Cheekye Fan Current Development Application District of Squamish - - PowerPoint PPT Presentation

cheekye fan current development application
SMART_READER_LITE
LIVE PREVIEW

Cheekye Fan Current Development Application District of Squamish - - PowerPoint PPT Presentation

Cheekye Fan Current Development Application District of Squamish Presentation at Public Information Meeting Nov 24, 2014 Outline Background Hazard Policies Next Steps Background The Cheekye Fan Sediment deposits from upper parts of


slide-1
SLIDE 1

Cheekye Fan Current Development Application

District of Squamish Presentation at Public Information Meeting Nov 24, 2014

slide-2
SLIDE 2

Outline

Hazard Policies Next Steps

Background

slide-3
SLIDE 3

Background

slide-4
SLIDE 4
  • Sediment deposits from upper

parts of the basin (Mount Garibaldi)

  • Recognized debris flow / flood

hazard

The Cheekye Fan

slide-5
SLIDE 5
  • 2011: Squamish Nation

may apply, with or without partner, to the Crown for ownership of ~200 acres of Cheekye Fan lands

Intergovernmental Cooperation Accord

slide-6
SLIDE 6

Official Community Plan: Hazard Policies

  • Development in

hazard zones 3 and 4 requires:

– Debris Flow Mgt. Plan – Area-wide mitigation measures.

slide-7
SLIDE 7

Development Application

slide-8
SLIDE 8

OCP Land Use Designations Zoning

Development Application: BMS Cheekeye One Partnership

Resource

slide-9
SLIDE 9

Hazard Policies

slide-10
SLIDE 10

Hazard and Risk

Hazard: Debris flow volume and frequency Risk: Probability X Consequences

Almost certain Very Unlikely Incidental Catastrophic Consequences Probability

slide-11
SLIDE 11

History

1993 Thurber Terrain Hazard and Land Use Study 2008 BGC Numerous Studies

How big / how often? Where will it go? What are the consequences?

2013 Application 2014 Expert Panel 30+ years of Study

slide-12
SLIDE 12

Expert Panel

  • How Big?: volume of 5.5M m3
  • How frequent?: 1:10,000 yr. return

period or 0.01% chance each year

  • Climate change likely to increase

frequency of small events and to a lesser extent, large events.

  • Risks to existing development should

be mitigated whether or not there is future development.

  • All forms of mitigation should be

considered and carefully evaluated.

slide-13
SLIDE 13

Expert Panel Recommendations Current Application Review Review OCP Policies and Hazard Zones Mitigation Strategy OCP and Rezoning

Hazard Policies

Hazard and Risk Risk mitigation options Development Regs

slide-14
SLIDE 14
  • Debris flow mitigation works

– DoS staff and 3rd party reviewer:

  • design standards, risk reduction, environmental impacts, operations and

maintenance

– Province:

  • Dike Maintenance Act (DMA), Water Act, etc.

– DoS Council:

  • (DMA) Agree to “diking authority”  ownership, mtn., operation and rehabilitation.
  • Concurrent review of OCP and zoning

– Council readings including a Public Hearing

Current Application Review

slide-15
SLIDE 15

OCP/Rezoning Application Review

District/ Peer Review

Staff Review Public Meeting Intro to Council Council Inputs Environ- mental Review

Operations and Maintenance Design Concept

Mitigation Strategy Provincial Review

Current Application Review

We Are Here

slide-16
SLIDE 16

Next Steps

slide-17
SLIDE 17
  • Continued review
  • Begin to update policies
  • Council update
  • Further public comment

Next Steps

slide-18
SLIDE 18

THANK YOU

http://www.squamish.ca/showcase Development and Project Showcase – New Development Applications District of Squamish Development Services planning@squamish.ca

slide-19
SLIDE 19

D R . M AT T H I AS J AK O B , P . G E O . B G C E N G I N E E R I N G I N C .

