APS SUBSTATION ZONE CHANGE/CONDITIONAL USE PERMIT PLANNING - - PowerPoint PPT Presentation

aps substation
SMART_READER_LITE
LIVE PREVIEW

APS SUBSTATION ZONE CHANGE/CONDITIONAL USE PERMIT PLANNING - - PowerPoint PPT Presentation

APS SUBSTATION ZONE CHANGE/CONDITIONAL USE PERMIT PLANNING COMMISSION PUBLIC HEARING MAY 21, 2019 Application Arizona Public Service is requesting a Zone Change to commercial and a Conditional Use Permit for a Public Utility to construct


slide-1
SLIDE 1

APS SUBSTATION

ZONE CHANGE/CONDITIONAL USE PERMIT PLANNING COMMISSION PUBLIC HEARING MAY 21, 2019

slide-2
SLIDE 2

Application

  • Arizona Public Service is requesting a Zone Change to

commercial and a Conditional Use Permit for a Public Utility to construct a substation

  • The parcel is 1591 SR 89A located on the south side of SR

89A between Clarkdale & Jerome

  • Adjacent to future Verde Valley Fire Station
  • Parcel is approximately 2.29 acres
  • Property is zoned R1-Single family residential – could allow

development of nine new single family homes

slide-3
SLIDE 3
slide-4
SLIDE 4

Zoning

slide-5
SLIDE 5

Why this location?

  • The substation must connect to a 69KV line
  • There is an existing 69KV line running south of the proposed

location

  • 69KV lines are exempt from being required to be

underground per Arizona State Statute

  • Property owner was willing to sell this parcel to APS
slide-6
SLIDE 6

Other possible locations

  • The only zoning district which

addresses public utilities is Commercial

  • In a Commercial Zone, a Conditional

Use Permit is required

  • Public utilities are not listed as either a

permitted use or conditional use in the Industrial Zone

slide-7
SLIDE 7

Considerations for a Zone Change Request

APS SUBSTATION APPLICATION

slide-8
SLIDE 8

General Plan Designation

  • Designated as Neighborhood

Commercial

  • This classification is intended for

commercial retail and service businesses

  • Site is under 100 acres-no minor

General Plan Amendment required

  • Objective 9.1 of the 2012

General Plan: Promote infrastructure expansion where it will be most efficient and effective while minimizing adverse impacts outside the identified areas

slide-9
SLIDE 9

Buffering

  • With the proposed

construction of the Fire Station to the east, the substation will be abutting a commercial use.

  • The proposed site design

leaves a 40-foot buffer to the residentially zoned property to the west and south.

  • Approximately an acre in

size based on engineering drawings

  • Wall enclosure structure is

approximately 190 feet by 214 feet

slide-10
SLIDE 10

Other considerations

  • Traffic will be minimal once construction is complete
  • Per the applicant, noise will be minimal. The project is

subject to the Town’s noise regulations.

  • Through conditions of approval and building permit

requirements, the proposed substation shall conform to all existing zoning regulations.

slide-11
SLIDE 11

Community Benefits

  • Improve service for existing customers
  • Serve future growth
  • Preserving social trail
  • Reducing traffic impact to SR 89A through shared

driveway with Fire Station

  • Installation of a utility infrastructure is listed in Section 13-

020.F as a specific consideration for approval of a zone change.

slide-12
SLIDE 12

Required Findings for a Conditional Use Permit

  • Compatibility of land use
slide-13
SLIDE 13

Adequacy of Site

  • The structure is

approximately 1-acre in size on a 2.29 acre parcel

  • Approximately 40 foot

buffer around the structure walls

  • The site will be

excavated and the equipment placed subgrade

slide-14
SLIDE 14

Performance

  • APS will coordinate with Unisource

regarding the gas main that traverses the frontage of the property

  • No batteries will be stored at the

substation

  • Traffic will be minimal after construction
  • Landscaping will meet code with

accommodations regarding gas line along frontage

  • The height of the wall can be raised to

provide greater screening

  • APS is willing to work with the community

to enhance the look of the exterior walls

slide-15
SLIDE 15

Site Renderings

  • Photo Renderings
slide-16
SLIDE 16

Zone Change Implications

  • The proposed location of the APS substation is adjacent to

a busy state highway. This site was selected specifically by APS due to the proximity of the existing overhead 69KV lines.

  • Although there are other commercially zoned properties,

specifically along SR89A between Cottonwood and Clarkdale and along the Broadway Corridor, locating the new substation in these areas would have a comparable community impact with the additional requirement of needing to extend the overhead power lines.

slide-17
SLIDE 17

Staff Analysis

  • In staff’s opinion, the zone change to Commercial is

reasonable considering the location of the property adjacent to a state highway.

  • Installation of utility infrastructure is specifically identified as

a community benefit eligible for consideration of a zone change request as listed in Section 13-020.D of the Zoning Code.

  • The proposed substation will provide more reliable service

to current customers and the ability to serve future growth.

  • With the recommended conditions, the application is in

compliance with the required findings for a Conditional Use Permit.

slide-18
SLIDE 18

Recommended Conditions of Approval

1. The Zone Change/Conditional Use Permit is void if a building permit is not issued within one year of approval of this Zone Change/Conditional Use Permit application. 2. The established social foot path parallel to SR 89A and within the ADOT right-of- way shall remain accessible to pedestrian traffic except during construction when it shall be rerouted as much as possible. 3. No porta potties shall remain on site after construction is completed. 4. All landscaping shall conform with the Landscape Design Standards effective May 10, 2019. 5. Access to the property shall be developed as agreed and in cooperation with the Town of Clarkdale, ADOT and the Verde Valley Fire District. This access shall be designed to be the minimum width necessary to serve projected traffic of both facilities. 6. The installation shall comply with the Town of Clarkdale Zoning Code 11-040 Section 19 regarding noise. Identified violations of the noise regulations in the Town Code shall be immediately remediated. 7. The Landscape Plan shall be modified to include at least fifty percent non- deciduous species to provide year-round screening of the structure wall.

slide-19
SLIDE 19

Applicant Presentation

  • Kendra Lee

APS Franchises & Technical Services

  • Ryan Weed, P.E.

CVL Consultants

slide-20
SLIDE 20

Public Hearing

  • Please address all comments to the Chair
  • When recognized, state your name and whether you are a

resident of Clarkdale

  • Out of respect for everyone’s time, if your comments or

concerns have been stated by a previous speaker, please keep your comments brief

slide-21
SLIDE 21
slide-22
SLIDE 22

Next Steps

  • The Commission may choose to
  • Move the application forward to Council with a recommendation of

approval as conditioned

  • Move the application forward Council with a recommendation of

approval with additional and/or revised conditions

  • Table the application and direct staff and/or APS to:
  • Move the application forward to Council with a recommendation of

denial based on specific findings: