HS2 Update
1
HS2 Update 1 Community engagement update Schools engagement - - PowerPoint PPT Presentation
HS2 Update 1 Community engagement update Schools engagement Rolling programme of activities for local schools Careers events at Maria Fidelis and Hampstead School to raise awareness of careers in construction STEAM activities at UCL
1
Schools engagement
awareness of careers in construction
Career pathways
engineering, town planning, IT, project management, town planning
Town Planning workshop at UCL
2
Piazza and towers demolition
use
complete to ground level
summer
Walkden, Wolfson, Ibis and Thistle demolition
complete
processing yard
St James’s Gardens
excavations is complete and tent structure removed
before exhumations continue
3
Power Signal Box (PSB)
Regent’s Park Estate
industry best practice
London
Stage of process
Number
Total number of properties in scheme
1400
Response received / interest shown
879
Surveys completed
860
Installed
350
not interfere with the cladding or fire safety systems
trickle vents. This will be used in conjunction with secondary glazing and anti- solar gain film
Ampthill
Independent Assessor (IA)
assessment tool that can be applied to certain property types known to be more susceptible to heat if residents apply for consideration
Adverse Effect Level), it was recognised they may not be aware of their classification under the E23 Policy, nor the existence of the Special Case procedure. A communications strategy is being developed to address this.
5
Sites for HS2 16” slip-lining works Re-lining sites working north to south. Works to commence after TWUL decommission main.
Water to share the effort of water main protection works
16” asset in the area of our works – reducing risk of bursts and impact on the community
Summer – dependent on pre-condition surveys and agreement to work within proximity to the Thames Water 16” asset
6
Site for TWUL 16” slip-lining works, TBC
Footway Closure – Pedestrians diverted to
Works are progressing on North Gower Street
Gower Street.
potential risk to road users and our workforce is managed
7
Zero carbon welfare units
welfare units, which is an advancement on traditional diesel power systems.
hydrogen power to eliminate local carbon emissions, therefore, zero carbon emissions, zero fuel and very quiet with no vibrations.
Stephenson Way to remove services from the Wolfson Site
ensure logistics routes and delivery/refuge access is maintained
8
mitigate noise generated from the works
Completed pipe installation works - 1.5km
Zoo car park Cumberland Market Robert Street Gloucester Gate Albany Street Redhill Street Osnaburgh Street Park Village East (PVE): 70m tunnel, two shafts fitted-out and connection made
Works remaining:
sewer for ongoing maintenance, to complete in March
stay in place and small worksites will be needed in Robert Street and Cumberland Market
the length of PVE and Augustus St. The main will not be removed but filled with grout.
March
New connection in PVE on the existing 42” water main.
10
West Ramp demolition underway Removal of platforms 17 & 18 roof Opening up of Piazza and mini- market Euston escalator upgrades Materials by rail ongoing environmental benefits Spring WCML passenger disruption campaign
Euston west ramp materials reused to reduce transportation effects 1st phase delivered so far:
Use of electrified and low carbon plant across Euston works is helping:
generators Since 2016 our movement of material by rail rather than road has:
Hydrogen fuel cell technology tower lights Electric vehicle
The construction noise assessment demonstrates that compared with the ES (as amended), no new residential receptors have been identified as eligible for NI or TRH. The noise model is based on a “worst case” scenario:
12
13
Test piling site layout Test ground anchor from track level (location and timing TBC) Test piling site layout
TBC
14
Track level 26m high approx.
(height of 10-storey building)
Piling rig bores hole 20-40m+ deep using quietest methods Crane lifts in steel cage to reinforce hole Concrete wagons arrive just in time* to pour wet concrete into bored holes Crane removes steel cage and leaves concrete to set *Concrete deliveries until 10pm
Varying street level
8m above track level
15
Walkden and Calumet
ground demolitions complete
Street
borough
April
investigations (exc. reinternments) complete
main works at RPE
May
structure demolition complete
demolished buildings in RPE complete
June
complete
adjacent to Hampstead Road Bridge
Cargo shed area
Hampstead Road site
July
diversion works
basement
August
installation at DB Cargo shed area
March
16
car park
to Hampstead Road
construction site starts (duration 3 months)
October
Park Village East (north)
DB Cargo shed area
November
Terrace Bridge and Hampstead Road
December
Village East (north)
January 2021
Road
February 2021
September