hs2 update
play

HS2 update 6 March 2019 Topic Presenter Material by Rail Rob - PowerPoint PPT Presentation

HS2 update 6 March 2019 Topic Presenter Material by Rail Rob Carr Enabling Works and Noise Insulation Lisa Hogben/ Timothy Burr Utilities (incl. 42 inch water main) James Leeming Euston Approach Colin Thomas Network Rail Tom Duckmanton


  1. HS2 update 6 March 2019

  2. Topic Presenter Material by Rail Rob Carr Enabling Works and Noise Insulation Lisa Hogben/ Timothy Burr Utilities (incl. 42 inch water main) James Leeming Euston Approach Colin Thomas Network Rail Tom Duckmanton Euston Station design development Rob Carr

  3. Material by Rail Rob Carr – Programme Director

  4. Progress made to enable Material by Rail at Euston HS2 Ltd has approved the implementation of Material by Rail (MbR) at Euston Station Stage A. • Reduces the volume of lorry movements by 34% across the Euston site. • Equivalent to 55,000 lorry movements Network Rail has been instructed to start the amendments to the rail infrastructure which will be completed as part of the decommissioning of Platforms 17 and 18. We have had confirmation that there are 4 freight train paths available each way per day. • NR are bidding for the freight paths as part of the forthcoming timetable planning conference. • We expect to have confirmation that these paths are available to us by June 2019. We have appointed Mace/Dragados as our Construction Partner for Euston who will: • Develop the site logistics to optimise the use of MbR; and • Work along with SCS to identify further opportunities to reduce the number of lorry movements.

  5. Material by Rail at Euston Insufficient budget to fund MbR at both Euston Station and the Portal/Euston Cutting. • HS2 is funding Euston Station Stage A because it operates the longest and provides the • greatest opportunity to move the most excavated material and reduction in lorry movements Portal and Euston Cutting (Park Road Sidings) Euston Station Stage A (Platform 17/18) • Total excavated material= 620,000m 3 • Total excavated material = 625,000m 3 • Potential for 18% reduction in lorry movements or 8% across • Potential for 54% reduction the Euston area. in lorry movements or 34% across the Euston area. • Equivalent to a reduction of 11,000 lorry movements • Equivalent to a reduction of 55,000 lorry movements • Operational Oct 2021 – Sept 2022 (> 1 year) • Operational from Oct 2020 to December 2023 (3 years)

  6. Next Steps NR are progressing the design and implementation of the rail infrastructure to allow Material by Rail to operate from October 2020. We will be working with our contractors and stakeholders to: • Continue to identify ways of reducing the volume of lorry movements. • Optimise the use of rail for Euston Station Stage A. • Demonstrate that we are delivering in line with our U&A’s, EMRs. We are investigating using high direct vision vehicles and high capacity (29 tonnes) to reduce the number of lorry movements and level of emissions. We will continue to update ECRG.

  7. Enabling Works & Noise Insulation Lisa Hogben – Programme Delivery Manager, CSjv/ HS2 Tim Burr – Engagement Programme Manager, CSjv

  8. Euston Enabling Works ‐ Overview Site compounds One Euston Square: Sep 2018 ‐ Jan 2020 TfL Interface Taxi Rank: Completed Nov 2018 Petrol Station: Grant Thornton Enabling Completed Sep House: Sep Works 2018 2018 ‐ Jan 2020 UCL Building: Underway Addison Lee Site Compound July 2018 ‐ July St James’ Gardens: 2019 Enabling Sep 2018 ‐ Jan 2020 Thistle Hotel: July Works 2018 ‐ Oct/Nov 2019 Completed Wolfson & Walkden Granby Terrace House: Sep 2018 ‐ Jan Bridge: Sep 2020 2018 ‐ Dec 2020 DB Cargo Shed: Completed Oct 2018 Ibis Hotel: July 2018 ‐ Regents Park March 2019 1 ‐ 3 Cobourg Calumet Block: Estate: February St: Completed July 2018 ‐ May 2018 ‐ Nov 2019 Nov 2018 2019 NTH Site Compound Insull Wing: July 2018 ‐ March 2019

  9. Euston South Cranes Roads and Paths Melton Street is closed Two tower cranes have to traffic with access been erected ‐ one on maintained for Euston Street and one pedestrians. between the two towers on the station Euston Street is closed piazza. This enables to traffic and heavy demolition to pedestrians. London commence. Euston Forecourt Units Strip Out We have taken We have been busy possession of three stripping out the commercial units on interiors of the two the Euston station towers, and the forecourt. buildings on Euston Street and Drummond These will be Street. demolished in late Spring.

