Highway 43 Winona Bridge Project Public Meeting August 12, 2013 - - PowerPoint PPT Presentation

highway 43 winona bridge project public meeting august 12
SMART_READER_LITE
LIVE PREVIEW

Highway 43 Winona Bridge Project Public Meeting August 12, 2013 - - PowerPoint PPT Presentation

Highway 43 Winona Bridge Project Public Meeting August 12, 2013 Outline Introductions o Winona Involvement o Project Goals / Responses o Project Background o Schedule Scope Cost Environmental Assessment New


slide-1
SLIDE 1

Highway 43 Winona Bridge Project Public Meeting August 12, 2013

slide-2
SLIDE 2

Outline

  • Introductions
  • Winona Involvement
  • Project Goals / Responses
  • Project Background
  • Schedule
  • Scope
  • Cost
  • Environmental Assessment
  • New Bridge Type
  • Historical Review
  • ROW
  • Next Steps
  • Questions?
slide-3
SLIDE 3

Introductions

Presenters: MnDOT Project Manager: Terry Ward MnDOT Historian/ Archaeologist: Kristen Zschomler We will take questions at the end. Comment and question cards are available. Historical Review one-pager handout.

slide-4
SLIDE 4

Winona Involvement

  • Original scope of project consisted of replacement or

reconstruction of the existing bridge.

slide-5
SLIDE 5

Winona Involvement

  • Both temporary bridges (high and low profile) and ferry

service options were reviewed as river crossing options during construction.

slide-6
SLIDE 6

Winona Involvement

slide-7
SLIDE 7

Winona Involvement

  • June 2012: Winona city and community leaders officially

call for new two-lane span. Gov. Mark Dayton and U.S.

  • Rep. Tim Walz also voice support for new two-lane span,

express frustration at project’s pace. Source: Winona Daily New s,

August 4, 2013

  • Result: Public meeting in September 2012 to announce

project scope including the current recommended alignment and introduction of a new concrete segmental box girder bridge.

slide-8
SLIDE 8

Winona Involvement

  • More than 40 Technical Advisory Group, Public

Advisory Group and public meetings involving Winona community members.

  • Literally hundreds of MnDOT and city staff meetings.
slide-9
SLIDE 9

Winona Involvement

On Deck:

  • Construction staging meeting with City of Winona staff

and Winona Chamber Transportation Committee representatives.

  • Municipal Consent Public Hearing August 19th.
slide-10
SLIDE 10

Winona Involvement

Visual Quality Committee:

  • Approximately 17 Winona community volunteers.
  • Plan to start in August.
slide-11
SLIDE 11

Winona Involvement

slide-12
SLIDE 12

Project Goals

  • Start construction on the new Mississippi River Bridge

as expeditiously as possible.

  • Move traffic to the new bridge as expeditiously as

possible.

  • Minimize the likelihood of detours related to bridge

maintenance work on the existing structure.

  • Keep the river crossing open during construction.
slide-13
SLIDE 13

Project Goals

  • Meet the Chapter 152 funding cap of $142 million (not

including ROW).

  • ROW estimated at additional $12 - $20 million.
  • Overall total estimated cost $154 - $162 million.

No funding has been diverted from the project. Project funding is different from prelim inary cost estim ates.

slide-14
SLIDE 14

Project Goals - Responses

  • Selected project for first use of Construction Manager

General Contractor (CMGC).

  • Qualifications Based Selection of Contracting Team.
  • Moved up start of construction:
  • Previously: Construction starting in 2015.
  • Currently: July 2014 to March 2015.
  • Assigned new Project Management Team.
  • Our construction staging approach w ill not close the

river crossing during construction.

slide-15
SLIDE 15

Project Goals - Responses

Our team wants to work with you to meet our mutual project goals and successfully deliver the first CMGC project for MnDOT as a partner with the City of Winona and the Winona community.

slide-16
SLIDE 16

Project Background - Schedule

Four scheduling tracks need to align to start construction:

  • Municipal Consent – ROW Track.
  • Environmental Assessment (EA) – Environmental

Permits Track.

