Board of Directors Operations Committee Meeting North Carolina Turnpike Authority June 21, 2018 Monroe Expressway Roadway Toll Collection System Overview Andy Lelewski, P.E. Director of Toll Operations Greg Vari Consultant 2 Monroe


slide-1
SLIDE 1

Board of Directors Operations Committee Meeting

North Carolina Turnpike Authority June 21, 2018

slide-2
SLIDE 2

Monroe Expressway Roadway Toll Collection System Overview

Andy Lelewski, P.E. Director of Toll Operations Greg Vari Consultant

2

slide-3
SLIDE 3

Monroe Expressway

Monroe Expressway RTCS Overview

3

slide-4
SLIDE 4

The Complete Transaction

Monroe Expressway RTCS Overview

  • Fully formed transactions generated at the

lane and delivered to the Back Office

Monroe Accuracy Metrics

  • Transponder Transactions

– 99.99% Accuracy – 2 hours from lane to back office

  • Image Transactions

– 99.8% Accuracy – 72 hours from lane to back office

4

BOS CSC I-77 Express Lanes US-74 Express Lanes Triangle Expressway Future Projects Monroe Expressway

slide-5
SLIDE 5

Project Procurement

Monroe Expressway RTCS Overview

  • RFP issued April 14, 2016
  • Three proposals submitted to NCTA
  • TransCore identified as best value
  • Best and Final Offer executed March 9, 2017

5

slide-6
SLIDE 6

Key Components

Monroe Expressway RTCS Overview

6

slide-7
SLIDE 7

VCARS – Vehicle Capture and Recognition System

Monroe Expressway RTCS Overview

  • Key Features

– Stereoscopic, dual camera license plate capture for each travel lane – Full redundancy to minimize revenue loss

7

slide-8
SLIDE 8

Automatic Vehicle Classification

Monroe Expressway RTCS Overview

  • IVIS – Intelligent Vehicle Identification

System

  • OPUS – Overhead Profile Unifying

System

8

slide-9
SLIDE 9

Janus Multi-Protocol Reader

Monroe Expressway RTCS Overview

  • Key Features

– Full multiprotocol functionality

  • Reads TDM, 6C and SeGo toll transponders

– High Accuracy, High Reliability

9

slide-10
SLIDE 10

Installation Status

Monroe Expressway RTCS Overview

10

slide-11
SLIDE 11

Installation Status

Monroe Expressway RTCS Overview

11

slide-12
SLIDE 12

Installation Status

Monroe Expressway RTCS Overview

12

slide-13
SLIDE 13

Installation Status

Monroe Expressway RTCS Overview

13

slide-14
SLIDE 14

Operations and Maintenance

Monroe Expressway RTCS Overview

  • TransCore assessed monthly based on 15

key performance measures

14

slide-15
SLIDE 15

Operations and Maintenance

Monroe Expressway RTCS Overview

  • Support Team

– Raleigh: System Auditing and Compliance Monitoring – Charlotte MRTMC: Roadway Operations and Traffic Management – Monroe: TransCore Maintenance Facility

15

slide-16
SLIDE 16

Charlotte Area Outreach

16

Social Media Bill by Mail Inserts Community Events Paid Advertisements, Sponsorships, & Direct Mailers

Project Design and Development Factory Acceptance Testing

Q2 2017 Q3 2017 Q4 2017 Q1 2018 Q2 2018 Q3 2018 Q4 2018

Procurement FAT Site Installation Remaining Installation Tolling Readiness Acceptance Testing

Project Schedule

slide-17
SLIDE 17

Charlotte Area Outreach

Andy Lelewski, P.E. Director of Toll Operations Kathryn Lorbacher Consultant

17

slide-18
SLIDE 18

Projects

Charlotte Area Outreach

18

  • Monroe Expressway

– November 2018

  • I-77 Express Lanes

– November 2018

slide-19
SLIDE 19

Milestones

Charlotte Area Outreach

19

Social Media

Today Monroe Factory Acceptance Testing Monroe Storefront Open I-77 Express Lanes Open

JUN. JUL. AUG. SEPT. OCT. NOV. DEC.

