SLIDE 1
- As a result of delays to the Interim Opening from East Kapolei to Aloha
Stadium (Segment 1), Core Systems Contractor AHJV (the “Contractor”) made its original Request for Contract Change (RFCC) to the Design-Build (DB) portion of its Contract.
- The Contractor subsequently amended the RFCC to include the delays to
the DB work to the projected Full Opening (East Kapolei to Ala Moana).
- Interim Opening is presently scheduled for December 2020, which is
1560 (4.3 years) days after the originally scheduled date.
- Full Opening is presently scheduled for January 2025, which is 2119 days
(5.8 years) after the originally scheduled date.
Basis of the Contractor’s Claim
2