HS2 Update to ECRG May 11 2018 Rob Carr Topics Update on Early - - PowerPoint PPT Presentation
HS2 Update to ECRG May 11 2018 Rob Carr Topics Update on Early - - PowerPoint PPT Presentation
HS2 Update to ECRG May 11 2018 Rob Carr Topics Update on Early Works Progress to date in Euston (CSjv) Ongoing design development of the Euston Throat (SCS) confirmation of scheme Material by Rail progress to date Noise Insulation
Topics
Update on Early Works Progress to date in Euston (CSjv) Ongoing design development of the Euston Throat (SCS) – confirmation of scheme Material by Rail – progress to date Noise Insulation Early works Look-ahead
Page 2
CSjv Early works - Drummond St hoardings
Successful collaboration with the Drummond St traders Looking to repeat with Stephenson Way Group Potential for Euston Station hoardings being investigated with NR PVE wall hoarding received positive feedback from local resident Page 3
CSjv Early works - DB Cargo Shed demolitions
Page 4 Demolition started, restricted to core hours Scheduled to complete by October 2018 Community open days held 24 & 26 April, 12 people attended Visitor Comment: “Many thanks. I certainly appreciated the visit and the team's openness to answer
- ur questions in so far as they were able.
Please keep up this level of community engagement ...it is so important for those who are so heavily affected by all the various works in the Euston Approach cutting.”
Euston Sq. Gardens - proposed Hoardings
Page 5 Slight delay to hoarding covering installation – expected soon These are artist impressions of what it will look like
Euston Sq. Temporary Taxi rank
Limiting tree removal prioritised in design
- Additional 7 trees retained from Hb design.
- 10 New Trees to be planted
- 26 Trees in taxi rank scheme
Scheme redesigned to retain tree that was then incorporated into a traffic Island Root protection measures put in place to retain further trees
Page 6
St James’s Gardens
Page 7 Trial pits continue to reveal extremely well preserved coffins Site visits by Historic England, GLAAS, APABE and LBC Environmental Health Team
Gravestone Cataloguing and recording – St James’s Gardens
355 gravestones lifted to date Volunteers are assisting MOLA Headland in identifying and recording headstones
Page 8
Early works – Noise/pollution Mitigation trials
CSjv Hybrid/electrical plant trials at St James’s Gardens:
- 1.5 tonne excavator and tracked mini-dumper
- Reduced noise & pollution (& carbon footprint)
- Challenging suppliers to embrace new technology &
equipment to reduce impact on local environment Hydrogen powered lighting equipment trial at OOC:
- Quiet/no pollution - only emits water
- Automatically request refill when nearing empty
Page 9
London
Euston 42” water main diversion
Thames Water compound set up in Zoo car park Albany Street works northern entrance
- f Redhill St (Jan 2018 – early 2019)
Cumberland Market works (Jan 2018 – end Sept 2018) Over 40 trial holes and boreholes, environmental and ecological surveys
Page 10
Temporary Pop-Up Garden – Hampstead Road
Page 11
Ongoing Design Development-Euston Throat
Skasnska – Costain -Strabag (SCS) joint venture awarded ‘Euston Tunnels’ contract July 2017 The Contract covers Hampstead Road Bridge to Old Oak common Station box Design development based on extending tunnels south of Mornington Street Bridge, as previously presented Scheme design well underway, to complete by Autumn 2018: No HS2 planned bridge demolitions no AP03 large Dive-under at Park Village East Reduced demolitions in the throat Significant reduction in disruption at existing station Within the Hybrid Bill Limits of Deviation
Page 12
Euston Throat Design Development
Euston Cavern Euston Scissor Cut
Westside Retaining Wall
Hampstead Road Bridge extension Euston Cavern Shaft Euston Crossover Tunnels Euston Throat Zone 5 Euston Portal Granby Terrace Bridge extension
Page 13 Indicative layout of revised design (As at 15 May 2018)
Community Engagement event arrangements underway: Initial engagement on structure and landscape designs w/c 25 June 2018 Follow-up events on structure and landscape designs Autumn 2018
Euston Station design & LU Vent Shaft
May Jun Jul Aug Sep Oct Nov
London Underground (LU) vent shaft / sub-station Public engagement (23 May) HS2 Euston station design development
ECRG design development working group ECRG design development working group ECRG design development working group
Public engagement (Oct/Nov)
- Schedule 17 submissions:
- LU vent shaft - late summer 2018
- HS2 Euston station – spring 2019
Page 14
- Arup appointed as HS2 Euston Station Design Service Contractor February 2018
- Will develop the Schedule 17 planning application and detailed design
- Co-located with Euston Throat design team (SCS) and NR station design team
Indicative Timeline for Engagement – LU Vent shaft and Euston Station Design
SCS are working with HS2 to develop a Material by Rail (MbR) proposal 1.Have appointed experienced rail logistics team (Legge) with a proven track record in transporting materials by rail (MbR) 2.They are developing an MbR Strategy that covers the whole of HS2’s Area South 3.Will comply with the Undertakings and Assurances (included within all HS2 contracts)
Material by Rail (MbR) - background
Page 15
SCS has signed & submitted ‘FCTAC’ (Freight Customer Track Access Contract) to NR which will give them track access rights and ability to secure the train paths into Euston Market engagement days held with all of the freight operating companies (FOCs) Procurement process commenced in April SCS are working with Suppliers and NR :
a) To confirm options available to transport Excavated Material by Rail b) Confirmed 9 suitable and available deposition sites linked to a Railhead c) To identify options for transporting Tunnel segments and Bulk materials by Rail
MbR - Recent progress and Future plans (1)
Page 16
MbRTest train:
A test train was run on 2 May 2018 to ensure the network can cope with the train loads Test train consist of 2 class 66 locos and 15 fully loaded waggons Preliminary feedback: test runs were successful sectional running times Euston to Wembley can be achieved Formal report will be used to support planning
Next Phase:
- Up to 7 train paths a day potentially available
- Work with NR to book freight paths in 2019 – 2020 timetable
- Availability of Platform 17 to be confirmed
- Efficient waggon loading system to be designed
MbR - Recent progress and future plans (2)
Page 17
Noise Mitigation
SCS specialist acoustician on board early June Predictive noise assessments on scheme design due by autumn ’18 Noise insulation will be available for any additional eligible properties identified No change to requirement to meet Environmental Minimum Requirements and to mitigate as far as practicable to reduce impacts ‘Best Practicable Means’ mitigation measures could include: a. Hoarding heights maximised where required, above the COCP standard b. Developing designs/methods to maximise working within core hours c. Maximise vehicle movements during core hours, even for 24hr operations d. Adapted equipment developed with suppliers eg piling rig shrouds / curtains and auger cleaners e. Site compound layouts designed to reduce noise impacts Presentation for ECRG on construction phases will be developed over the summer
Page 18
Noise Insulation(NI) in Euston - Update
Status
- All NI contractors fully mobilised.
- Demolition works are proceeding
- Access granted via Landlord licence to:
- 830 Camden properties,
- 52 Goldsmith House properties (NI complete)
- 66 properties within Peabody Estates
(Richmond House, Tintern House)
- 48 properties at Silsoe House (29 requested NI-
15 installations completed) Exemplar Listed Building Consent Application received conditional approval on 19th March 2018.
Planned Actual
NI Scheme Letters (Interest) Sent 1336 1336 Resident showed interest in the scheme 1184 745 Resident accepted to book a survey 1184 477 Surveyed 477 380 Design complete and issued to resident 380 223 Manufacture complete 223 184 Installed 201 84 Page 19
Early works lookahead – key milestones
Open NTH welfare compound on Hampstead Road
- 4 June 2018
Commence Thistle Hotel soft strip
- 25 June 2018
Open pop-up garden at NTH compound on Hampstead Road
- 1 July 2018
Commence Ibis Hotel soft strip
- 16 July 2018
Commence internal demolition of UCL building and petrol station
- 30 July 2018
Complete trial trench excavations St. James’s Gardens
- 1 Aug 2018
Complete construction of archaeology tent in St. James’s Gardens
- 1 Oct 2018
Opening of Temporary taxi rank at Euston
- 30 Oct 2018
Page 20