Cheekeye River Fan and its proposed residential development:

Public Meeting, Squamish November 24, 2014

slide-20
SLIDE 20

Objectives

  • Establish a reliable frequency-magnitude relationship of debris flows
  • Estimate/model the hazard intensity on the fan
  • Estimate the existing risk for loss of life on the fan
  • Can portions of the fan be safely occupied? If so, what type and scale of

mitigation is needed?

  • What can be done to improve current resident’s safety and reduce hazard of

future development to tolerable levels?

  • In absence of legislated levels of risk tolerance, what levels are deemed

reasonable by the DoS/the province?

21

slide-21
SLIDE 21

Current Elements at Risk

First Nations Reserves Don Ross Secondary School Brackendale Elementary School Brackendale Residential Highway 99 Users Cheekeye Bridge BC Railway Squamish Airport DOS Infrastructure BC Hydro Substation Ross Road Saw Mill Squamish Valley Road Cheekeye Development

22

slide-22
SLIDE 22

23

Brakendale Airport

Elements at Risk

  • Hwy. 99

Cheekeye Subdivision Schools BC Hydro Transmission Line First Nation IRs First Nation IR BC Rail Possible Development Area

slide-23
SLIDE 23

24

slide-24
SLIDE 24

The July 2010 rock avalanche and debris flow at Capricorn Creek, Mount Meager

25

Photos: courtesy Prof. John Clague

slide-25
SLIDE 25

26

Cat Lake

SQUAMISH

Lower fan

Cheekeye Ridge Linears Upper fan

slide-26
SLIDE 26

27

Highschool Primary School

B R A C K E N D A L E

  • Approx. fan boundary

SQUAMISH

Squamish River

You are here

slide-27
SLIDE 27

Not completed

The Steps

Steps completed to date:

Hazard Recognition Frequency-Magnitude Analysis Hazard Intensity Mapping Consequence Determination Risk Calculations Risk Evaluation Risk Reduction Development

28

slide-28
SLIDE 28

Glacial History

29

S O U R C E : F R I E L E

slide-29
SLIDE 29

Fan Evolution

30

12,000 - 10,200 yrs 10,200 - 6,900 yrs 6,900 yrs 6,000 to 2,000 yrs present

slide-30
SLIDE 30

Dendrochronolgy

  • ~60 wedges,

cores, discs sampled along channel

  • Cross-sections

reconstituted along confined reaches

  • Discharge

back-calculated

31

slide-31
SLIDE 31

Test Trenching Program

32

Objectives:

  • Determine size of Garbage Dump debris flow
  • Update frequency-magnitude analysis
slide-32
SLIDE 32

Test Trenching Program

33

5 m

Fluvial Gravels

Southern part of airport Northern part of airport Garbage Dump event 1 m Fluvial Gravels

slide-33
SLIDE 33

34

Garbage Dump Debris Flow ~ 900 years ago Airport

  • Hwy. 99

BC Hydro Sub Cheakamus R. 2.1 M m 3 = 175,000 dump truck loads

slide-34
SLIDE 34

Debris Flow Volume

35

100,000 1,000,000 10,000,000

10 100 1,000 10,000 100,000

Return Period (years)

Total Debris Flow Volume (m

3)

10,000 yr  2.8 Mm 3 2500 yr  2.4 Mm 3 500 yr  1.4 Mm 3 20 yr = 0.2 Mm 3 100 yr = 0.6 Mm 3 500,000 200 yr = 0.8 Mm 3 5,000,000 50 yr = 0.4 Mm 3 2500 yr  2.8 Mm 3 10,000 yr  5.5 Mm3

Design return period, debris flows Austria Design return period, debris flows Switzerland Former design return Period, geohazards, Canada National Building Code, Seismic Design, Canada Upper Design Return Period, Cheekeye Best Estimate Worst Estimate

slide-35
SLIDE 35

What does 5.5 Mm3 debris mean?

