2018 INTEGRATED RESOURCE PLAN PROJECT UPDATE APRIL 10, 2018 - - PowerPoint PPT Presentation

2018 integrated resource plan
SMART_READER_LITE
LIVE PREVIEW

2018 INTEGRATED RESOURCE PLAN PROJECT UPDATE APRIL 10, 2018 - - PowerPoint PPT Presentation

2018 INTEGRATED RESOURCE PLAN PROJECT UPDATE APRIL 10, 2018 Commission Presentation August 9, 2016 Presentation Outline 2 What is an Integrated Resource Plan (IRP)? Key Takeaways from 2016 IRP Preview 2018 IRP Information 2018


slide-1
SLIDE 1

2018 INTEGRATED RESOURCE PLAN

PROJECT UPDATE

APRIL 10, 2018

Commission Presentation August 9, 2016

slide-2
SLIDE 2

 What is an Integrated Resource Plan (IRP)?  Key Takeaways from 2016 IRP  Preview 2018 IRP Information  2018 IRP Considerations  Summary

Presentation Outline

2

slide-3
SLIDE 3

What is an IRP?

3

slide-4
SLIDE 4

What is an IRP?

 Washington State RCW 19.280 mandate  10 year strategy to meet energy, capacity, and renewables  Evaluates generation resources, conservation and Renewable

Energy Credits (REC)

 Provides strategies for reliable, low cost electricity at

reasonable risk

 Creates action plan over two to four years

4

slide-5
SLIDE 5

IRP Inputs/ Modeling

5

slide-6
SLIDE 6

Key Takeaways from 2016 IRP

6

slide-7
SLIDE 7

Key Takeaways From 2016 IRP

 District long on resources with seasonal capacity deficit  District relying on market  Energy needs  Capacity needs  Renewable Energy Credits (REC) needs  Regional summer capacity constraints growing post 2019

 PNUCC Northwest Regional Forecast  Power Council Resources Adequacy Studies  BPA White Book (2015 Pacific NW Loads & Resources Study)

 Regional uncertainty of future legislation

7

slide-8
SLIDE 8

Preview 2018 IRP Information

8

slide-9
SLIDE 9

2018 IRP Project Charter

9

slide-10
SLIDE 10

2018 Assumptions & Modeling

Carbon Assumption Load Growth Assumption Low Natural Gas Price Modeling Stochastic Modeling

10

slide-11
SLIDE 11

25 50 75 100 125 150 175 200 225 250 275 300 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 aMW Block Critical Slice Renewables Market Frederickson Resource Requirement*

Block Slice

Renewables

Frederickson

Market

Load/Resource Balance – DRAFT

Annual – Critical Water

11

* Retail Load Forecast plus distribution & transmission losses

slide-12
SLIDE 12

25 50 75 100 125 150 175 200 225 250 275 300 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 aMW Block Critical Slice Average Slice Adder Renewables Frederickson Resource Requirement*

Renewables

Average Water Slice Adder

Block Slice

Frederickson

Load/Resource Balance – DRAFT

Annual – Average Water

12

* Retail Load Forecast plus distribution & transmission losses

slide-13
SLIDE 13
  • 50

100 150 200 250 300 350 January February March April May June July August September October November December aMW Block Critical Slice Average Slice Renewables Frederickson 2018 Resource Requirement

Block/Slice Generation observed over the last 3 years Frederickson available as energy call option through August 2022

Rely on Frederickson & Market to meet load Average Slice needed to serve load Slice surplus sold to market

2018 Monthly Forecasted Loads

Block and Critical/Average Slice over time

13

slide-14
SLIDE 14

50 100 150 200 250 300 350 400 450 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MWh Hour Ending

Load/Resource Balance (2015 Peak Day)

Block To Load Slice To Load Nine Canyon Wind - To Load White Creek - To Load Packwood - To Load Fredrickson - To Load District Market Purchases Actual Load

Temperature Observed1: 105 F

1 – As observed by the Hanford Meteorological Station

Example of Hourly Market Purchases

How hourly loads are met on a extreme hot summer day

14

slide-15
SLIDE 15

Capacity Deficits

15

Without Frederickson With Frederickson

slide-16
SLIDE 16

2018 IRP Considerations

16

slide-17
SLIDE 17

2018 IRP Considerations

 Energy & Capacity Uncertainties  Resource Adequacy Studies (PNUCC, NWPCC & BPA)  Market availability? Who and when will build?  Frederickson CT contract retires in 2022  Legislation Uncertainty

 EIA requirements  Carbon Policy

 Customer Preferences Changing?

 Customer Green Rate options

 BPA Post 2028

17

slide-18
SLIDE 18

Summary

 Key Draft Takeaways

 Regional seasonal capacity constraints growing  Winter constrained  Summer constraints growing  District continues to be annually long on resources  Critical water- short after 2022  Frederickson expires in 2022  Average water- long thru 2028  District seasonal deficits continue to be met by RMC hedging

 2018 Considerations/Uncertainties

 Market, Legislation, Customer Preference, BPA 2028

 Commission updates throughout summer

 Adopt 2018 IRP by August 28th

18

slide-19
SLIDE 19

Questions

19