DESIGN AND IMPLEMENTATION OF REMOTE RFI MONITORING SYSTEM For Ghana - - PowerPoint PPT Presentation

design and implementation of remote rfi monitoring system
SMART_READER_LITE
LIVE PREVIEW

DESIGN AND IMPLEMENTATION OF REMOTE RFI MONITORING SYSTEM For Ghana - - PowerPoint PPT Presentation

DESIGN AND IMPLEMENTATION OF REMOTE RFI MONITORING SYSTEM For Ghana Radio Astronomy Obervatory-Nkutunse BY Joseph A. K. Nsor September 21, 2020 (GSSTI) GRAO September 21, 2020 1 / 33 OUTLINE OF PRESENTATION 1 Abstract 2 Introduction 3


slide-1
SLIDE 1

DESIGN AND IMPLEMENTATION OF REMOTE RFI MONITORING SYSTEM For Ghana Radio Astronomy Obervatory-Nkutunse

BY Joseph A. K. Nsor

September 21, 2020

(GSSTI) GRAO September 21, 2020 1 / 33

slide-2
SLIDE 2

OUTLINE OF PRESENTATION

1 Abstract 2 Introduction 3 Internal Challenge 4 Objectives 5 Engineering 6 Results 7 Conclusion 8 Future Upgrade

(GSSTI) GRAO September 21, 2020 2 / 33

slide-3
SLIDE 3

Outline

1 Abstract 2 Introduction 3 Internal Challenge 4 Objectives 5 Engineering 6 Results 7 Conclusion 8 Future Upgrade

(GSSTI) GRAO September 21, 2020 3 / 33

slide-4
SLIDE 4

Abstract

This work presents the design of an automated Radio Frequency Interference Monitoring System (RFIMS) for an informed data and future upgrades for interferences mitigation. Generally, the degradation

  • f radio telescopes data is influenced by several factors that are due to

the current environmental conditions.This requires an Investigation of Radio Frequency Interference (RFI) for the proposed telescope

  • peration frequency by performing a site survey to gather information
  • f the spectrum usage of the converted 32m class antennas into radio

astronomy telescopes. Keywords: Radio Astronomy, LNA, Frequency Spectrum, Radio Frequency Interference, and Mitigation Techniques.

(GSSTI) GRAO September 21, 2020 4 / 33

slide-5
SLIDE 5

Outline

1 Abstract 2 Introduction 3 Internal Challenge 4 Objectives 5 Engineering 6 Results 7 Conclusion 8 Future Upgrade

(GSSTI) GRAO September 21, 2020 5 / 33

slide-6
SLIDE 6

History

Figure 1: Ghana’s Decommission Satellite Dish

(GSSTI) GRAO September 21, 2020 6 / 33

slide-7
SLIDE 7

Global Issue

Figure 2: World Network of Telescopes

(GSSTI) GRAO September 21, 2020 7 / 33

slide-8
SLIDE 8

Minus Ghana

Figure 3: UV Coverage of The Milky Way Without Ghana

(GSSTI) GRAO September 21, 2020 8 / 33

slide-9
SLIDE 9

Plus Ghana

Figure 4: Ghana’s Contribution to Viewing the Milky Way

(GSSTI) GRAO September 21, 2020 9 / 33

slide-10
SLIDE 10

Outline

1 Abstract 2 Introduction 3 Internal Challenge 4 Objectives 5 Engineering 6 Results 7 Conclusion 8 Future Upgrade

(GSSTI) GRAO September 21, 2020 10 / 33

slide-11
SLIDE 11

Evidence

Figure 5: Conversion of Decommission Dishes into Telescopes

(GSSTI) GRAO September 21, 2020 11 / 33

slide-12
SLIDE 12

Environmental Factors

Figure 6: Traditional Measurement Method

(GSSTI) GRAO September 21, 2020 12 / 33

slide-13
SLIDE 13

Outline

1 Abstract 2 Introduction 3 Internal Challenge 4 Objectives 5 Engineering 6 Results 7 Conclusion 8 Future Upgrade

(GSSTI) GRAO September 21, 2020 13 / 33

slide-14
SLIDE 14

Objectives

This project undertaken is: To design and implement an automated RFI monitoring system. To determine the exact direction of an interfering signal.

(GSSTI) GRAO September 21, 2020 14 / 33

slide-15
SLIDE 15

Proposed

Figure 7: Proposed Solution

(GSSTI) GRAO September 21, 2020 15 / 33

slide-16
SLIDE 16

Outline

1 Abstract 2 Introduction 3 Internal Challenge 4 Objectives 5 Engineering 6 Results 7 Conclusion 8 Future Upgrade

(GSSTI) GRAO September 21, 2020 16 / 33

slide-17
SLIDE 17

Polarization Subassembly

(a) First Subsystem

(GSSTI) GRAO September 21, 2020 17 / 33

slide-18
SLIDE 18

Azimuth Subassembly

(a) Second Subsystem

(GSSTI) GRAO September 21, 2020 18 / 33

slide-19
SLIDE 19

Complete Antenna System

(a) Antenna System

(GSSTI) GRAO September 21, 2020 19 / 33

slide-20
SLIDE 20

Wire Configuration

Figure 11: Wiring Layout

(GSSTI) GRAO September 21, 2020 20 / 33

slide-21
SLIDE 21

Step Parameters

Steprev= 1Rev

Stepz 360 1.8 =200 step rev

(1) For antenna polarization in E/H plane, its step angle is obtained by multiplying the step-rev to the number of micro stepping per

  • revolution. And so in achieving 90o angle for a full revolution,

Pangle = steprev microstepping = 200 1/4 = 50step rev (2) where (P-Angle) is Polarization angle. Considering the antenna pattern it is recommended that monitoring is done at an angle of 45o for a full revolution of 360o, with (A-angle) as the azimuth angle of rotation [70]. Aangle = steprev microstepping = 200 1/8 = 25step rev (3)

(GSSTI) GRAO September 21, 2020 21 / 33

slide-22
SLIDE 22

User Interface

Figure 12: Antenna Interface

(GSSTI) GRAO September 21, 2020 22 / 33

slide-23
SLIDE 23

Outline

1 Abstract 2 Introduction 3 Internal Challenge 4 Objectives 5 Engineering 6 Results 7 Conclusion 8 Future Upgrade

(GSSTI) GRAO September 21, 2020 23 / 33

slide-24
SLIDE 24

Preliminary Survey

Measurement Platform. Cardinal Compass.

(a) Azimuth Platform (b) Compass

(GSSTI) GRAO September 21, 2020 24 / 33

slide-25
SLIDE 25

Results

Figure 14: Horizontal Polarization

(GSSTI) GRAO September 21, 2020 25 / 33

slide-26
SLIDE 26

Results

Figure 15: Vertical Polarization

(GSSTI) GRAO September 21, 2020 26 / 33

slide-27
SLIDE 27

FAT Ref1

Figure 16: FAT for 5GHz

(GSSTI) GRAO September 21, 2020 27 / 33

slide-28
SLIDE 28

FAT Ref2

Figure 17: FAT for 6.7GHz

(GSSTI) GRAO September 21, 2020 28 / 33

slide-29
SLIDE 29

Outline

1 Abstract 2 Introduction 3 Internal Challenge 4 Objectives 5 Engineering 6 Results 7 Conclusion 8 Future Upgrade

(GSSTI) GRAO September 21, 2020 29 / 33

slide-30
SLIDE 30

Conclusion

Figure 18: Complete RFIMS

(GSSTI) GRAO September 21, 2020 30 / 33

slide-31
SLIDE 31

Outline

1 Abstract 2 Introduction 3 Internal Challenge 4 Objectives 5 Engineering 6 Results 7 Conclusion 8 Future Upgrade

(GSSTI) GRAO September 21, 2020 31 / 33

slide-32
SLIDE 32

Upgrade

To write an algorithm that the RFIMS can point to an interfering frequency of interest.

(GSSTI) GRAO September 21, 2020 32 / 33

slide-33
SLIDE 33

END OF PRESENTATION

THANK YOU

(GSSTI) GRAO September 21, 2020 33 / 33