GLEN ROAD PEDESTRIAN BRIDGE & TUNNEL Design Review Panel - - - PowerPoint PPT Presentation

glen road pedestrian bridge tunnel
SMART_READER_LITE
LIVE PREVIEW

GLEN ROAD PEDESTRIAN BRIDGE & TUNNEL Design Review Panel - - - PowerPoint PPT Presentation

GLEN ROAD PEDESTRIAN BRIDGE & TUNNEL Design Review Panel - Presentation #2 July 16, 2020 Background Site Context Glen Road Pedestrian Bridge & Tunnel July 16, 2020 Background The Environmental Assessment In December 2017 a


slide-1
SLIDE 1

GLEN ROAD PEDESTRIAN BRIDGE & TUNNEL

Design Review Panel - Presentation #2

July 16, 2020

slide-2
SLIDE 2

Background – Site Context

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-3
SLIDE 3

In December 2017 a Municipal Class Environmental Assessment (EA), including public consultation, concluded. This study determined the preferred design concept for the bridge & tunnel. The EA recommended that:

  • the bridge be replaced in the same location with a similar looking

structure

  • the tunnel be widened to the west and maintain its current

alignment

Background – The Environmental Assessment

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-4
SLIDE 4

Background – Cultural Heritage

July 16, 2020 Glen Road Pedestrian Bridge & Tunnel

1884 – First record of bridge over Rosedale Valley 1951 – Bridge closed to vehicular traffic; pedestrian use only 1973 – Construction of the current pedestrian bridge 1992 – Officially renamed as the Morley Callaghan Footbridge 2003 – Bridge designated under the Ontario Heritage Act

slide-5
SLIDE 5

The EA the project team presented to the DRP on July 18, 2017. DRP asked the design team to consider:

  • Improvements to universal accessibility
  • Extending public realm improvements southward
  • Slimming the bridge structure
  • Integrating tunnel and bridge lighting with railing
  • Softer and indirect lighting in the tunnel ceiling
  • Importance of public art, not as just as graffiti deterrent, but to create

narratives

  • Access to Rosedale Valley
  • Stronger bridge and tunnel presence from Bloor Street East

Background – DRP Presentation #1

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-6
SLIDE 6

Key Plan

  • f Project

Scope

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Bridge North Landing Tunnel South Landing/ New Stair Sloped Path Public Realm South of Tunnel

slide-7
SLIDE 7

Background – Public Art Competition

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Economic Development & Culture (EDC) carried out the public art competition for the tunnel site in summer 2019 Five 5 artist proposals were shortlisted for technical and jury review. The jury selected Inuit artist Couzyn Van Heuvelen’s proposal.

slide-8
SLIDE 8

Project Scope – Health & Safety

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Bridge Barriers After the completion of the Glen Rd EA, Toronto Public Health and Transportation Services began incorporating suicide prevention measures into state of good repair projects. Bridge barriers have been added to the scope of the Glen Rd Pedestrian bridge.

slide-9
SLIDE 9

Project Scope – Health & Safety

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Personal Security Personal safety was a concern for stakeholders during the EA. A Crime Prevention Through Environmental Design (CPTED) review has been

  • completed. The public realm design includes strategies to increase:
  • lighting
  • sight lines
  • pedestrian traffic

Transportation Services and Corporate Security are evaluating how to best deliver increased security services & equipment on site. Some components will be included in capital construction, while others may be provided through a separate vendor. Equipment being considered:

  • cameras
  • emergency poles
slide-10
SLIDE 10

Background – Schedule

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Consultation

  • Virtual Public Event - Fall 2020 (update community on final design,

schedule, phasing, construction impacts) Design & Construction

  • 100% detailed design - Fall 2020
  • Tender - Winter 2021
  • Construction Start - Early spring 2021
  • Construction Completion – Summer 2022
slide-11
SLIDE 11

View east of existing bridge from Rosedale Valley Road

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-12
SLIDE 12

Bridge - Elevation

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Design Maintains:

  • 2 leg system, tapered leg geometry and girder style

Updated:

  • Third girder added to allow reduction of girder depth
  • Girder depth reduced by 350mm at leg tops and 250mm at mid span
slide-13
SLIDE 13

Bridge – Cross Section

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Existing - 3.0m clearway Proposed - 4.8m clearway

slide-14
SLIDE 14

View north of Existing Pedestrian Tunnel under Bloor St. East from Glen Rd

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-15
SLIDE 15

Pedestrian Tunnel under Bloor St. East

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Maintained:

  • Tunnel widened to west by 1.8 m to achieve 4.8 m clearway
  • Tunnel height maintained at 2.45m

Updated:

  • Strip lighting to be incorporated into ceiling corner chamfers
  • Public art formed into interior tunnel walls

Existing stairs to Bloor St to remain Sherbourne Station Entrance Bloor St above New parapet & guard Sherbourne Station 2.66m below

South Elevation of Proposed Pedestrian Tunnel (view north from Glen Rd south of Bloor St)

slide-16
SLIDE 16

Rendering from Rosedale Valley Road Looking East

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-17
SLIDE 17

Bridge - Barrier & Railing Design

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Suicide Prevention

  • Many international

precedents/guidelines, not standardized; sufficient height (minimum 2200-2500mm); barrier needs to discourage climbing; ideally no toe or footholds Barrier Aesthetic Objectives

