Geotechnical Aspects of Borders Railway Mine Infill Grouting 1 May - - PowerPoint PPT Presentation

geotechnical aspects of borders railway mine infill
SMART_READER_LITE
LIVE PREVIEW

Geotechnical Aspects of Borders Railway Mine Infill Grouting 1 May - - PowerPoint PPT Presentation

Geotechnical Aspects of Borders Railway Mine Infill Grouting 1 May 15 Geotechnical Aspects of Borders Railway Mine Infill Grouting 2 May 15 Geotechnical Aspects of Borders Railway Mine Infill Grouting 3 May 15 Geotechnical Aspects of


slide-1
SLIDE 1

May 15 1

Geotechnical Aspects of Borders Railway Mine Infill Grouting

slide-2
SLIDE 2

May 15 2

Geotechnical Aspects of Borders Railway Mine Infill Grouting

slide-3
SLIDE 3

May 15 3

Geotechnical Aspects of Borders Railway Mine Infill Grouting

slide-4
SLIDE 4

May 15 4

Geotechnical Aspects of Borders Railway Mine Infill Grouting

slide-5
SLIDE 5

May 15 5

United Kingdom Coalfields

slide-6
SLIDE 6

M74 Glasgow Stirling-Alloa Dolphingstone Borders Railway

May 15 6

slide-7
SLIDE 7

Borders Railway

May 15 7

slide-8
SLIDE 8

Borders Railway - Design

− URS design − 1.75m perimeter hole spacing − 3.75 or 1.75m infill hole spacing − Rock Cover to the seams

  • Depth of treatment uses 10:1 cover ratio principle
  • Beneath structures 10:1 applies but with min 30m

cover

  • Angle of draw on the permanent way = 2V:1H

May 15 8

slide-9
SLIDE 9

Borders Railway Shafts

May 15 9

slide-10
SLIDE 10

The way we worked…..

  • 50Nr weeks on-site
  • 1125Nr rig shifts (10 Nr rigs)
  • 250,000 linear metres drilled
  • 5000te of grout injected
  • 11Nr mine shafts consolidated
  • 2.5km of consolidated railway
slide-11
SLIDE 11

Exploring New Horizons

May 15 11

New Plant

  • State of the art Bulk Mixing Unit utilised within

Cementation Skanska for the first time. Materials loaded by a fully automated conveyor belt system

  • Remote control drilling rigs championed, which

allowed the Operator to work remotely from the rig

  • Infra red camera system trialled with a potential to

replace the safety gate system

slide-12
SLIDE 12

Cementation Skanska Rail Capability

  • Access Planning
  • Vegetation Clearance
  • Temporary Works
  • Drainage
  • Earthworks
  • Reinforced Soils
  • Grundomat Piling
  • Ground Anchors
  • Grouting
  • Soil Nails
  • Mini Piling
  • Sheet Piling
  • Gabion Baskets
  • Reinforced Concrete
  • Planting
  • Fencing & Handrails
  • In Ground Instrumentation
  • Track Monitoring

May 15 12

slide-13
SLIDE 13

Relationships that Work

  • Over 10 years of working together
  • Nearly £10 million worth of work

executed

− Dolphingstone, East Coast Main line − Stirling to Alloa Railway Link − Borders Railway

13