Estimation of logistic consumption for the Norwegian Armed Forces - - PowerPoint PPT Presentation

estimation of logistic consumption for the norwegian
SMART_READER_LITE
LIVE PREVIEW

Estimation of logistic consumption for the Norwegian Armed Forces - - PowerPoint PPT Presentation

Estimation of logistic consumption for the Norwegian Armed Forces Terje Nilsen Norwegian Defence Research Establishment Be nice to a logistican if you want to Overview hear a BANG! and not a CLICK! ............. Introduction


slide-1
SLIDE 1

Estimation of logistic consumption for the Norwegian Armed Forces

Terje Nilsen Norwegian Defence Research Establishment

slide-2
SLIDE 2

Overview

  • Introduction
  • Consumption estimates

– method – inputs – results

  • Consumption rates and prognosis
  • Methodological challenges
  • Conclusions

”Be nice to a logistican if you want to hear a BANG! and not a CLICK! .............”

slide-3
SLIDE 3

Introduction

  • NDRE has for about 6 years run a series of projects focussing
  • n logistic issues
  • The main reason for calculating the consumption estimates is to

support a long term planning study on operational logistics

  • Other applications of our estimation efforts are:

– Logistics planning of stocks – Operational planning – Prognosis

slide-4
SLIDE 4

Consumption estimates - method

Gamepieces (Units) Scenario Personnel Material Units Activity profile Activities Existing expertise and estimates Special analysis Consumption Consumption rates Casualty rates Logistical requirements

slide-5
SLIDE 5

Consumption estimates - inputs

  • The choice of units, scenario, activities, and activity profiles

were all done in close cooperation with military expertise – The scenario was based on three criteria: 1) Relevance, 2) Scope, and 3) Representativity – Defined the activities after mapping all the different tasks the units were to do in the different missions – Activity profiles constructed by a sequence of activities for each unit

  • Consumption rates gathered from NDLO, staff handbooks,

maintenance databases etc.

  • Casualty rates equal to zero
slide-6
SLIDE 6

Consumption estimates - results

  • The results were made for the supply types: provisions, water,

fuel, spare parts, and ammunition for each of the primary missions: training, defensive combat, offensive combat, normal and high stabilization

  • Calculated consumption estimates:

– in weight, volume and cost for a standard seven days period

  • f each of the primary missions

– for an operation of six months duration based on a sequence

  • f consumption of standard seven days period
slide-7
SLIDE 7

Consumption rates and prognosis (1)

Battle area Unit A Base Contractor Unit B Asset manager Supply network Information network Sensors TAV

  • Focus on the resources in the ”big picture”
  • Able to overrule the self-organizing groups if

needed

  • Self-organized

Prognosis Prognosis Sensors Battle area Unit A Base Contractor Unit B Asset manager Supply network Information network Sensors TAV

  • Focus on the resources in the ”big picture”
  • Able to overrule the self-organizing groups if

needed

  • Self-organized

Prognosis Prognosis Sensors

Based on the ”Sense and Respond Logistics” concept (US)

slide-8
SLIDE 8

Consumption rates and prognosis (2)

  • One objective in the ”Sense and Respond Logistics” concept is

to decrease stocks (reduced ”footprint”) – one way to do this is to have accurate prognoses tools, and hence the best possible input numbers in the form of consumption rates

  • Our work gave consumption rates for the supply types: Water,

provisions, fuel, spare parts, and ammunition – the consumption rates for all supply types except for spare parts is in the right measure to be used in prognoses tools

  • studies have been undertaken to get the right measure

for spare parts but more work is necessary

slide-9
SLIDE 9

Methodological challenges (1)

  • Verification of the level of accuracy

– the results have only been validated intuitively by military experts – further validation: to compare the results with an actual

  • peration as similar as possible to the scenario studied
  • Representativity of results

– the most generic available scenario was used – necessary to get support from military expertise if the results are going to be extrapolate to other scenarios

?

Consumption estimates S14 Consumption estimates S2 Consumption estimates S1

. . . . . . . .

slide-10
SLIDE 10

Methodological challenges (2)

  • Area of application

– four areas of application: Force structure planning, logistics planning of stocks, operational planning, and prognosis – operational planning: important for the operational planner to know all the assumptions that were used to get the results

slide-11
SLIDE 11

Methodological challenges (3)

  • Deaggregation of results

– the results for the supply types: water, provisions, fuel and ammunition all have the ”right” measure from a supplier point

  • f view

– the challenge consists of getting the results for spare parts from Norwegian kroner per hour (for each consumer) to number of per hour (for each spare part) – a solution could be to get a fixed distribution of spare parts being used by each consumer corresponding to a certain amount measured in Norwegian kroner

slide-12
SLIDE 12

Conclusions

  • We now have:

– a method for calculating consumption estimates – a set of calculated basic seven days operations that can be used for quick estimates of different operations

  • We would like to compare our results with experienced

consumptions in real operations

  • The consumption rates for the supply types: water, provisions,

fuel, spare parts, and ammunition, except spare parts, will constitute a good basis as input numbers to prognoses tools

slide-13
SLIDE 13

Contact information: Terje Nilsen Division of analysis Norwegian Defence Research Establishment Terje.Nilsen@ffi.no + 47 63 80 77 85 + 47 41 62 16 56