  • sensitivity to unique context: quiet

natural setting, scale & aesthetic of the new structure, community/ heritage values

  • visually cohesive with other

components of the project

  • achieve “a good balance”

between technical and aesthetic

  • bjectives
slide-18
SLIDE 18

Bridge - Barrier & Railing Design

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-19
SLIDE 19

Materiality

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

  • Respond to existing bridge palette
  • Proposed: Charcoal grey/black paint

finish to primary structural steel components; natural metal finish to infill railing panels, durable wood handrail, earth tone deck surfacing

slide-20
SLIDE 20

Bridge Rendering – View Crossing Bridge Looking North

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-21
SLIDE 21

Bridge - Lighting

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

  • Primary – linear LED fixtures @ 4m o.c. integrated

into handrail

  • Secondary Accent – continuous LED strip at top of
  • uter barrier
slide-22
SLIDE 22

Bridge Rendering – View Crossing Bridge Looking South

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-23
SLIDE 23

Bridge Rendering – View Approaching Tunnel

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-24
SLIDE 24

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Public Art – Concept

  • Art concept centred around Inuit stone cut

print making, stone carving and the theme

  • f migration
  • Tunnel walls illustrate a stone carving wet

with paint in the printing process

slide-25
SLIDE 25

View looking north from Glen Rd South of Bloor

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Metal birds silhouettes on the outer tunnel walls continue the shapes and colors used in Inuit printmaking on walls that are not being re-cast.

slide-26
SLIDE 26

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Tunnel Walls

slide-27
SLIDE 27

Tunnel Walls

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-28
SLIDE 28

Pre-cast Bollards

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

slide-29
SLIDE 29

Barrier Free Connection & Stair Replacement

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

  • Construction access road alignment identified in EA unfeasible due to utility conflicts
  • Revised alignment has greater impact ravine slope
  • Additional disturbance provides opportunity for barrier free connection

Construction Access Barrier Free Connection

slide-30
SLIDE 30

Barrier Free Connection & Stair Replacement

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Path Design

  • 3.0m width, 4.6% grade
  • Straight alignment selected over switchbacks due to:

– pedestrian origin-destination survey gathered during EA – shortest barrier free route to subway platforms via Sherbourne St entrance – ease of use for bicycles and mobility devices

Bloor St Rehabilitated Ravine Slope Sidewalk Construction Access Landing on Grade 4.6% raised path Bridge Landing Tunnel Below Retaining Wall 85m length

slide-31
SLIDE 31

Barrier Free Connection & Stair Replacement

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Path Design:

  • Elevated path using micropiles and precast concrete decking

to limit ravine slope impacts

  • Retaining walls needed at southeast end to meet and match

bridge landing elevation

  • Metal guardrails with vertical pickets painted dark colour and

LED strip lighting under handrail are consistent with bridge design and heritage style fencing adjacent to site

slide-32
SLIDE 32

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Existing South Bridge Landing View from bridge approaching tunnel

slide-33
SLIDE 33

South Bridge Landing - Stair, Tunnel & Path Crossroads

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

  • Increased landing area improves sight lines, accessibility and user experience
  • New staircase meeting current codes, angled geometry in keeping with bridge and pathway

NORTH Slope Restoration Tunnel Below Landing with Matacryl surfacing New Pole & Luminaire Bridge with Matacryl surfacing New Wall Mounted Luminaire New Staircase Bollards

slide-34
SLIDE 34

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Existing Public Realm south of Tunnel View looking north from Glen Rd

slide-35
SLIDE 35

Glen Road

451 Bloor Street East driveway R.O.W. NORTH

Public Realm South of Tunnel

BikeShare Station Public Art Bollards Sherbourne Station Entrance Tunnel Barrier Curb Mountable Curb Flush Curb New sidewalk Existing Sidewalk New Light Existing Street Trees

User Experience:

  • Reduced ROW encroachments
  • High branching trees
  • Transparent Fencing
  • New pole light
  • Retaining wall recapped
  • Unit paved plaza space

New planting

slide-36
SLIDE 36

Glen Road

451 Bloor Street East driveway R.O.W. NORTH

Public Realm South of Tunnel

Mobility:

  • New sidewalk connection
  • Mountable curb access for

tunnel and bridge users

  • New BikeShare station
  • Formalized driveway access

BikeShare Station Public Art Bollards Sherbourne Station Entrance Tunnel Barrier Curb Mountable Curb Flush Curb New sidewalk Existing Sidewalk New Light Existing Street Trees New planting

slide-37
SLIDE 37

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Existing Landing at Glen Rd & Dale Ave View looking south from Glen Rd

slide-38
SLIDE 38

Landing at Glen Rd and Dale Ave

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

Maintained

  • Removal of cloverleaf planter and

relocation of Morley Callahan Plaque to improve accessibility and sight lines Updated

  • New bridge heritage plaque within

planter

  • Consolidation of fencing & guards

New & relocated heritage plaques in planting with new flowering tree Bollards NORTH Bridge & landing with Matacryl surfacing Concrete paving to match existing sidewalk Bollards Curb cut with tactile warning

slide-39
SLIDE 39

Questions

Glen Road Pedestrian Bridge & Tunnel July 16, 2020

  • Does the panel have any feedback on the proposed material palette considering the

heritage context and public art?

  • Does the panel have any feedback on how to best mitigate conflicts between different

bridge & path users on the site, while accommodating accessibility for all ages and abilities?