Integrated Regional Resource Plan Inaugural Local Advisory Committee - - PowerPoint PPT Presentation
Integrated Regional Resource Plan Inaugural Local Advisory Committee - - PowerPoint PPT Presentation
GREENSTONE-MARATHON Integrated Regional Resource Plan Inaugural Local Advisory Committee Meeting June 29, 2015 Presentation Outline Introduction to the Ontario Electricity Sector Electricity planning in Northwestern Ontario Summary
- Introduction to the Ontario Electricity Sector
- Electricity planning in Northwestern Ontario
- Summary of findings from the Greenstone-Marathon Integrated
Regional Resource Plan (IRRP)
- Community engagement
- Next steps
- Discussion of long-term needs and community priorities
Presentation Outline
2
3
IESO - Who We Are and What We Do
The Independent Electricity System Operator (IESO) works at the heart of Ontario's power system – ensuring there is enough power to meet the province's energy needs in real time while also planning and securing energy and its delivery for the future. It does this by:
- Planning
- Ensuring supply
- Operating the grid
- Engaging communities
- Promoting conservation
The IESO and the former Ontario Power Authority (OPA) merged on January 1, 2015 under the name Independent Electricity System Operator
Key Participants in Ontario’s Electricity Sector
4
Ontario Energy Board
Ontario Electricity Customers
Regulation Generation Distribution Transmission System Operation, Planning and Procurement
Hydro One, GLP, Five Nations and others LDCs, Hydro One Distribution and other distribution utilities OPG and other generators Ministry of Energy
5
ELECTRICITY PLANNING IN NORTHWEST ONTARIO
The Three Levels of Electricity Planning
7
Background – Bulk System Planning
- A process for identifying and meeting local electricity needs; objective of
maintaining a safe and reliable electricity supply
- It is the link between provincial bulk system planning (led by the IESO) and
local distribution system planning (led by LDCs)
- Operates in the context of existing criteria and frameworks
– Applies the IESO’s reliability standards – Aligns with planning policies – Accounts for local interests
- Integrated approach: looks at conservation, generation, wires and other
innovative solutions
- A Working Group has been established to develop regional plans – for
Greenstone-Marathon this includes the IESO and Hydro One Networks Inc.
What is Regional Planning?
8
- Engagement meetings in Thunder
Bay in fall 2014 to kick-off scoping process for: – Thunder Bay – West of Thunder Bay – Greenstone-Marathon
- Following a public comment period,
the final Scoping Report was posted in January 2015 and the IRRP process begun for the three planning areas
9
Background – Integrated Regional Resource Planning
10
The IRRP Process
Municipalities and First Nations and Métis communities engaged at various points in the process Electricity Demand Forecast Electricity Needs & Timing Solution Options Near-Term Investments & Longer-term Roadmap
Process Outcomes
Data Gathering
Data includes:
- Area electricity demand
- Local community growth
- Local economic
development
- Electricity infrastructure
equipment
Technical Study
Assess system capability against planning standard:
- Maintain sufficient supply to
meet future growth
- Minimize customer
interruptions during power
- utage
Options
Consider solutions that integrate the followings:
- Conservation and
distributed generation
- Local generation
- Infrastructure expansion
Actions
Actions include:
- Initiate regulatory
process for near-term projects
- Monitor the growth and
update the plan for the long term
11
GREENSTONE-MARATHON INTERIM IRRP (PRESENT-5 YEARS)
11
- An IRRP is being developed to provide recommendations to
municipalities, First Nation communities, Métis community councils, and industry stakeholders related to what the most economic and technically feasible electricity solutions are for the region
- An Interim IRRP report has been developed with community input
to facilitate decision making related to electricity supply for near- term industrial and community developments in the area
- The medium and long term plan will also be developed with
community input and informed by this LAC
Introduction to the Greenstone-Marathon IRRP
12
13
Local Electricity System
- Mining development
- Gas to oil pipeline conversion project
- Recovery of forestry industry
- Growth in communities
14
Drivers
- Greenstone sub-system:
– Industrial customers drive the need for additional capacity requirements in the near term
- North Shore sub-system:
– Existing system expected to be adequate to supply all forecasted demand scenarios (see Appendix A)
- Marathon Area sub-system:
– Existing system expected to be adequate to supply all forecasted demand scenarios (see Appendix B) – Confirmed by System Impact Assessment for Marathon PGM- Cu project
15
Near-term (present-5 years) Needs
Scenario A
- LDC demand growth
(including two sawmill re- starts) from existing stations
- No large industrial
projects materialize Scenario B
- LDC demand growth
(including two sawmill re- starts) from existing stations
- Geraldton area mining
project:
- phase 1 mine (2018)
- phase 2 mine (2020)
Scenario C
- LDC demand growth
(including two sawmill re- starts) from existing stations
- Geraldton area mining
project:
- phase 1 mine (2018)
- phase 2 mine (2020)
- Pipeline conversion
project:
- 4 oil pumping
stations (2020)
16
Near-term (present-5 years) Needs: Greenstone Subsystem Forecast Scenarios
The Greenstone-Marathon IRRP working group does not consider these forecast scenarios to be of greater or lesser likelihood.
17
Near-term (present-5 years) Needs: Greenstone Sub-system
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 2015 2016 2017 2018 2019 2020 Demand [MW] Year
Greenstone Sub-system Forecast Scenarios
Scenario C Scenario B Scenario A Load Meeting Capability
Scenario A: Existing System is sufficient Scenario B: approx. 30 MW incremental LMC required Scenario C: approx. 90 MW incremental LMC required
LMC: Load Meeting Capability
Greenstone-Marathon IRRP: Engagements prior to developing near-term plan
18
Date Engagement October 2014 Series of engagement meetings in Thunder Bay January 2015 Posting of Scoping Process Outcome Report and Terms of Reference April 2015 Municipal meetings in Marathon and Geraldton May 2015 First Nation meetings
Scenario B – Alternatives Analysis
Alternative NPV Cost ($ millions) Option B1
1) Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) 2) Install customer-generation (2x10 MW) at customer mine site
55 Option B2
1) Customer self-generation (off-grid)
200 Option B3
1) Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) 2) Replace existing line with higher capacity line
40
19
Notes:
- 1. Scenario A does not require the development of alternatives because the existing system is
capable of supplying growth while meeting all planning criteria
- 2. Maps of alternatives are included in Appendix C
Scenario C – Alternatives Analysis
Alternative NPV Cost ($ millions) Option C1
1) Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) 2) New 230 kV Line to Longlac 3) Off-grid gas generation for two pumping stations
170 Option C2
1) Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) 2) New 230 kV Line to Longlac 3) New 115 kV line Manitouwadge-Longlac
165 Option C3
1) Grid-connected gas-fired generating plant (6x18 MW) 2) New 115 kV line Manitouwadge-Longlac
350 Option C4
1) Customer self-generation (off-grid) at mine 2) Customer self-generation (off-grid) at four pumping stations
510
20
Notes:
- 1. Maps of alternatives are included in Appendix C
Alternative Analysis: Observations
- All economic alternatives have a common first stage:
– Install reactive compensation (+40 MVar synchronous condenser or STATCOM) at the Geraldton mine site to accommodate phase 1 of the mine.