  10. Euston North St James’s Gardens Ibis Hotel Archaeological After a period of excavations continue demobilisation whilst in the Gardens as well UKPN de ‐ energised a as trial holes along substation, demolition Cardington Street. works at the Ibis have The tent roof has now now recommenced been completed by Palmers. London Thistle Hotel Insull Wing Asbestos removal With the above ground continues in the superstructure now basement, plus soft demolished, Keltbray strip on the ground are breaking out the and first floors. ground floor slab down Propping and to the basement and demolition ongoing in excavating chapel the southwest wing. basements.

  11. Euston Approaches UCL Building The Dales Structural demolition Having now taken full of the UCL building possession of the continues, with the top Dales, the site has two floors complete been secured and plus the wall and surveys have columns on the private commenced. access road. Structural demolition London is due to start in May. Granby Terrace Bridge Hoarding Installation of new Hoarding installation utilities pipes and has commenced ducts ongoing at around the Regent’s Stanhope and Robert Park Estate. St, plus manhole Artwork for the construction and sewer hoarding has been disconnection works at designed by local Harrington Street. schoolchildren.

  12. 6 Month Look Ahead September March April May Commence soft ‐ strip at ‘The Dales’ Complete structural demolition of Complete demolition of Calumet Ibis Hotel superstructure Block Complete first ‘area’ of St James Gardens Exhumation Commence GTB bridge span Commence structural demolition of deconstruction ‘The Dales’ Commence structural demolition of Cottage Hotel and William Hill on Complete scaffolding at the two Complete Granby Terrace Bridge Euston St towers utilities diversions Complete structural demolition of Commence structural demolition of August Insull Wing the two towers June July Ongoing works Commence Granby Terrace Bridge Complete structural demolition of excavation the UCL Building

  13. Noise Insulation Mechanical Stage of Process Some previously Number Ventilation in unresponsive residents have now Heritage Properties Total number of properties in scheme 1400 been contacted with Camden’s assistance. Response received / interest shown 849 A Listed Building Consent 97% of the properties Application for temporary Surveys completed 827 where interest has mechanical ventilation been shown have Installed London 214 (Sonair F+) was submitted been surveyed. at the end of January for a Electricity property on Mornington A holistic system design is required for the Costs AMPTHILL Terrace. Ampthill Estate high rise blocks which does Solution not interfere with the buildings' cladding or developed for first The application was fire safety systems. 26 properties. ‘registered’ by Camden on A specification has been prepared and we Long term the 7 th February 2019 and solution in are in the process of procuring a feasibility we are awaiting a decision. development. study.

  14. Security Additional yellow and red bulkhead lighting every 3m. White/yellow bulkheads light up the pedestrian route. Map of security patrols Patrols every 20 minutes day and night between Euston sites and site perimeters. Single person patrols during the day and in pairs at night. London CCTV cameras installed around the perimeter of the site. The emergency services have been notified about the closure of GTB and HS2’s possession of the Dales. Emergency vehicles still have access to all properties in the area and can access the site from either end in the event of a site emergency.

  15. Hampstead Road community space Before After (until Summer 2019) London

  16. Request for additional footpath The requested path would cut through You asked us if we could create a footpath through our work site across the estate the demolition site, and the plant: Not possible pedestrian interface risk is too great. because The requested footpath is further north than our hoarding line. In that area there will be substation de ‐ commissioning works, demolition, utility works and London scaffolding The demolition method being considered would not be possible with a footpath in this location. We will put signage and wayfinding But.. advertising the businesses on the other side of the estate in the new community garden on Hampstead Road. Requested footpath

  17. Cyclists Litter Littering outside Silverdale Littering outside Silverdale Historical issue with Signage and chicanes along Hampstead Road ‐ along Hampstead Road – cyclists & mopeds installed to encourage Before After clean ‐ up ignoring signs and cyclists and mopeds to using footpaths follow diversions We’re also using Customer Experience Representatives to improve compliance

  18. Euston Station - Wayfinding and Signage You asked for more signage to local businesses at Euston station… We have agreed the following with Network Rail: New signage directing people from London NR platforms to step free access to Drummond Street Additional signage on the forecourt hoarding for local stakeholders Investigating finger-point wayfinding

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend