Integrated Resource Plan Integrated Resource Plan
Rick Haener September 4th, 2015
Integrated Resource Plan Integrated Resource Plan Rick Haener - - PowerPoint PPT Presentation
Integrated Resource Plan Integrated Resource Plan Rick Haener September 4th, 2015 Integrated Resource Plan (IRP) Public utilities first began preparing integrated resource plans (IRPs) in the early 1990s IRPs are Public Utility Commission
Rick Haener September 4th, 2015
early 1990s
utility expects to provide service to customers for the next 20 years y p p y
transmission options
P bli i l i k f h l i
Load Forecast
5% g o t pea
Transmission Projects
EPA’s Proposed 111(d) Rule ( )
compliance and coal retirement assumptions PURPA Contracts PURPA Contracts
North Valmy Generating Station North Valmy Generating Station
5500 5000 4500 3500 4000 3000 3500 2015 2020 2025 2030 2015 2020 2025 2030
Load 95 Percentile Annual Peak Forecast Resource Capacity
2009 2011 2013 2015 Projects MW Projects MW Projects MW Projects MW Hydro 60 137 62 141 65 148 68 154 Hydro 60 137 62 141 65 148 68 154 Cogen 5 37 5 37 5 37 4 31 Bi 7 26 11 37 11 49 10 29 Biomass 7 26 11 37 11 49 10 29 Solar 1 20 1 20 19 461 Wind 17 252 22 447 27 577 32 627 Total 89 452 101 682 109 831 133 1,302
1,302 MW
831 MW 1,302 MW
Portfolio P6(b)
by 2034
to agree on a depreciation date and eventual closure date with NV Energy, and g p gy, PUC approval of an accelerated depreciation schedule
Date Resource Installed Capacity Peak-Hour Capacity 2025 Boardman to Hemingway 500 MW transfer capacity Apr-Sep 200 MW transfer capacity Oct-Mar 500 MW 2025 Retire North Valmy (both units) (262 MW) (262 MW) 2030 Demand response 60 MW 60 MW 2030 Ice-based thermal energy storage 20 MW 20 MW 2031 Combined-cycle combustion turbine 300 MW 300 MW Total retired capacity (262 MW) Total added capacity 880 MW Net peak-hour capacity 618 MW
and regulatory filings
( ) f d d d f k d d megawatts (aMW) for energy demand and 126 MW for peak demand.
planning for CAA Section 111(d).
g g p
technology technology
up to approximately 4 MW up to app o ate y
technology gy
synchronize depreciation dates and determine if a date can be established to cease coal‐fired operations
units 1 and 2 at Jim Bridger in the 2017 IRP
Solar PV on Distribution Feeder Lines Install solar PV panels near the end of long distribution feeders to boost/regulate
Thermal Ice Storage Pilot Project (Ice Bears) Thermal Ice Storage Pilot Project (Ice Bears) Identify and work with a commercial customer to install thermal ice storage. The initial phase would involve identifying a customer, designing the system, and putting together a detailed cost estimate. The second phase would be to purchase and install th i t f ll d b d t ll ti f i d f ti t d t i th the equipment followed by data collection for a period of time to determine the effectiveness of the concept. Shoshone Falls Upgrade Project pg j The previously planned 59 MW expansion of the Shoshone Falls Hydroelectric Project has been scaled back to an upgrade of 1.7 to 4.0 MW. Construction is tentatively planned to commence in 2017.
Utility Scale Single Axis
2015 IRP Assumed Solar Capacity Factors
Month Utility Scale, Single Axis Tracking Residential, Fixed Tilt January 12% 7% February 19% 11% March 26% 16% April 32% 20% May 37% 23% June 41% 25% July 42% 26% August 39% 24% September 33% 20% October 25% 16% Octobe 5% 6% November 14% 9% December 11% 7% Annual Capacity Factor
27.5% 17.0%