  • Final Design Consultant Contracts Track.
  • CMGC Contracts Track.
slide-17
SLIDE 17

Project Background - Schedule

So far, all four scheduling tracks are on schedule for a July 2014 construction start.

*Very Aggressive and not a Guarantee.

slide-18
SLIDE 18

Project Background - Schedule

  • Municipal Consent – August 19th Public Hearing.
  • ROW offers begin 1-2 months after Municipal Consent

(approx. 28 parcels).

  • Environmental Assessment (EA) Public Hearing this fall.
  • Finding of No Significant Impact (FONSI) by end of year.
  • Environmental Permits by July 1, 2014.
slide-19
SLIDE 19

Project Background - Schedule

Construction Schedule (based on staying on tracks as planned)

  • Phase I: July 2014 – March 2015
  • New bridge river piers
  • Phase II: March 2015
  • Remainder of new bridge and roadway
  • Phase III: Fall 2016 (traffic on new bridge)
  • Rehab and reconstruct existing bridge and remaining roadway

Complete construction Fall 2019 / Spring 2020

slide-20
SLIDE 20

Project Background - Scope

slide-21
SLIDE 21

Project Background - Scope

slide-22
SLIDE 22

Project Background - Scope

slide-23
SLIDE 23

Project Background - Scope

Preliminary Design

slide-24
SLIDE 24

Project Background - Scope

slide-25
SLIDE 25

Project Background - Cost

  • Based on our current scope and risk profile.
  • Existing bridge costs: $56-$63 million
  • New bridge: $52-$59 million
  • Roadway costs: $7-$9 million
  • Total estimated construction cost: $115-$131 million.
  • Total funding (not including ROW): $142 million.
  • Difference is project development and delivery costs
  • We were able to add a new bridge to project within funding

limitations.

slide-26
SLIDE 26

Environmental Assessment (EA)

  • EA Public Hearing coming this fall
  • National Environmental Policy Act (NEPA) Process
  • Opportunity for public and agency formal comment
  • Requires Finding of No Significant Impact (FONSI) from

FHWA

slide-27
SLIDE 27

Environmental Assessment (EA)

slide-28
SLIDE 28

Environmental Assessment (EA) – New Bridge

Recommended EA Bridge Type: Concrete Segmental Box Girder (Main River Spans) Historical Review Team Findings MnDOT District 6 Cost / Maintenance Environmental Agency Feedback (Migratory Birds)

City of Winona

slide-29
SLIDE 29

Environmental Assessment (EA)

Concrete segmental box girder for the main river span is recommended for new bridge type in the EA

slide-30
SLIDE 30

Concrete Segmental Box Girder

slide-31
SLIDE 31

Tied Arch

slide-32
SLIDE 32

Cable Stayed

slide-33
SLIDE 33

New Bridge Type

  • Cost: Tied Arch - $14-$15 million more
  • Funding not in current project budget
  • Cost: Cable Stayed – Even more money than tied arch
  • Start of construction
slide-34
SLIDE 34

Concrete Segmental Box Girder

slide-35
SLIDE 35

Tied Arch

slide-36
SLIDE 36

Cable Stayed

slide-37
SLIDE 37

Comparisons

slide-38
SLIDE 38

Concrete Segmental Box Girder

slide-39
SLIDE 39

Tied Arch

slide-40
SLIDE 40

Cable Stayed

slide-41
SLIDE 41

Comparisons

slide-42
SLIDE 42

Section 106 Process Historical Review

Kristen Zschomler, MnDOT

slide-43
SLIDE 43
  • Section 10 6 Process
  • Partners- agencies & organizations
  • Cultural resource com ponents

» Archaeology » Architecture » Historic Bridge » New Bridge

OVERVIEW

slide-44
SLIDE 44
  • Federal Highway Adm inistration (FHWA)

– MnDOT Cultural Resources Unit (CRU)

  • Other Federal agencies
  • MnDOT

– District 6 , Bridge Office, Environm ental Stewardship

  • State Historic Preservation Office (SHPO)
  • City of Winona
  • Public

Section 106 Partners

slide-45
SLIDE 45
  • Section 10 6 requires federal agencies to take into

account the effects of their undertakings on historic properties.

