Euston Community Representatives Group

  • HS2 update

3 December 2019 For community use only Version One

slide-2
SLIDE 2

Local Area Engagement Plan

2

  • Finalised and printed
  • Post-election publication on hs2.org
  • Next steps
slide-3
SLIDE 3

Community Engagement update

Regent’s Park Estate pop-up events

  • 20 pop-up events in Regent’s Park Estate over 120 residents attending.
  • Reached new audiences, made new relationships
  • Enabled quick resolution of issues, positive feedback

Local business opportunities

  • Held business event for over 40 local businesses
  • Shared HS2 businesses opportunities and guidance on how to get involved.

Schools engagement

  • Gave Netley School space on our hoardings to promote their open days,

which increased attendance

  • Led a careers day for 120 Year 7 students at Maria Fidelis and a competition
  • n the local area

Funds updates

  • Camden Fund - £2.4m to 36 projects. Recent projects include, Regent’s Park

allotment; the Steel pan trust; Healthy Minds, Healthy Bods.

  • CEF/ BLEF - £450,000 to 7 Camden projects.

3

slide-4
SLIDE 4

Euston Works

Towers, Walkden, Wolfson

  • Structural demolition of all

buildings are in advanced stages

  • Demolitions are due to

complete mid-2020.

  • Design for opening of Piazza

area complete, works in late planning stages

Ibis, Thistle Demolitions

  • Demolitions substantially

complete

  • Following the demolition of

the Ibis, the area is now a concrete processing yard

St James Gardens

  • First section of

archaeological excavations is complete and tent structure has been removed.

  • Undertaken trial

holes.

  • Archaeological

excavations to continue under Cardington Street as part of the utilities programme, and excavations up to the Thistle boundary wall.

  • These works also to

be shielded from public view.

slide-5
SLIDE 5

Euston Approaches

Hampstead Road (UCL)

  • Demolition of the UCL building is complete.
  • Area now used as small logistical hub
  • We are awaiting NR vacation of the Power Signal box in

early 2020. Regents Park Estate

  • Demolition

underway using Kevlar curtain and dust suppression systems

  • Asbestos removal

is complete at Eskdale and Silverdale.

slide-6
SLIDE 6

6 Month Lookahead

6

December

  • Start of utility works in Euston area

(beginning in western areas)

  • Calumet super structure demolition

complete

  • 1 Euston Square demolition to 2nd floor

January

  • Start of works on 1st Floor slab of Grant

Thornton House

  • North Gower and Stephenson Way

Street utilities works commence

February

  • Completion of utilities works at Granby

Terrace Bridge

  • Start of Cardington Street exhumations
  • Old Tenants Hall and Granby House

(Regents Park Estate) demolition complete

  • Wolfson House demolished to

basement

March

  • Start of basement backfill at Wolfson,

Walkden and Calumet

  • Silverdale and Stalbridge House

(Regents Park) demolition complete

April

  • Euston power signal box soft strip

complete

  • St James Gardens exhumations and

investigations (excluding reinternments) complete

  • Euston Street utilities works begin

May

  • Walkden House super structure

demolition complete

slide-7
SLIDE 7

London

Stage of Process

Number

Total number of properties in scheme

1400

Response received / interest shown

879

Surveys completed

860

Installed

350

Noise Insulation

An holistic system design is required for the Ampthill Estate high rise blocks, which does not interfere with the cladding or fire safety systems. A feasibility study was completed, which recommends a viable solution comprising an induct fan with plenum, which uses the existing ducting and trickle vents, secondary glazing and solar film. Procurement of the detailed design stage has commenced.

Ampthill

HS2’s Legal Counsel advised that the original stance on external secondary glazing still stands. If a resident chooses to seek permission for and install external secondary glazing at their own cost, HS2 will remove the offer / potential

  • ffer of internal secondary glazing for the windows/doors in
  • question. We will still install any internal secondary glazing (that we have

designed, proposed and sought permission for) to eligible windows.

External Secondary Glazing Independent Assessor (IA)

  • We have commissioned the creation of a light touch desktop

assessment that could be applied to certain property types known to be more susceptible to heat if residents apply for consideration.

  • We produced a decision paper that found that whilst LOAEL

residents may experience an adverse effect in terms of noise, the level of impact does not warrant mitigation except in special cases. It was recognised that LOAEL residents may not be aware of their classification under the E23 Policy, or of the existence of the special case procedure therefore, we have recommended a ‘push’ communications strategy to inform LOAELs of the Special Case Procedure. 7

slide-8
SLIDE 8

London

42” water main diversion – progress

Robert St/Cumberland Market (160m remaining) – complete March 2020

  • The worksite is now past the Rydal Water car park
  • The second worksite in Cumberland Market is now

working towards the junction of Redhill Street

Zoo car park & Park Village East - complete spring 2020

  • 70m tunnel complete.
  • Shaft fit-out continues to progress.
  • The tunnel avoids the need of an extensive closure of the

Parkway junction.

