INDICATIVE 2. Euston demolitions 3. Euston Street demolitions 4. - PowerPoint PPT Presentation

Contents 1. Taxi rank INDICATIVE 2. Euston demolitions 3. Euston Street demolitions 4. Questions INDICATIVE EUSTON GARDENS TAXI RANK 3D Concept of the interim taxi rank INDICATIVE * Trees not shown for clarity. Tree removal works for


  1. Contents 1. Taxi rank INDICATIVE 2. Euston demolitions 3. Euston Street demolitions 4. Questions

  2. INDICATIVE EUSTON GARDENS TAXI RANK

  3. 3D Concept of the interim taxi rank INDICATIVE * Trees not shown for clarity. Tree removal works for taxi rank construction now complete, with pruning to follow in the next 2 months

  4. Key dates for works in the area INDICATIVE Footpath diversion around Euston Square Gardens West • Works started 12 March 2018 • Works to complete Easter weekend • New route open Tuesday 3 April 2018 Interim taxi rank • Construction will start straight after footpath diversion operational • Taxi rank completed & operational in October 2018

  5. INDICATIVE EUSTON DEMOLITIONS

  6. Terminology INDICATIVE ■ Soft strip – Removal of all non-structural elements of the building including asbestos, partition walls, windows, pipes and cables etc. (recycled or reclaimed where possible) ■ Hard demolition – Removal of building structural elements

  7. Demolition around Euston Station 1 Food outlets INDICATIVE 1 Euston Square Grant Thornton House Ibis Hotel Walkden House Wolfson House Thistle Hotel The Cottage Hotel Various bounded by 1 & 3 Coburg St Wm Hill Euston/Cobourg/ Drummond/ Melton St NTH South (Insull) Wing

  8. Demolition around Euston Station 2 INDICATIVE Soft strip – July 18 to October 18 Hard demolition – October 18 to July 19 Soft strip – April 18 to June 18 Hard demolition – July 18 to May 19

  9. INDICATIVE EUSTON STREET DEMOLITIONS

  10. INDICATIVE Calumet block

  11. Senator International Disused LUL entrance INDICATIVE Bree Louise PH • Calumet block Calumet 3d View of P027 d Photographic

  12. INDICATIVE • Utilities isolations • Build Scaffolding May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  13. INDICATIVE • Soft strip • Create access into site • Build scaffolding May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  14. INDICATIVE • Demolish Calumet Soft strip perimeter • buildings May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  15. INDICATIVE • Demolish Calumet • Soft strip perimeter buildings May Jun Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun Jul

  16. INDICATIVE • Demolish perimeter buildings May Jun Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun Jul Aug

  17. INDICATIVE • Demolish perimeter buildings May Jun Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun Jul Aug

  18. INDICATIVE • Demolish perimeter buildings May Jun Sep Nov Dec Jan '19 Feb Mar Apr May Jun Jul Aug Oct

  19. INDICATIVE • Demolish final buildings • Install 1st stage propping May Jun Sep Nov Dec Jan '19 Feb Mar Apr May Jun Jul Aug Oct

  20. INDICATIVE • Stage 1 propping complete May Jun Sep Nov Dec Jan '19 Feb Mar Apr May Jun Jul Aug Oct

  21. INDICATIVE South of Euston Street

  22. Walkden House Wolfson House INDICATIVE Cottage Hotel William Hill

  23. INDICATIVE • Utilities isolations • Build scaffolding • Soft strip Wm Hill and Cottage Hotel May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  24. INDICATIVE • Soft strip Walkden House • Demolish Wm Hill & Cottage Hotel • Build scaffolding May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  25. INDICATIVE • Construct tower crane base for Walkden House • Soft strip Wolfson House May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  26. INDICATIVE • Erect tower crane • Soft strip Wolfson House • Scaffolding May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  27. INDICATIVE • Dismantle Walkden House roof and 5 th floor • Soft strip Wolfson House May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  28. INDICATIVE • Dismantle Walkden House roof and 5th floor • Demolish Wolfson roof – Plant rooms May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  29. INDICATIVE • Demolish Walkden 5th floor • Demolish Wolfson 6th floor May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  30. INDICATIVE • Demolish Walkden 4th floor • Demolish Wolfson 5th & 4th floor May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  31. INDICATIVE • Demolish Walkden 3rd floor • Demolish Wolfson 3rd & 2nd floor May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  32. INDICATIVE • Demolish Walkden House 3 rd and 2 nd floors • Demolish Wolfson 1st floor & ground floor May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  33. INDICATIVE • Dismantle & demolish Walkden House 2 nd floor • Demolish Wolfson Gd fl • 1st stage propping May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  34. INDICATIVE • Demolish Walkden House 2 nd floor May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  35. INDICATIVE • Demolish Walkden House 1 st floor • Hand over to delivery team for new LUL substation May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  36. INDICATIVE • Demolish Walkden House ground floor slab May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  37. INDICATIVE • Demolish Walkden House basement internal structures and prop May Jun Jul Aug Sep Oct Nov Dec Jan '19 Feb Mar Apr May Jun

  38. INDICATIVE QUESTIONS

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.