Euston Community Representatives Group
- HS2 update
3 December 2019 For community use only Version One
Euston Community Representatives Group - HS2 update 3 December - - PowerPoint PPT Presentation
Euston Community Representatives Group - HS2 update 3 December 2019 For community use only Version One Local Area Engagement Plan Finalised and printed Post-election publication on hs2.org Next steps 2 Community Engagement update
3 December 2019 For community use only Version One
2
Regent’s Park Estate pop-up events
Local business opportunities
Schools engagement
which increased attendance
Funds updates
allotment; the Steel pan trust; Healthy Minds, Healthy Bods.
3
Towers, Walkden, Wolfson
buildings are in advanced stages
complete mid-2020.
area complete, works in late planning stages
Ibis, Thistle Demolitions
complete
the Ibis, the area is now a concrete processing yard
St James Gardens
archaeological excavations is complete and tent structure has been removed.
holes.
excavations to continue under Cardington Street as part of the utilities programme, and excavations up to the Thistle boundary wall.
be shielded from public view.
Hampstead Road (UCL)
early 2020. Regents Park Estate
underway using Kevlar curtain and dust suppression systems
is complete at Eskdale and Silverdale.
6
December
(beginning in western areas)
complete
January
Thornton House
Street utilities works commence
February
Terrace Bridge
(Regents Park Estate) demolition complete
basement
March
Walkden and Calumet
(Regents Park) demolition complete
April
complete
investigations (excluding reinternments) complete
May
demolition complete
London
Stage of Process
Number
Total number of properties in scheme
1400
Response received / interest shown
879
Surveys completed
860
Installed
350
An holistic system design is required for the Ampthill Estate high rise blocks, which does not interfere with the cladding or fire safety systems. A feasibility study was completed, which recommends a viable solution comprising an induct fan with plenum, which uses the existing ducting and trickle vents, secondary glazing and solar film. Procurement of the detailed design stage has commenced.
Ampthill
HS2’s Legal Counsel advised that the original stance on external secondary glazing still stands. If a resident chooses to seek permission for and install external secondary glazing at their own cost, HS2 will remove the offer / potential
designed, proposed and sought permission for) to eligible windows.
External Secondary Glazing Independent Assessor (IA)
assessment that could be applied to certain property types known to be more susceptible to heat if residents apply for consideration.
residents may experience an adverse effect in terms of noise, the level of impact does not warrant mitigation except in special cases. It was recognised that LOAEL residents may not be aware of their classification under the E23 Policy, or of the existence of the special case procedure therefore, we have recommended a ‘push’ communications strategy to inform LOAELs of the Special Case Procedure. 7
London
Robert St/Cumberland Market (160m remaining) – complete March 2020
working towards the junction of Redhill Street
Zoo car park & Park Village East - complete spring 2020
Parkway junction.
Gloucester Gate - complete
Redhill St – complete
Redhill Street is now complete
Albany St (25m remaining) – complete Dec 2019
is connecting in to Gloucester Gate
Over 1.2km of the 1.5km diversion completed, improving the resilience of Camden’s future water supply.
8
Left: Working around existing services in Redhill Street Right: Fit out of the zoo car park shaft underway
Osnaburgh St – complete
Sites for HS2 16” slip-lining works Re-lining sites working north to south. Works to commence after TWUL decommission main.
Water to share the effort of water main protection works.
area of our works before we start – reducing risk of bursts and impact on the community.
works with the completion of Thames repair works - we will not be starting any works on Eversholt Street until a date is confirmed in the new year.
9
Site for TWUL 16” slip-lining works, TBC
Footway Closure – Pedestrians diverted to opposite footpath
We’ve completed the maintenance staff delivery
HS2
We’re building a temporary wall between the station and platfrom 17 & 18 We’re continuing the construction of the new compactor yard to help recycle more waste
10
Work is underway to clear a retail unit for more concourse space by platforms 12-16
Network Rail current and planned works
to the balcony by April 20
station January/ February 20
tbc)
Site of work for the upcoming parcel deck demolition
Agenda item 4
AP03 Taxi Scheme:
the western side of Eversholt Street adjacent to the station
up facility in the site currently occupied by Royal Mail
Crescent AP03 Construction Compounds
compounds Post AP03 considerations
AP03 Scheme AP03 Scheme Construction compound
Overall there were greater concerns over the noise and disruption of the Eversholt St
Recent work
road safety considerations
further discussion planned
delay mitigations Timescales
Considerations for the recommendation of the East Gardens:
disruption to road network
AP03 design
provision
schools, business and community on Eversholt St
Next steps :