SLIDE 1
COASTAL HIGH HAZARD AREA (CHHA) Main Library May 21, 2019 - - PowerPoint PPT Presentation
COASTAL HIGH HAZARD AREA (CHHA) Main Library May 21, 2019 - - PowerPoint PPT Presentation
COASTAL HIGH HAZARD AREA (CHHA) Main Library May 21, 2019 Definitions: CHHA, Evac Zone, SFHA COASTAL HIGH HAZARD AREA (CHHA) F.S. 163.3178 Area below the elevation of the Category 1 storm surge line as established by a Sea, Lake and Overland
SLIDE 2
SLIDE 3
Coastal High Hazard Area
- 1. How long has the CHHA been around: 1986
- 2. How are CHHA boundaries determined: SLOSH Model
- 3. Expansion from 2010 to 2016: 41% of the City
- 4. Why did the CHHA double in size: Updated Technology
- 5. What areas of the City are located in the expanded CHHA?
SLIDE 4
2010 CHHA Acreage
7,705 Acres
SLIDE 5
2016 CHHA Acreage
2010: 7,702 2016: 8,623 16,325 Acres
SLIDE 6
Gateway and Carillon Town Center Jabil Headquarters Campus Baypoint Commerce Center ASI / Progressive Insurance HQ
- Dr. ML King Jr. St. No. (62nd Ave. No.)
4th Street No. (54th Ave. No.) Innovation District USFSP Campus Coquina Key Shopping Center Skyway Marina District 10 Mobile Home Parks
2010
SLIDE 7
Gateway and Carillon Town Center Jabil Headquarters Campus Baypoint Commerce Center ASI / Progressive Insurance HQ
- Dr. ML King Jr. St. No. (62nd Ave. No.)
4th Street No. (54th Ave. No.) Innovation District USFSP Campus Coquina Key Shopping Center Skyway Marina District 10 Mobile Home Parks
2016
SLIDE 8
Requests for residential density increases within the Coastal High Hazard Zone shall not be approved.
- St. Petersburg Land Use Policy 7.1
SLIDE 9
Proposal
- To consider Land Use Map Amendment requests for increasing
residential density and/or commercial intensity within the Coastal High Hazard Area, where:
- Map amendments are requested through public hearing(s)
- Evacuation times / shelter capacity are mitigated
- Construction is more resilient to storm surge, built above
current standards
SLIDE 10
State Statute 163.3178(8)
A proposed comprehensive plan amendment shall be found in compliance with state coastal high-hazard provisions if:
- a. The adopted level of service (16 hours) for out-of-county hurricane
evacuation is maintained for a category 5 storm; or
- b. A 12-hour evacuation time to shelter is maintained for a category 5 storm
event and shelter space is available; or
- c. Appropriate mitigation is provided that will satisfy subparagraph 1 or
subparagraph 2. Appropriate mitigation shall include, without limitation, payment of money, contribution of land, and construction of hurricane shelters and transportation facilities.
SLIDE 11
Countywide Rules: Balancing Criteria
A. Access to Emergency Shelter Space & Evacuation Routes B. Utilization of Existing and Planned Infrastructure C. Utilization of Existing Disturbed Area D. Maintenance of Scenic Qualities / Improve Public Access E. Water Dependent Uses F. Part of Community Redevelopment Area G. Overall Reduction of Density or Intensity H. Clustering of Uses I. Integral Part of Comprehensive Planning Process J. Location within an Activity Center or Target Employment Center K. Furthers the Goals and Policies of the Integrated Sustainability Action Plan L. Reduction of Storm Vulnerable Structures
SLIDE 12
Land Development Regulations
- A. Shelter Mitigation requirements
Construction of multi-family (resulting from a map amendment to increase density within CHHA) shall provide for mitigation: payment of money, contribution of land, construction of hurricane shelter(s).
- B. Hurricane Evacuation Mitigation
Construction of new hotels and residential units (multi-family) shall require hurricane evacuation plan, incorporated into legal documents, such as lease.
- C. Establish CHHA design standards, Building more resilient
structures Comprehensive list of stricter building standards based on a model
from Norfolk, Virginia.
SLIDE 13
Norfolk, Virginia Resiliency Quotient
SLIDE 14
SLIDE 15
SLIDE 16
SLIDE 17
Collaborative Effort
- 1. County-wide Working Group
The County and City Emergency Management agencies, Forward Pinellas, County and other municipal planning staff are working together on a mitigation solution.
- 2. ULI Grant Award
Technical experts to weigh in on the proposed development standards on feasibility, cost and appropriateness along with stakeholder analysis.
- 3. Stakeholders Workshops and Meetings
Public outreach and input needed every step of the way.
SLIDE 18
Next Steps
- 1. Stakeholder Meeting – May 21st 6:30- 8:00 PM
Main Library
- 2. ULI Technical Advisory Event – June 18-19
- 3. City Council, Committee of the Whole Workshop – July 25th
- 4. Workshops/Public Hearings – September through December
SLIDE 19
COASTAL HIGH HAZARD AREA (CHHA)
Britton Wilson, AICP Planner II Urban Planning and Historic Preservation Division Planning and Development Services Department City of St. Petersburg 727.551.3542 Britton.Wilson@stpete.org