- Grid-connected alternatives are more cost-effective than off-grid
alternatives
- Large grid-connected generation is more costly than transmission
reinforcement
- A new 230 kV transmission supply is the most cost-effective way to
supply the Geraldton mine and the pipeline conversion project for 2020 (Scenario C)
21
Recommended Near-term Plan
Scenario Recommendation Stage 1 (for 2018) Stage 2 (for 2020) Scenario A No new facilities required Scenario B Install power equipment to support service quality needs at customer mining site (reactive compensation device providing +40 MVar) Install customer-generation (2x10 MW) at customer mine site or replace existing line with higher capacity line Scenario C Install new 230 kV line to Longlac, new 115 kV line Manitouwadge-Longlac, and required transformation, switching, and compensation devices
22
23
Recommended Near-term Plan: Stage 1
Scenario B and C (i.e. common to both)
- Geraldton mine phase 1 materializes
Recommendation
- Install +40 MVar reactive compensation
(either synchronous condenser or STATCOM) at mine site In-service date
- 2018
Net present value cost
- $5 million
Reactive Compensation
24
OR
New 115 kV line New 230 kV line
Recommended Near-term Plan: Stage 2a
Scenario C
- In addition to the Geraldton mine,
pipeline conversion project proceeds according to public 2020 date Recommendation
- Install new 230 kV transmission supply
- Install new 115 kV connection line
In-service date
- 2020
Net present value cost
- $160 million
East of Nipigon Route West of Marathon Route
25
Recommended Near-term Plan: Stage 2b
Scenario B
- Geraldton mine phase 2 proceeds, but
pipeline conversion project does not proceed by public 2020 date Recommendation
- Install new customer generation in the
form of two 10 MW natural gas gensets at the Geraldton mine site, or replace line sections of A4L In-service date
- 2020
Net present value cost
- $35 M – Line Section Replacement
- $50 M – Customer Generation
New gas DG Replacement 115 kV line
OR
Implementation Considerations
- The plan elements are driven by industrial customer development and
therefore, in accordance with the Ontario Energy Board’s Transmission System Code, benefitting customers are responsible for the related costs
- Lead-times can be accommodated, but new transmission would require
urgent action by the benefiting customers for 2020 in-service, based on typical lead times
- The IESO is available to provide support for any regulatory and / or
environmental approvals
- The IESO does not have a mandate to procure facilities for individual
customers
26
Greenstone-Marathon IRRP: Engagements for Mid to Long Term Planning
27
Date Engagement October 2014 Series of engagement meetings in Thunder Bay January 2015 Posting of Scoping Process Outcome Report and Terms of Reference April 2015 Municipal meetings in Marathon and Geraldton May 2015 First Nation meetings May 2015 Advertisements for the establishment of a Local Advisory Committee (LAC) June 2015 Released Near-Term Plan and Inaugural meetings of the Local Advisory Committees
Next Steps
- Development of medium and long term plan with input from the
Local Advisory Committees
– Discussion of medium to long-term needs – Discussion of community priorities – Engagement of broader community
- Release 20-year Greenstone-Marathon IRRP in first half of 2016
28
- What key electricity demand drivers do you see for the 5
to 10 year period and beyond?
- Are there additional local priorities that need to be
considered in the development of the longer-term plan?
- How can the broader community be engaged in this
discussion?
Discussion of Long-term Needs and Community Priorities
29
30
QUESTIONS
31
APPENDICES
32
Appendix A: North Shore Subsystem Forecast
33
Appendix B: Marathon Area Subsystem Forecast
34
APPENDIX C
34
Scenario B – Alternatives Analysis
- Option B1
– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install 2x10 MW gas-fired gensets at the mine site coincident with phase 2 of the mine (2020)
- Option B2
– Install 6x9.5 MW off-grid gas generation plant at the Geraldton mine site (2018)
- Option B3
– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Replace 117 km of existing circuit A4L from Nipigon to Longlac with higher capacity conductor coincident with phase 2 of the mine (2020)
35
Scenario B – Alternatives Analysis
Alternative NPV Cost ($ millions) Option B1
1) +40 MVar synchronous condenser or STATCOM 2) 2x10 MW customer-generation at mine
55 Option B2
1) 6x9.5 MW off-grid gas generation plant at mine
200 Option B3
1) +40 MVar synchronous condenser or STATCOM 2) 117 km replacement of circuit A4L
40
36
Maps of alternatives are included in Appendix C
Scenario B – Alternative Analysis: Option B1
– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install 2x10 MW gas-fired gensets at the mine site coincident with phase 2 of the mine (2020)
37 Reactive Compensation (2018) New gas DG (2020)
Scenario B – Alternative Analysis: Option B2
– Install 6x9.5 MW off-grid gas generation plant at the Geraldton mine site (2018)
38 Off-grid Gas Generation (2018)
Scenario B – Alternative Analysis: Option B2
39 Reactive Compensation (2018) A4L Replacement (2020)
– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Replace 117 km of existing circuit A4L from Nipigon to Longlac with higher capacity conductor coincident with phase 2 of the mine (2020)
Scenario C – Alternatives Analysis
- Option C1
– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install a new 230 kV transmission supply from the East-West Tie to Longlac TS coincident with phase 2 of the mine, and the pipeline conversion project (2020) – Install two off-grid gas generating plants to supply two remote pumping stations from the pipeline conversion project (2020)
- Option C2
– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install a new 230 kV transmission supply from the East-West Tie to Longlac TS coincident with phase 2 of the mine, and the pipeline conversion project (2020) – Install a new 115 kV transmission connection line from Manitouwadge to Longlac TS to supply two remote pumping stations from the pipeline conversion project (2020)
40
Scenario C – Alternatives Analysis
- Option C3
– Install a grid-connected generation plant at near Longlac with a dependable capacity (i.e. considering unit outages and de-ratings) of 80 MW in 2018 – Install a new 115 kV transmission connection line from Manitouwadge to Longlac TS to supply two remote pumping stations from the pipeline conversion project (2020)
- Option C4
– Install 6x9.5 MW off-grid gas generation plant at the Geraldton mine (2018) – Install four off-grid gas generation plants totalling approximately 80 MW at each
- f the pumping stations from the pipeline conversion project (2020)
41
Scenario C – Alternatives Analysis
Alternative NPV Cost ($ millions) Option C1
1) +40 MVar synchronous condenser or STATCOM 2) New 230 kV Line to Longlac 3) Off-grid gas generation for two pumping stations
1701 Option C2
1) +40 MVar synchronous condenser or STATCOM 2) New 230 kV Line to Longlac 3) New 115 kV line Manitouwadge-Longlac
165 Option C3
1) 6x18 MW grid-connected gas-fired generating plant 2) New 115 kV line Manitouwadge-Longlac
350 Option C4
1) 6x9.5 MW off-grid gas generation plant at mine 2) 2x9.5 MW off-grid gas generation plants at four pumping stations
510
42
1. Not fully secure if 230 kV line is lost
Maps of alternatives are included in Appendix C
Scenario C – Alternative Analysis: Option C1
– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1
- f the mine (2018)
– Install a new 230 kV transmission supply from the East-West Tie to Longlac TS coincident with phase 2 of the mine, and the pipeline conversion project (2020) – Install two off-grid gas generating plants to supply two remote pumping stations from the pipeline conversion project (2020)
43
OR
Reactive Compensation (2018) New off-grid gas generation (2020) East of Nipigon Route West of Marathon Route New 230 kV line (2020)
Scenario C – Alternative Analysis: Option C2
44
OR
Reactive Compensation (2018) New 230 kV line (2020) New 115 kV line (2020) East of Nipigon Route West of Marathon Route
– Install +40 Mvar of reactive compensation in the form of either a synchronous condenser or a STATCOM at the Geraldton mine site coincident with phase 1 of the mine (2018) – Install a new 230 kV transmission supply from the East-West Tie to Longlac TS coincident with phase 2 of the mine, and the pipeline conversion project (2020) – Install a new 115 kV transmission connection line from Manitouwadge to Longlac TS to supply two remote pumping stations from the pipeline conversion project (2020)
Scenario C – Alternative Analysis: Option C3
45 New 115 kV line (2020) West of Marathon Route
– Install a new grid-connected gas-fired generating plant with a dependable capacity of 80 MW (2018). Dependable capacity for gas generation considers a single unit outage. For costing purposes, a 6x18 MW facility was assumed. – Install a new 115 kV transmission connection line from Manitouwadge to Longlac TS to supply two remote pumping stations from the pipeline conversion project (2020)
New grid-connected gas generation
Scenario C – Alternative Analysis: Option C4
– Install 6x9.5 MW off-grid gas generation plant at the Geraldton mine site (2018) – Install four off-grid gas generating plants to supply the pumping stations from the pipeline conversion project (2020)
46 New off-grid gas generation (2020) Off-grid Gas Generation (2018) New off-grid gas generation (2020)