

510

20

Notes:

  • 1. Maps of alternatives are included in Appendix C
slide-21
SLIDE 21

Alternative Analysis: Observations

  • All economic alternatives have a common first stage:

– Install reactive compensation (+40 MVar synchronous condenser or STATCOM) at the Geraldton mine site to accommodate phase 1 of the mine.

  • Grid-connected alternatives are more cost-effective than off-grid

alternatives

  • Large grid-connected generation is more costly than transmission

reinforcement

  • A new 230 kV transmission supply is the most cost-effective way to

supply the Geraldton mine and the pipeline conversion project for 2020 (Scenario C)

21

slide-22
SLIDE 22

Recommended Near-term Plan

Scenario Recommendation Stage 1 (for 2018) Stage 2 (for 2020) Scenario A No new facilities required Scenario B Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) Install customer-generation (2x10 MW) at customer mine site or replace existing line with higher capacity line Scenario C Install new 230 kV line to Longlac, new 115 kV line Manitouwadge-Longlac, and required transformation, switching, and compensation devices

22

slide-23
SLIDE 23

23

Recommended Near-term Plan: Stage 1

Scenario B and C (i.e. common to both)

  • Geraldton mine phase 1 materializes

Recommendation

  • Install +40 MVar reactive compensation

(either synchronous condenser or STATCOM) at mine site In-service date

  • 2018

Net present value cost

  • $5 million

Reactive Compensation

slide-24
SLIDE 24

24

OR

New 115 kV line New 230 kV line

Recommended Near-term Plan: Stage 2a

Scenario C

  • In addition to the Geraldton mine,

pipeline conversion project proceeds according to public 2020 date Recommendation

  • Install new 230 kV transmission supply
  • Install new 115 kV connection line

In-service date

  • 2020

Net present value cost

  • $160 million

East of Nipigon Route West of Marathon Route

slide-25
SLIDE 25

25

Recommended Near-term Plan: Stage 2b

Scenario B

  • Geraldton mine phase 2 proceeds, but

pipeline conversion project does not proceed by public 2020 date Recommendation

  • Install new customer generation in the

form of two 10 MW natural gas gensets at the Geraldton mine site, or replace line sections of A4L In-service date

  • 2020

Net present value cost

  • $35 M – Line Section Replacement
  • $50 M – Customer Generation

New gas DG Replacement 115 kV line

OR

slide-26
SLIDE 26

Implementation Considerations

  • The plan elements are driven by industrial customer development and

therefore, in accordance with the Ontario Energy Board’s Transmission System Code, benefitting customers are responsible for the related costs

  • Lead-times can be accommodated, but new transmission would require

urgent action by the benefiting customers for 2020 in-service, based on typical lead times

  • The IESO is available to provide support for any regulatory and / or

environmental approvals

  • The IESO does not have a mandate to procure facilities for individual

customers

26

slide-27
SLIDE 27

Greenstone-Marathon IRRP: Engagements for Mid to Long Term Planning

27

Date Engagement October 2014 Series of engagement meetings in Thunder Bay January 2015 Posting of Scoping Process Outcome Report and Terms of Reference April 2015 Municipal meetings in Marathon and Geraldton May 2015 First Nation meetings May 2015 Advertisements for the establishment of a Local Advisory Committee (LAC) June 2015 Released Near-Term Plan and Inaugural meetings of the Local Advisory Committees

slide-28
SLIDE 28

Next Steps

  • Development of medium and long term plan with input from the

Local Advisory Committees

– Discussion of medium to long-term needs – Discussion of community priorities – Engagement of broader community

  • Release 20-year Greenstone-Marathon IRRP in first half of 2016

28

slide-29
SLIDE 29
  • What key electricity demand drivers do you see for the 5

to 10 year period and beyond?

  • Are there additional local priorities that need to be

considered in the development of the longer-term plan?

  • How can the broader community be engaged in this

discussion?

Discussion of Long-term Needs and Community Priorities

29

slide-30
SLIDE 30

30

QUESTIONS

slide-31
SLIDE 31

31

APPENDICES

slide-32
SLIDE 32

32

Appendix A: North Shore Subsystem Forecast

slide-33
SLIDE 33

33

Appendix B: Marathon Area Subsystem Forecast

slide-34
SLIDE 34

34

APPENDIX C

34

slide-35
SLIDE 35

Scenario B – Alternatives Analysis

  • Option B1

– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install 2x10 MW gas-fired gensets at the mine site coincident with phase 2 of the mine (2020)

  • Option B2

– Install 6x9.5 MW off-grid gas generation plant at the Geraldton mine site (2018)

  • Option B3

– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Replace 117 km of existing circuit A4L from Nipigon to Longlac with higher capacity conductor coincident with phase 2 of the mine (2020)

35

slide-36
SLIDE 36

Scenario B – Alternatives Analysis

Alternative NPV Cost ($ millions) Option B1

1) +40 MVar synchronous condenser or STATCOM 2) 2x10 MW customer-generation at mine

