ATTACHMENT 8 Geotechnical Program Summary Presentation Page 8 of 10 - - PDF document

attachment 8 geotechnical program summary presentation
SMART_READER_LITE
LIVE PREVIEW

ATTACHMENT 8 Geotechnical Program Summary Presentation Page 8 of 10 - - PDF document

LEDCOR TECHNICAL SERVICES INFRASTRUCTURE SERVICES GROUP CANADA NORTH FIBRE LOOP Rev. 002 Mackenzie & Peel River Geotechnical Land Use Application Date of Last Revision: 2016-08-17 ATTACHMENT 8 Geotechnical Program Summary Presentation


slide-1
SLIDE 1

LEDCOR TECHNICAL SERVICES INFRASTRUCTURE SERVICES GROUP

CANADA NORTH FIBRE LOOP

  • Rev. 002

Mackenzie & Peel River Geotechnical Land Use Application Date of Last Revision: 2016-08-17 Page 8 of 10

ATTACHMENT 8 – Geotechnical Program Summary Presentation

slide-2
SLIDE 2

CANADA NORTH FIBRE LOOP PROPOSED GEOTECHNICAL & GEOPHYSICAL PROGRAM OVERVIEW

MACKENZIE AND PEEL RIVER CROSSINGS FEASIBILITY STUDIES

REVISION 0006 AUGUST 2 2016

slide-3
SLIDE 3

2

PROJECT INTRODUCTION

  • The Canada North Fibre Loop (CNFL) is a Northwestel (NWTel) driven project

to complete a fibre loop between 26 terrestrial Northern communities in the Yukon and the Northwest Territories.

  • This loop will be accomplished by running a 775 km length of fibre cable

along the Dempster Highway from Dawson City, YT to Inuvik, NT and joining up with the Mackenzie Valley fibre line currently under construction.

  • Presentation includes 2 main portions:
  • Description of fibre redundancy
  • Description of scope of work for geotechnical and geophysical studies
  • Phase 1 of this project is to finalise the design and cost.
  • Phase 1 includes desk top assessments, GIS work and some field work.
  • As recommended by the Gwich'in Land and Water Board, we are reaching out

to all stakeholders and First Nations to discuss the project and the requirement for this small drilling program in particular.

slide-4
SLIDE 4

3

FIBRE REDUNDANCY

  • Current situation results in service disruptions for

Northern communities

  • Solution requires significant investment in fibre

infrastructure Northwestel seeking to implement self-healing fibre rings to protect services for communities in the Yukon and Northwest Territories

slide-5
SLIDE 5

4

FIBRE WITH NO DIVERSITY (CURRENT STATE)

  • If fibre is damaged due to events such as a forest fire or

a contractor who cut the line while doing work along the road – then service between communities 1 and 2, and then communities 2, 3 and 4, is disrupted.

  • Depending on location of damaged cable, it can take

from 6 to 12 hours to mobilize resources to repair the cable, travel to the site, complete repairs & restore service.

  • As businesses increasingly rely on the Internet to
  • perate – whether for point-of-sale equipment, inventory

management, purchasing, airline passenger check-in or a host of other applications – any service outage can result in forced shut-downs and/or closures until service is restored.

Fibre damage can have significant impact on the economy & community

slide-6
SLIDE 6

5

SELF HEALING FIBRE LOOP (FUTURE STATE)

  • A fibre loop (or ring) can be compared to an oval

racetrack: there are 2 ways around the track and if you start in one direction and encounter an

  • bstruction, you can simply turn and go the other way

around the track to get to the other locations.

  • With a ring, if the control equipment senses a

disruption in the data travelling in one direction, it simply re-routes traffic in the other direction so that communities remain fully connected.

Fibre rings are automatically self healing, maximizing network reliability, ensuring no loss of service for customers

slide-7
SLIDE 7

6

FIBRE CUTS IN THE NORTH

Telecommunications facilities have become critical infrastructure for communities to function in our modern economy

Fibre Disruption

  • Aug. 1, 2016
  • Sept. 23, 2015
  • Sept. 2014

Summer 2013

Event Fibre Cut Fibre Cut Fibre Cut Fibre Melt Services Impacted Internet, Cellular & Satellite Long Distance (LD) Internet, Cellular & Satellite Long Distance (LD) Internet & Cellular LD, Internet & Cellular Communities Impacted Yukon, Mackenzie Delta & all Satellite Served Yukon, Mackenzie Delta & all Satellite Served Yukon, Mackenzie Delta & all Satellite served Mackenzie Valley Duration 6 hours during day 6 hours during day 8 hours during afternoon & evening 16 hours during day & night

slide-8
SLIDE 8

7

CANADA NORTH FIBRE LOOP

  • Canada North Fibre Loop would connect fibre in the Yukon with the MVFL in the Northwest Territories, creating full

redundancy in the two Territories

  • Requires placing approximately 775km of fibre from Dawson City (YK) to Inuvik (NWT)
  • Benefits of this project – once complete, this self-healing fibre loop will provide robust protection against fibre cuts in:
  • Yukon, Northern BC and along the Mackenzie Valley in the NWT (26 communities)
  • Cellular and Internet in the satellite served communities in the North (36 communities)
  • In preparation for this link, Northwestel will complete the extension of the existing fibre from Stewart Crossing to Dawson