  • Federal funding invokes Section 10 6 of the

National Historic Preservation Act.

  • FHWA is the lead federal agency responsible for

com pliance with Section 10 6 .

Section 106 Process

slide-46
SLIDE 46
  • As allowed in the Section 10 6 regulations, FHWA

delegates review authority to professionally qualified staff in MnDOT’s CRU

  • CRU m akes all Section 10 6 determ inations and

findings on behalf of FHWA

  • FHWA can exercise final authority and overrule at any

point

Section 106 Process

slide-47
SLIDE 47

Are historic properties present in project area?

  • Archaeological survey
  • Architectural survey

If yes, then effects (direct or indirect) to those properties are determ ined

  • No Adverse
  • Adverse

Section 106 Process

slide-48
SLIDE 48
  • Surveyed proposed construction lim its
  • No sites that m eet the National Register criteria

were identified

  • Few parcels rem ain to survey when right-of-way

acquired

Section 106 Process - Archaeology

slide-49
SLIDE 49
  • Surveyed all pre-19 6 0

properties.

  • Identified 34 properties

listed on or eligible for the National Register.

Section 106 Process - Architectural

slide-50
SLIDE 50
  • The Winona Bridge is historic because of its

engineering.

Section 106 Process – Historic Bridge

slide-51
SLIDE 51
  • Rehabilitation study was com pleted to determ ine

if the bridge could be rehabilitated and reconstructed and still m eet the transportation needs. – Collaborative effort between Bridge Engineers and Historians

Section 106 Process – Historic Bridge

slide-52
SLIDE 52
  • CRU determ ined, and SHPO concurred,

proposed rehabilitation and reconstruction of the existing bridge had No Adverse Effect.

Section 106 Process – Historic Bridge

slide-53
SLIDE 53
  • MnDOT’s recom m ended alternate

– Rehabilitate and reconstruct existing bridge and build new parallel bridge – New segm ental concrete box girder bridge also m eets budget and m igratory bird concerns.

Section 106 Process-Finding

slide-54
SLIDE 54
  • CRU’s findings

– Girder concept m eets Standards

  • m inim al profile in com parison/ doesn’t

com pete visually.

  • doesn’t replicate historic elem ents.
  • m aintains prim ary view of historic bridge

from downtown. – Girder concept has no adverse effect.

  • SHPO concurred

Section 106 Process – Finding

slide-55
SLIDE 55
  • Project overall has No

Adverse Effects to historic properties

  • Program m atic Agreem ent

will be entered into to ensure no adverse effects

  • ccur during the final

design process

Section 106 Process – Finding

slide-56
SLIDE 56

Section 106 Process – Finding

slide-57
SLIDE 57

Concrete Segmental Box

slide-58
SLIDE 58

Tied Arch

slide-59
SLIDE 59

Cable Stayed

slide-60
SLIDE 60

Comparisons

slide-61
SLIDE 61

Concrete Segmental Box

slide-62
SLIDE 62

Tied Arch

slide-63
SLIDE 63

Cable Stayed

slide-64
SLIDE 64

Comparisons

slide-65
SLIDE 65

New Bridge Type – Cass Street Bridges

slide-66
SLIDE 66

Project Background – ROW

slide-67
SLIDE 67

Project Background – ROW

slide-68
SLIDE 68

Similar Projects – St. Anthony Falls (35W)

slide-69
SLIDE 69

Next Steps

  • Municipal Consent: Public Hearing August 19th
  • Environmental Assessment: Fall 2013
  • FONSI: End of the year
  • Construction Start: July 2014 – March 2015
slide-70
SLIDE 70

Questions?

MnDOT Project Website: www.mndot.gov/ d6/ projects/ winonabridge/ index.html

slide-71
SLIDE 71
slide-72
SLIDE 72

Similar Projects - Missouri