55 Option B2

1) 6x9.5 MW off-grid gas generation plant at mine

200 Option B3

1) +40 MVar synchronous condenser or STATCOM 2) 117 km replacement of circuit A4L

40

36

Maps of alternatives are included in Appendix C

slide-37
SLIDE 37

Scenario B – Alternative Analysis: Option B1

– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install 2x10 MW gas-fired gensets at the mine site coincident with phase 2 of the mine (2020)

37 Reactive Compensation (2018) New gas DG (2020)

slide-38
SLIDE 38

Scenario B – Alternative Analysis: Option B2

– Install 6x9.5 MW off-grid gas generation plant at the Geraldton mine site (2018)

38 Off-grid Gas Generation (2018)

slide-39
SLIDE 39

Scenario B – Alternative Analysis: Option B2

39 Reactive Compensation (2018) A4L Replacement (2020)

– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Replace 117 km of existing circuit A4L from Nipigon to Longlac with higher capacity conductor coincident with phase 2 of the mine (2020)

slide-40
SLIDE 40

Scenario C – Alternatives Analysis

  • Option C1

– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install a new 230 kV transmission supply from the East-West Tie to Longlac TS coincident with phase 2 of the mine, and the pipeline conversion project (2020) – Install two off-grid gas generating plants to supply two remote pumping stations from the pipeline conversion project (2020)

  • Option C2

– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install a new 230 kV transmission supply from the East-West Tie to Longlac TS coincident with phase 2 of the mine, and the pipeline conversion project (2020) – Install a new 115 kV transmission connection line from Manitouwadge to Longlac TS to supply two remote pumping stations from the pipeline conversion project (2020)

40

slide-41
SLIDE 41

Scenario C – Alternatives Analysis

  • Option C3

– Install a grid-connected generation plant at near Longlac with a dependable capacity (i.e. considering unit outages and de-ratings) of 80 MW in 2018 – Install a new 115 kV transmission connection line from Manitouwadge to Longlac TS to supply two remote pumping stations from the pipeline conversion project (2020)

  • Option C4

– Install 6x9.5 MW off-grid gas generation plant at the Geraldton mine (2018) – Install four off-grid gas generation plants totalling approximately 80 MW at each

  • f the pumping stations from the pipeline conversion project (2020)

41

slide-42
SLIDE 42

Scenario C – Alternatives Analysis

Alternative NPV Cost ($ millions) Option C1

1) +40 MVar synchronous condenser or STATCOM 2) New 230 kV Line to Longlac 3) Off-grid gas generation for two pumping stations

1701 Option C2

1) +40 MVar synchronous condenser or STATCOM 2) New 230 kV Line to Longlac 3) New 115 kV line Manitouwadge-Longlac

165 Option C3

1) 6x18 MW grid-connected gas-fired generating plant 2) New 115 kV line Manitouwadge-Longlac

350 Option C4

1) 6x9.5 MW off-grid gas generation plant at mine 2) 2x9.5 MW off-grid gas generation plants at four pumping stations

510

42

1. Not fully secure if 230 kV line is lost

Maps of alternatives are included in Appendix C

slide-43
SLIDE 43

Scenario C – Alternative Analysis: Option C1

– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1

  • f the mine (2018)

– Install a new 230 kV transmission supply from the East-West Tie to Longlac TS coincident with phase 2 of the mine, and the pipeline conversion project (2020) – Install two off-grid gas generating plants to supply two remote pumping stations from the pipeline conversion project (2020)

43

OR

Reactive Compensation (2018) New off-grid gas generation (2020) East of Nipigon Route West of Marathon Route New 230 kV line (2020)

slide-44
SLIDE 44

Scenario C – Alternative Analysis: Option C2

44

OR

Reactive Compensation (2018) New 230 kV line (2020) New 115 kV line (2020) East of Nipigon Route West of Marathon Route

– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install a new 230 kV transmission supply from the East-West Tie to Longlac TS coincident with phase 2 of the mine, and the pipeline conversion project (2020) – Install a new 115 kV transmission connection line from Manitouwadge to Longlac TS to supply two remote pumping stations from the pipeline conversion project (2020)

slide-45
SLIDE 45

Scenario C – Alternative Analysis: Option C3

45 New 115 kV line (2020) West of Marathon Route

– Install a new grid-connected gas-fired generating plant with a dependable capacity of 80 MW (2018). Dependable capacity for gas generation considers a single unit outage. For costing purposes, a 6x18 MW facility was assumed. – Install a new 115 kV transmission connection line from Manitouwadge to Longlac TS to supply two remote pumping stations from the pipeline conversion project (2020)

New grid-connected gas generation

slide-46
SLIDE 46

Scenario C – Alternative Analysis: Option C4

– Install 6x9.5 MW off-grid gas generation plant at the Geraldton mine site (2018) – Install four off-grid gas generating plants to supply the pumping stations from the pipeline conversion project (2020)

46 New off-grid gas generation (2020) Off-grid Gas Generation (2018) New off-grid gas generation (2020)