economical analysis of the coal mining waste dump x in
play

Economical analysis of the coal-mining waste dump `X` in USCB - PowerPoint PPT Presentation

Economical analysis of the coal-mining waste dump `X` in USCB Thousands of PLN (general) Total sales 160,000 Profit before taxation and interest 50,000 Interest 4,3 Taxation 8,5 Net profit 35,000 Add Depreciation 20,000 Net cash


  1. Economical analysis of the coal-mining waste dump `X` in USCB Thousands of PLN (general) Total sales 160,000 Profit before taxation and interest 50,000 Interest 4,3 Taxation 8,5 Net profit 35,000 Add Depreciation 20,000 Net cash generated 55,000 Purchase Consideration Capital Expenditure 20,000 Net Cash Available 35,000 Source: Analysis of Ipas Polska sp. z o.o., unpublished

  2. Recovery of carboniferous rocks from the dumps for aggregate production

  3. Exploitation and fire hazards

  4. Recovery of materials from post- metallurgic dump sites

  5. Flotation tailings of Zn-Pb ores in Bytom

  6. Dumps of Fe wastes near Czestochowa

  7. Post mining dumping grounds of USCB (PIG, 2001)

  8. Legal regulations regarding mining wastes in Poland The valid legal regulations in Poland regulate the issues connected with coal mining dumping grounds in a very general way. It is necessary to prepare supplements to the legal provisions or new regulations concerning post-mining dumping grounds. It seems to be beneficial to create new regulations in the form of local law deeds.

  9. The recovery of coal due to the latest legal regulations in Poland is very important and compulsory. The main rule of managing of wastes in Poland according to legal deed about wastes (Ustawa z 27.04.2001r. o odpadach, art. 5 pkt. 2) requires ensuring environmental compliant recovery if there was no possibility of avoiding of origination of wastes. The owner of the wastes should in the order of priority to treat them in a recovery process, and if it is not possible from the technological point of view or not economically justified the owner should treat the wastes as harmless rendering using Best Available Techniques (BAT`s).

  10. CONCLUSIONS The coal mining and post-metallurgic waste dumps in Poland cause serious environmental hazards, particularly danger of self ignition and dump fires. The state of reclamation of many objects is not sufficient, although officially these objects are considered as reclaimed. The recovery of coal reduces environmental hazards, there is also reduction of dump volume, which may be afterwards efficiently reclaimed.

  11. There is a possibility and necessity of recovering of coal and other materials from industrial waste dumps, what should be linked with appropriate legal regulations. The main legal acts in Poland require recovery as the priority.

  12. Not only does the effective recovery and reclamation of post-mining dumps on the area of GZW, carried out in accordance with the guidelines specified by detailed legal regulations, prevent from environmental threats but it also makes it possible to realize interesting (often spectacular) projects of these types of land’s development.

  13. Thank you for your attention!

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.