36

5.5 million cubic metres is roughly twice the volume of BC Place Stadium

Images from www.bcplacestadium.com

slide-36
SLIDE 36

Rock Avalanche Modeling

37

slide-37
SLIDE 37

38

20-year return period event, unmitigated

Brackendale

BC Hydro Sub

slide-38
SLIDE 38

39

100-year return period event, unmitigated

Brackendale

BC Hydro Sub

slide-39
SLIDE 39

40

2500-year return period event, unmitigated

Brackendale

BC Hydro Sub

slide-40
SLIDE 40

41

10,000-year return period event, unmitigated

slide-41
SLIDE 41

42

Preliminary mitigation concepts

~ 35 m high barrier Sedimentation basin

slide-42
SLIDE 42

Safety Risk

43

  • In Safety Risk one differentiates between Individual Risk Safety and Group

Risk Safety

  • Individual Risk: Unacceptable for current development
  • Group Risk: Unacceptable for current development
  • Highway Users: Unacceptable Group Risk

given risk tolerance standards practiced, for example, by the District of North Vancouver. Therefore, mitigation required irrespective of new development (expert panel). New development does require higher mitigation standard than existing developments.

slide-43
SLIDE 43

Safety Target Risk Criteria

  • New development individual residual risk: 1 in 100,000 (10-5).
  • Existing development individual residual risk: 1 in 10,000 (10-4).
  • Total group residual risk: “ALARP” zone which means “As Low As

Reasonably Practical”

slide-44
SLIDE 44

Barrier Design

  • Barrier to retain an “extreme” debris flow event – 5.5 Mm3
  • Barrier to have a outlet to pass the Cheekeye River while maintaining the

existing channel shape and sediment load downstream

  • After an event, the outlet will maintain an outlet for the Cheekeye River and

provide practical access for cleanout from the top

  • Events that pass through the outlet are to be managed by risk reduction

measures that could include earthworks on the banks of the Cheekeye River as well as debris basin upstream of Hwy 99.

slide-45
SLIDE 45

Main Barrier

(preliminary design concept)

46

Downstream view Squamish River

slide-46
SLIDE 46

Main Barrier

(preliminary design concept)

47

Upstream view

slide-47
SLIDE 47

Main Barrier

(preliminary design concept)

48

Upstream view

slide-48
SLIDE 48

49

Vision of Post-Mitigation Design

Brackendale

BC Hydro Sub 5.5 Mm3 debris Sedimentation basin Principal retention basin I.R. 11

slide-49
SLIDE 49

Site Investigation

  • 5 boreholes have been completed at the Barrier site, 1 in the basin.
  • Bedrock depth is variable. 5 to >80 m at the barrier
  • The rock is overlain by sand, gravel and cobbles from previous debris events
  • 15 Test pits have been dug to characterize the near-surface (<5m) soils
  • Geophysics is being done to interpolate the characterization between

boreholes

slide-50
SLIDE 50

Conclusions

51

  • Safety risk is currently unacceptable compared to, for example, DNV

standards and mitigation is recommended irrespective of future developments

  • Moderate and large sized debris flows, if unmitigated, would also result in

significant economic loss

  • The expert review panel recommended the structure(s) be designed for a

10,000-year return period event with a volume of 5.5 Mm3

  • The topography allows mitigation works to be technically feasible and would

protect, amongst other elements at risk, the current and future development and the people of the Squamish Nation.

  • Preliminary mitigation concept is to provide one primary barrier structures

with auxiliary risk reduction measures and monitoring

slide-51
SLIDE 51

Questions?

52

slide-52
SLIDE 52

1.00E-08 1.00E-07 1.00E-06 1.00E-05 1.00E-04 1.00E-03 1.00E-02 1.00E-01 1 10 100 1000 10000

N (Number of Fatalities) Frequency of N or more fatalities (F) ____

UNACCEPTABLE ALARP ACCEPTABLE

Pre-Barrier (All Buildings) Post-Barrier (All Buildings) Post-Barrier (Future Buildings) Pre-Barrier (Existing Buildings) Post-Barrier (Existing Buildings) Pre-Barrier (Future Buildings)