City in 2016

Building a more connected North

slide-9
SLIDE 9

8

CANADA NORTH FIBRE LOOP

Yukon Whitehorse Watson Lake Upper Liard Teslin Tagish Swift River Marsh Lake Carcross Carmacks Faro Ross River Pelly Crossing Stewart Crossing Mayo Keno Dawson City NWT Fort Simpson Wrigley Tulita Norman Wells Fort Good Hope Tsiigehtchic Inuvik Fort MacPherson Aklavik Tuktoyaktuk

Full Self-Healing Redundancy for 26 Terrestrial Northern Communities

* Also benefits 36 satellite communities served from Whitehorse

slide-10
SLIDE 10

9

CANADA NORTH FIBRE LOOP STATUS

  • Yukon Government has endorsed the Canada North Fibre Loop as best solution for redundancy
  • Northwest Territories Government is supportive of this project
  • Nunavut Government supportive
  • High level cost estimates range significantly today, and phase 1 is to provide a more accurate estimate and

provide the project timing required to construct the fibre route, this information is needed to facilitate the approvals and funding needed to undertake the project

  • Proposed geo-technical work is important to clarify costs of boring under two major rivers in the NWT
slide-11
SLIDE 11

10

PHASE 1 - STATUS

  • Initial planning stage:
  • Preliminary river crossing investigations
  • Route review
  • Construction methodology review
  • Stakeholder engagement
  • Desktop assessment of cultural, environmental and wildlife sensitivities
  • Geotechnical and geophysical investigations:
  • Current plan is to complete geotechnical and geophysical investigations at the Mackenzie

and Peel River crossings

  • Purpose is to understand subsurface details at existing ferry/ice bridge crossings in order to

determine cost and feasibility of crossing with a large horizontal directional drill (HDD)

  • Type A Land Use Permit required for investigations
  • NWTel and Ledcor Technical Services (LTS) will commence engagement with intent to

apply for the Type A Land Use Permit under the Gwich’in Land and Water Board (GLWB)

slide-12
SLIDE 12

11

PROJECT TEAMS

  • Northwestel
  • John-Eric Petersson
  • Kluane Adamek
  • Don Pumphrey
  • Ledcor Technical Services
  • Jordan Woodall
  • Cheryl Katnick
  • Dan Commons

Paladin Crossings has been contracted to plan large HDD crossings and will be managing the geotechnical and geophysical investigations.

slide-13
SLIDE 13

12

TYPE A LAND USE PERMIT - SCHEDULE

Task Date Comments

Written Notification

  • Email out informational

PowerPoint presentation July 13th, 2016

  • Draft Application can be provided

upon request. Follow-up with Stakeholders

  • Discuss written notification
  • Address any comments

July 15th through July 29th

  • Comments to be documented

and addressed

  • Engagement record to be

maintained Stakeholder Meetings

  • If required, open house will be

scheduled for direct meeting with project representatives TBD

  • If required, one to two

stakeholder presentations “open houses” to be held

slide-14
SLIDE 14

13

TYPE A LAND USE PERMIT - SCHEDULE

Task Date Comments

Land Use Permit Application Submission

  • Engagement Plan
  • Project Description
  • Environmental and Resource

Impacts and Mitigation Measures Week of Aug 15th, 2016

  • 10 day completeness check by

the GLWB

  • Comments from the GLWB to be

addressed immediately GLWB 42 Day Review Project August/Sept 2016 Type A Land Use Permit Issuance Second week of September Geotechnical and Geophysical Field Program Last week of September Follow-up Reporting to the GLWB Last week of September

slide-15
SLIDE 15

14

PROGRAM OVERVIEW

  • Goal is to determine the subsurface profile of sediments and rocks
  • Cannot estimate cost and effort of the large drills without knowledge of the

underlying structure

  • Drill will occur within DoT Right of Way next to existing ferry terminals
  • Highway or Ferry traffic will not be affected during drilling operations
  • Crew to stay in Tsiigehtchic & Fort McPherson and travel to and from site
  • Hours of work to be between 7 am and 7 pm
slide-16
SLIDE 16

15

PROGRAM OVERVIEW

  • Geotechnical Investigation
  • 1 bore drilled on either side of rivers (Mackenzie 90m, Peel 65m deep)
  • 20 m x 25 m work space per bore
  • 3-person crew, up to 15 days to complete all four drills
  • Geophysical Investigation
  • Electrical resistivity (ERT)
  • Bathymetry survey
  • Ground penetrating radar (GPR)
  • 3-person crew, 5 days to complete at both sites
slide-17
SLIDE 17

16

slide-18
SLIDE 18

17

GEOTECHNICAL

Tools available include:

  • Standard Penetration Test (SPT) Hammer
  • Provides information about soils
  • Odex Percussion Down-the-Hole Hammer Drill
  • High penetration especially in rock
  • Good for soil sampling
  • Advantageous in unconsolidated formations
  • Mud Rotary Drill
  • drill often used when sediments may be

saturated with groundwater

slide-19
SLIDE 19

18

GEOPHYSICAL

  • ERT (Electrical Resistivity Tomography)
  • Technique for imaging sub-surface geotechnical stratigraphy
  • Acquires a series of resistivity measurements from an array of very low

current electrodes contained in a wire that is placed along the bottom of the river.

  • The variation in the resistivity is what is used to delineate the subsurface

stratigraphy.

  • Low current poses no risk to fish or fish habitat.
  • Peel River – ERT approx 500 m in length
  • MacKenzie River – ERT approx 1.2 km in length
  • ERT Methodology
  • The ERT line will be positioned on the bottom of the river channel during

testing and up either bank of the river.

  • The line will be removed once testing is completed.
  • Navigable Waters not required for this program.
slide-20
SLIDE 20

19

GEOPHYSICAL PROGRAM

  • Bathymetric Survey
  • Purpose to map profile of river bottom
  • Conducted using a ground penetrating radar (GPR)

system with controller, module and 100 MHz antenna

  • GPR sends a tiny pulse of energy and records strength

and time required for return of any reflected signal

  • Uses pulses to image the sub-surface
  • Non-intrusive method that poses no hazards to fish and

fish habitat

  • Geophysical program will be completed using an

aluminum boat/zodiac traversing along the proposed alignment.

slide-21
SLIDE 21

20

SURVEY RESULTS

  • Example of survey results at the MVFL

Mackenzie River crossing with colour-contouring

* Source: GLD MVFL Geophysical Surveys for Investigation of Three Fibre Optic River Crossings, NWT (Golder Associates, 2015)

slide-22
SLIDE 22

21

ENVIRONMENTAL CONSIDERATIONS

  • Spill Management Plan
  • Spill response and clean-up procedures
  • Drip trays for all equipment
  • Secondary containment for all oils,

liquids, containment

  • Spill kit to contain 10 ft. oil only socks,

polypropylene sorbent pads, 6 mil poly disposal bags, epoxy plug compound (hydrocarbon compatible), 10 Quart Cellulose Sorbent Material, fuel spill response kit

  • Re-fueling procedures
  • Procedures and secondary containment

for fueling equipment on daily basis.

  • Fuel to be transported in double lined

truck mounted 99 gallon slip tanks

  • Secondary containment procedures
  • Gravel Berm around site
  • Waste Management Plan
  • Drilling mud management and disposal

process will be outlined after drilling contractor finalized

  • “Inert” mud plan will include a combination of

bentonite and polymer non toxic drilling fluid products

  • Water Extraction
  • Electrical submersible pumps to be used to

eliminate pump fuel spills

  • Per DFO standards, 3 mm fish screens will be

used for water extraction

  • Flow meter to be installed in pump

configuration to properly document water withdrawal volumes

Project-specific spill contingency, waste management, and site reclamation plans will be included in full application package

slide-23
SLIDE 23

22

ENVIRONMENTAL CONSIDERATIONS

  • Reclamation Plan
  • All boreholes will be backfilled and sealed off with cuttings and

non-toxic bentonite chips

  • Artesian flow management plan will be in place
  • Any ruts will be repaired
  • Any spills/releases will be cleaned up and properly documented
  • A pre-construction and post construction report will be provided
  • Traditional Fisheries
  • The in-river surveys pose no risk and will not interfere with

traditional fisheries

  • Suitable environmental controls will be in place during the

geotechnical drilling to ensure no impact to the rivers will occur.

  • Containment berms, distance from the water (maximum possible)
slide-24
SLIDE 24

23

WATER WITHDRAWAL

  • Estimated 30 to 40 m3 water will be extracted on a daily basis

during geotechnical drilling operations

  • In total, an estimated volume of 100 m3 is expected for each

borehole (400 m3 for the entire program)

  • Option to receive municipal water via water truck is also being

considered

slide-25
SLIDE 25

24

HEALTH AND SAFETY (HS&E)

  • All planned geo-physical and geotechnical work will be completed in

accordance with Ledcor’s HS&E requirements and reporting processes

  • Safety stats will be included in the daily Field Report, Summary provided

during weekly updates, and at end of project

  • All required ground disturbance procedures will be completed
  • All crew members will have required safety tickets and job specific training

prior to borehole drilling

slide-26
SLIDE 26

25

ADDITIONAL QUESTIONS?

Kluane Adamek

Director of Government Relations PO Box 2727, 301 Lambert Street Whitehorse, Yukon, Y1A 4Y4 Cell: (867) 332-1530 Tel: (867) 455-4200 Fax: (867) 668-3236 email: kadamek@nwtel.ca Website: www.nwtel.ca

Cheryl Katnick

Manager – Permitting & Environmental

Project Services

Ledcor Technical Services Suite 1500-1055 Hastings St W Vancouver, BC V6E 2E9 p 604-699-2593 c 604-862-9051 email: Cheryl.Katnick@ledcor.com www.ledcor.com

  • FORWARD. TOGETHER.
slide-27
SLIDE 27

26