May 15 1
Geotechnical Aspects of Borders Railway Mine Infill Grouting 1 May - - PowerPoint PPT Presentation
Geotechnical Aspects of Borders Railway Mine Infill Grouting 1 May - - PowerPoint PPT Presentation
Geotechnical Aspects of Borders Railway Mine Infill Grouting 1 May 15 Geotechnical Aspects of Borders Railway Mine Infill Grouting 2 May 15 Geotechnical Aspects of Borders Railway Mine Infill Grouting 3 May 15 Geotechnical Aspects of
May 15 2
Geotechnical Aspects of Borders Railway Mine Infill Grouting
May 15 3
Geotechnical Aspects of Borders Railway Mine Infill Grouting
May 15 4
Geotechnical Aspects of Borders Railway Mine Infill Grouting
May 15 5
United Kingdom Coalfields
M74 Glasgow Stirling-Alloa Dolphingstone Borders Railway
May 15 6
Borders Railway
May 15 7
Borders Railway - Design
− URS design − 1.75m perimeter hole spacing − 3.75 or 1.75m infill hole spacing − Rock Cover to the seams
- Depth of treatment uses 10:1 cover ratio principle
- Beneath structures 10:1 applies but with min 30m
cover
- Angle of draw on the permanent way = 2V:1H
May 15 8
Borders Railway Shafts
May 15 9
The way we worked…..
- 50Nr weeks on-site
- 1125Nr rig shifts (10 Nr rigs)
- 250,000 linear metres drilled
- 5000te of grout injected
- 11Nr mine shafts consolidated
- 2.5km of consolidated railway
Exploring New Horizons
May 15 11
New Plant
- State of the art Bulk Mixing Unit utilised within
Cementation Skanska for the first time. Materials loaded by a fully automated conveyor belt system
- Remote control drilling rigs championed, which
allowed the Operator to work remotely from the rig
- Infra red camera system trialled with a potential to
replace the safety gate system
Cementation Skanska Rail Capability
- Access Planning
- Vegetation Clearance
- Temporary Works
- Drainage
- Earthworks
- Reinforced Soils
- Grundomat Piling
- Ground Anchors
- Grouting
- Soil Nails
- Mini Piling
- Sheet Piling
- Gabion Baskets
- Reinforced Concrete
- Planting
- Fencing & Handrails
- In Ground Instrumentation
- Track Monitoring
May 15 12
Relationships that Work
- Over 10 years of working together
- Nearly £10 million worth of work
executed
− Dolphingstone, East Coast Main line − Stirling to Alloa Railway Link − Borders Railway
13