RFI and Webcast November 20, 2012 Greetings and Introduction - - PowerPoint PPT Presentation
RFI and Webcast November 20, 2012 Greetings and Introduction - - PowerPoint PPT Presentation
District of Columbia 22-Mile Priority Streetcar System RFI and Webcast November 20, 2012 Greetings and Introduction Agenda Project Overview Review of Issues Identified Through RFI Project Procurement and Delivery Project
Agenda
- Greetings and Introduction
- Project Overview
- Review of Issues Identified
Through RFI
- Project Procurement and Delivery
- Project Planning and Permitting
- Project Elements
- Project Funding/Financing
- Moving the Project Forward
- Discussion
Greetings and Introductions
- Welcome - Terry Bellamy, Director, District Department of
Transportation, DDOT
- Project Procurement and Delivery - Garey Foyt, HDR
Engineering
- Project Elements, Planning and Permitting - Steven Carroll,
HDR Engineering
- Project Funding/Financing - Robert Bannister, Ernst & Young
Infrastructure Advisors
Priority Streetcar System of 22 miles
- Design, Build, Finance,
Operate and Maintain
Local Bus Operations within the District
- All Non-Regional
Service
- Operate and Maintain;
Vehicles
4
Project Overview
Review of Issues Identified Through RFI
5
- Project Procurement and Delivery
- Project Planning and Permitting
- Project Elements
- Project Funding/Financing
6
Review of Issues Identified Through RFI
Project Procurement and Delivery
Current Approach:
- District focusing on evaluating availability payment based
concession model of delivery.
- District seeking to utilize two-staged, RFQ/RFP process.
– RFQ phase will focus on team qualifications. – RFP phase will be broken into technical proposal and financial proposal.
7
Review of Issues Identified Through RFI
Project Procurement and Delivery
Next Steps:
- District beginning development of RFQ for release Spring 2013.
– 60 day response time for interested parties. – 60 day review of responses. – No more than 4 teams would be short-listed following review process.
- District currently analyzing potential RFP process to follow RFQ short-listing process (details such as
schedule and stipend under consideration and will be detailed in RFP phase).
- District currently intending to use “best value” approach for selection of concessionaire to deliver
22-mile priority system.
- Additional details on procurement method to be included in RFQ. Specific contract provisions TBD
in consultation with short-listed firms during RFP process and during negotiations with selected firm.
- District is developing policies and procedures for disclosures and conflicts of interest to be
provided to interested proposers during RFQ Phase.
8
Review of Issues Identified Through RFI
Project Planning and Permitting
- District recognizes that the environmental review and permitting process is a
critical issue for proceeding with a concession.
- District is currently proceeding with some level of planning and/or
environmental review process for the majority of project segments.
- Additional segments are being scheduled for review.
- Complete update and schedule of completed and underway
planning/environmental review processes will be included in the forthcoming RFQ.
- Utility and ROW issues may pose similar risk factor. District will provide
updated status for these items in the RFQ.
9
Review of Issues Identified Through RFI
Project Elements—Bus
- District beginning process of compiling and analyzing detailed information for
bus services including:
– Condition and ownership of all existing assets, – Status of all existing contractual obligations, – Existing service levels
- Analysis will also include investigation of concepts for achieving desired
service levels through integration of streetcar and bus services.
- Results of above analyses will be reported in the forthcoming RFQ.
10
Review of Issues Identified Through RFI
Project Elements—Streetcar
- Options for procurement of new vehicles (and the integration of existing
vehicles) are under consideration:
– Integrated procurement with the overall concession agreement, or – Separate procurement process.
- Off-wire vehicle operating capability key requirement for system. District
continues to investigate technology alternatives. Additional industry input in this area is of particular interest to the District.
- District is continuing with preliminary system engineering and design
- exercises. These exercises will form basis of preliminary technical
requirements.
- Completion of the above analyses will inform the RFQ.
11
Review of Issues Identified Through RFI
Project Funding/Financing
- District focusing on evaluating availability payment based concession model of
delivery.
- District understands there is limited market interest for transfer of certain
revenue risks including:
– Farebox – Property Value Capture.
- Transfer of risks under potential concession agreement likely to have
significant impact on project schedule and/or require contractual protections.
- District has unique budget appropriation process and is working to
mitigate/remove uncertainty raised by process.
- District has no plan to issue debt to finance project. Payment structure must
be consistent with District’s debt limitations & accounting policies.
- Mayor’s Task force to assist in preparation of final project funding plan.
- Findings relative to above issues to be provided in forthcoming RFQ.
MOVING THE PROJECT FORWARD
NEXT STEPS
Mayor’s DC Streetcar
Financing & Governance Task Force
- Represents high level of commitment to
moving the project forward.
- Comprised of District government leaders as
well as leaders from local private sector.
- Role is to work closely with DDOT to develop
both a project funding plan and a plan for
- verall governance of the program.
- Findings will be a key input to the RFQ/RFP
process.
13
Task Force Members
Public Members:
Richard Bradley
Executive Director, Downtown Business Improvement District
Charles "Sandy" Wilkes
Chairman of The Wilkes Company
Matthew Klein
President of Akridge
Robert Puentes
Senior fellow, Brookings Institution's Metropolitan Policy Program
Ginger Laytham
Senior Executive Officer to the President/ CEO/ Chairman of Clyde's Restaurant Group
Officials:
Terry Bellamy
Director of DDOT
Victor Hoskins
Deputy Mayor for Planning and Economic Development
Harriet Tregoning
Director of the Office of Planning
Natwar Gandhi
D.C. Chief Financial Officer
Eric Goulet
Director of the Mayor's Office of Budget and Finance
Brian Hanlon
Director of the Department of General Services
Nicholas Majett
Director of the Department of Consumer and Regulatory Affairs
Chair: Allen Lew
City Administrator
Vice Chair: Jair Lynch
President / CEO of JAIR LYNCH Development Partners