slide-53
SLIDE 53

Risk Reduction Benefits

54

  • The community of Brackendale (northern portions)
  • The Cheekeye subdivision within Squamish
  • I.R. 11
  • The Cheekeye Substation (BC Hydro). Existing risk is already low due to a natural shelter by a

large bedrock bluff and an existing perimeter berm

  • Lower transmission towers (BC Hydro)
  • Squamish Airport
  • Squamish Garbage Dump
  • CN Rail. Risk to track washout or bridge loss over Cheekeye River will be significantly reduced.
  • Brackendale high school and primary school
  • Users of Government Road and Squamish Valley Road
  • Users of Highway 99
  • Resort Municipality of Whistler and Village of Pemberton. Economic losses due to highway

closure caused by bridge loss or highway erosion or sediment deposition will be significantly reduced

  • Fortis Gas. Risk of pipeline exposure by erosion will be significantly reduced
  • Aquatic habitat Cheekeye, Brohm, Cheakamus Rivers. The likelihood of extreme events

destroying fish or spawning habitat will be signficiantly reduced

  • District of Squamish. Rates of fluvial sediment transport and aggradation in the Squamish River

floodplain near Squamish will be reduced

slide-54
SLIDE 54

Stump Lake Sediment Coring

55

Cheekeye River Stump Lake ~ 6900 yrs BP ~ 11,600 yrs BP

A A’

V = 15-30 m/ s Debris flow deposits

slide-55
SLIDE 55

Proposed Cheekeye Development

PUBLIC INFORMATION MEETING

Monday November 24th

slide-56
SLIDE 56

Request

Amendments to the District of Squamish’s official community plan and zoning bylaw to permit a new single family neighbourhood, educational/community uses, parks, greenways and trails.

slide-57
SLIDE 57

Background

1970’s-80’s

 241 manufactured home strata plan was registered on the property (still exists) and site servicing completed (existing paved road layout remains)  Project halted due to the threat of a debris flow originating from the Cheekeye River  Crown retained ownership of the lands

1993

 Identified in the Thurber/Golder Cheekye River Terrain Hazard and Land Use Study. Subsequently incorporated into the Squamish Official Community Plan.

2008

 Umbrella Agreement between Squamish Nation and District of Squamish recognizes further development potential of these lands

2011

 Accord between the Squamish Nation and the District of Squamish recognizing future development potential of the lands

slide-58
SLIDE 58

Development Proposal

Complement Brackendale’s existing community by introducing affordable housing options close to existing schools, services while also extending the park and greenway system, trails and constructing the needed hazard debris barrier.

slide-59
SLIDE 59

Single Family Lots

Single Family Lots #

  • Approx. Size

(sq. ft) Approx. Frontage (ft) % of Lots Small Lots 79 2850 30 11 Medium Lots 591 4500 45 79 Large Lots 78 6000 60 10

slide-60
SLIDE 60

Parks and Open Spaces

 57 acres of parkland and greenways  51 acre community park (home of Brackendale Fall Fair)  6 acres of parkways including park improvements

slide-61
SLIDE 61

Community/Educational Uses

 Proposed Education Facility (i.e. independent school, continuing education, etc.)  Daycare Facility

slide-62
SLIDE 62

Trails

 Retain, enhance and expand Ray Peters Trail by a further 1.3 km  Introduce enhanced “through” and “connecting trails” by 1.6 km  Net gain of trails by 2.2 km  Opportunities to design unique, multi-ability trails for neighbourhood and community

slide-63
SLIDE 63

Debris Barrier

slide-64
SLIDE 64

Timing and Phasing

 Subject to development approval process and local real estate conditions  Intent to develop in two phases, south to north due to efficiencies with servicing installation  20 year timeframe for build out (approximately 40 lots per year)

slide-65
SLIDE 65

Geotechnical Engineering (Debris Flow Mitigation) Environmental Review (wildlife, terrestrial, and riparian) Site Servicing (conceptual civil design for utilities and roads) Traffic Study

Technical Studies

slide-66
SLIDE 66

Community Questions and Comments

Public Information Meeting is the initial step in the development approval process