New Transponders Website Updates Charlotte Storefront Open BOS Updates New Account Types/Plans Monroe Expressway Open

slide-20
SLIDE 20

NC Quick Pass Program Updates

Charlotte Area Outreach

  • Account types/plans
  • Transponders
  • Remote storefronts

20

slide-21
SLIDE 21

Account Types/Plans

Charlotte Area Outreach

21

Account Type Plan Payment Personal Standard (max 5 transponders) Prepaid Motorcycle Prepaid Business Standard Prepaid Government Postpaid Transit Postpaid First Responder (Non-Revenue) n/a HOV HOV Only (incl. Motorcycle) n/a

New account type/plan *NC Quick Pass transponders will be required for all account types and plans

slide-22
SLIDE 22

Transponders

Charlotte Area Outreach

22

Transponder Cost to Customer Standard FREE Headlamp FREE First Responder* FREE Transit* FREE

*Not available to public, NCTA approval required New transponder

slide-23
SLIDE 23

Transponders

Charlotte Area Outreach

23

Transponder Cost E-ZPass (Interior) $7.40 +tax E-ZPass (Front Bumper Mount) $13.49 +tax E-ZPass Flex (Switchable) $16.49 +tax

New transponder

slide-24
SLIDE 24

Outreach Challenges

Charlotte Area Outreach

  • Remote storefronts
  • New market unfamiliar with:

– Tolling – NC Quick Pass – Bill by Mail

  • New High Occupancy Tolling (HOT) program
  • Coordination with private concessionaire

24

slide-25
SLIDE 25

NC Quick Pass Storefronts

Charlotte Area Outreach

25

Charlotte Monroe

slide-26
SLIDE 26

Charlotte Area Outreach

26

I-77 Express Lanes Monroe Expressway

3034 Winston Ave. Monroe, NC 28110

slide-27
SLIDE 27

Charlotte Area Outreach

27

Social Media Bill by Mail Inserts Community Events Paid Advertisements, Sponsorships, & Direct Mailers

NC Quick Pass Brand Awareness Outreach (municipalities, businesses, first responders, transit) Sponsorships Community Events Advertising Campaign

JUN. JUL. AUG. SEPT. OCT. NOV. DEC.

slide-28
SLIDE 28

NC Quick Pass Brand Awareness

Charlotte Area Outreach

  • Social media
  • BBM inserts
  • Website
  • Promotional materials

28

slide-29
SLIDE 29

Advertising Campaign Considerations

Charlotte Area Outreach

  • Digital marketing
  • Direct mailers
  • Print advertisements
  • Radio advertisements
  • Partnership with transit agencies

29

slide-30
SLIDE 30

Charlotte Area Outreach

30

slide-31
SLIDE 31

Complete 540 Procurement Update

Rodger Rochelle, P.E. Chief Engineer

31

slide-32
SLIDE 32

Complete 540

Complete 540 Procurement Update

  • R-2721A
  • 4.6 mile new location
  • ~ 190 parcels
  • R-2721B
  • 4.9 mile new location
  • ~ 210 parcels
  • R-2828
  • 8.6 mile new location
  • ~ 250 parcels

32

slide-33
SLIDE 33

Current Project Schedule

Complete 540 Procurement Update

  • Record of Decision:

June 6, 2018

  • Corridor Permit Application:

Summer 2018

  • Right of Way Plans for R-2721A & R-2721B: Fall 2018
  • Anticipate Permits:

Late 2018/Early 2019 (phased for R-2828 & construction for R-2721A and R-2721B)

  • Design-Build Contract Letting

– R-2828: November 2018 – R-2721B: February 2019 – R-2721A: April 2019 – R-2829: Future (2027)

  • Complete Project Finance:

Early 2019

33

slide-34
SLIDE 34

Status and Next Steps

Complete 540 Procurement Update

R-2828 R-2721B R-2721A Advertisement  April 16 July 2 September 4 SOQ Due Date  May 11 July 31 October 2 Shortlist Date  May 24 August 14 October 18 Issue 1st Draft RFP  May 24 Debrief Teams  Week of June 4 1st Meeting with Teams  June 7 Issue 2nd Draft RFP June 26 2nd Meeting with Teams July 10

34

slide-35
SLIDE 35