Gloucester Gate - complete

  • The works in Gloucester Gate are complete

Redhill St – complete

  • The northern section of Cumberland Market and

Redhill Street is now complete

Albany St (25m remaining) – complete Dec 2019

  • The worksite at the northern extent of Albany Street

is connecting in to Gloucester Gate

Over 1.2km of the 1.5km diversion completed, improving the resilience of Camden’s future water supply.

8

Left: Working around existing services in Redhill Street Right: Fit out of the zoo car park shaft underway

Osnaburgh St – complete

  • The work in Osnaburgh Street is now complete
slide-9
SLIDE 9

Euston Utilities - Eversholt Street

Sites for HS2 16” slip-lining works Re-lining sites working north to south. Works to commence after TWUL decommission main.

  • HS2 are working closely with Thames

Water to share the effort of water main protection works.

  • HS2 will re-line the failing 16” asset in the

area of our works before we start – reducing risk of bursts and impact on the community.

  • We have aligned the start of the HS2

works with the completion of Thames repair works - we will not be starting any works on Eversholt Street until a date is confirmed in the new year.

9

Site for TWUL 16” slip-lining works, TBC

Footway Closure – Pedestrians diverted to opposite footpath

slide-10
SLIDE 10

Network Rail update Euston and West Coast main line – Winter 2019

We’ve completed the maintenance staff delivery

  • ffice build and transferred power signalling box to

HS2

We’re building a temporary wall between the station and platfrom 17 & 18 We’re continuing the construction of the new compactor yard to help recycle more waste

10

Work is underway to clear a retail unit for more concourse space by platforms 12-16

Network Rail current and planned works

  • Ongoing work to add better access

to the balcony by April 20

  • Installation of new gates at the

station January/ February 20

  • Demolition of the parcel deck (date

tbc)

Site of work for the upcoming parcel deck demolition

slide-11
SLIDE 11

Proposed new temporary taxi rank

Agenda item 4

slide-12
SLIDE 12

Hybrid Bill Design Recap

AP03 Taxi Scheme:

  • Taxi pick-up, set-down and ranking facility located on

the western side of Eversholt Street adjacent to the station

  • Turnaround facility provided to the north of the pick-

up facility in the site currently occupied by Royal Mail

  • Ranking on Eversholt Street and Drummond

Crescent AP03 Construction Compounds

  • East & West gardens to be used for construction

compounds Post AP03 considerations

  • Royal Mail Group site can’t be used
  • Network Rail bi-directional basement
  • Maria Fidelis school relocation

AP03 Scheme AP03 Scheme Construction compound

slide-13
SLIDE 13
  • Concerns about air quality
  • Request to reduce the number of ranking spaces
  • Avoid loss of green spaces and trees
  • Request to consider alternative locations
  • Concerns about noise and traffic disruption on Eversholt St
  • Impact on bus stops
  • Conflict with other road users (cyclists/ motorcycle users)
  • Consideration of impacts of private hire (eg Uber) pick up and drop off
  • Impact on businesses
  • Interaction with Thames Water sewer re-lining works on Eversholt St

Overall there were greater concerns over the noise and disruption of the Eversholt St

  • ption.

Feedback received on interim taxi rank options

slide-14
SLIDE 14

Recent work

  • Community Engagement –
  • Community Traffic Working Group,
  • HS2inCamden Commonplace website,
  • Drop-In session
  • Working with TfL, LBC, Network Rail identifying

road safety considerations

  • Taxi survey undertaken – analysis underway,

further discussion planned

  • Traffic modelling to inform best option and bus

delay mitigations Timescales

  • September 2020 – planned start
  • f taxi rank construction
  • March 2021 relocation

Interim taxi rank recommendation

slide-15
SLIDE 15

Considerations for the recommendation of the East Gardens:

  • A contained site allows for reduced impact and

disruption to road network

  • Area is designated as a construction compound in

AP03 design

  • Reduced conflict between users on Eversholt St
  • Positioned to avoid the larger, perimeter trees
  • New signalised pedestrian routes to be provided
  • Comparable taxi ranking spaces to original

provision

  • Accessible bays would be located away from

schools, business and community on Eversholt St

Interim taxi rank recommendation – East Gardens

Next steps :

  • Fix and develop access points – understanding impacts on buses, heritage and trees
  • Discuss taxi survey results to decide necessary footprint
  • Develop road junction & lane changes – considering wider traffic enforcement
Interim Solution prior to NR station works Interim Solution prior to NR station works