Decision-making process for substation renovation and equipment end - - PowerPoint PPT Presentation

decision making process for substation renovation and
SMART_READER_LITE
LIVE PREVIEW

Decision-making process for substation renovation and equipment end - - PowerPoint PPT Presentation

Decision-making process for substation renovation and equipment end of life assessment C. Neumann (Germany) 2009 IEEE Substations Committee Meeting, Kansas City RWE Transportnetz Strom 08-2008 PAGE 1 Decision-making process for substation


slide-1
SLIDE 1

RWE Transportnetz Strom 08-2008 PAGE 1

Decision-making process for substation renovation and equipment end of life assessment

  • C. Neumann (Germany)

2009 IEEE Substations Committee Meeting, Kansas City

slide-2
SLIDE 2

RWE Transportnetz Strom 04.2009 PAGE 2

Decision-making process for substation renovation and equipment end of life assessment

1.Introduction (German EHV grid) 2.Basic methodology 3.Ascertainment of actual condition 4.Determination of other c - parameters 5.Assessment of end of service life 6.Combination of parameters for decision making 7.Conclusion

slide-3
SLIDE 3

RWE Transportnetz Strom 04.2009 PAGE 3

Introduction

Fundamental changes in the regulatory framework of the electricity

market in the last decade

Intensified efforts of the grid operators for an optimized utilization of

their networks with respect to technical and economical aspects

At the same time the grid operators have to assure a sufficient power

quality & reliability

Substations are the nodes of the grid substantially affecting the

reliability & availability of the grid in total

Substations represent an essential part of the grid assets Of particular interest with regard to optimization of the grid costs, i. e.

investments & operational expenditure – CAPEX & OPEX ⇒ Methodology and decision making process for substation renovation and equipment end of life assessment

slide-4
SLIDE 4

RWE Transportnetz Strom 04.2009 PAGE 4

RWE EON VET EnBW 13 19 30 38 Share load [%]** 1,936 6,700 5,400 5,200 Network length 380 kV [km] 1,721 2,865 5,300 6,100 Network length 220 kV [km] 76 k.A. 138 175 Annual transmission [TWh] 34.6 109.0 139.4 73.1 Served area [1000 km²]* EnBW VET E.ON RWE

* in Germany ** Renewable Energy Act load compensation 2005

German EHV grid

Operational areas of German Transmission System Operators

slide-5
SLIDE 5

RWE Transportnetz Strom 04.2009 PAGE 5

RWE EON VET EnBW

RWE

220 kV transmission lines 380 kV transmission lines

German EHV grid

Operational areas of German Transmission System Operators

slide-6
SLIDE 6

RWE Transportnetz Strom 04.2009 PAGE 6

RWE

220 kV transmission lines 380 kV transmission lines 90,100 MVA 121 110 kV substations 145 220 kV transformer 235 380 kV transformer 110 220 kV substations 62 380 kV substations 6,100 km 220 kV circuits 5,200 km 380 kV circuits

German EHV grid

Operational areas of German Transmission System Operators

slide-7
SLIDE 7

RWE Transportnetz Strom 04.2009 PAGE 7

Information for decision making process

AM ⇔ qualified information of the system and the equipment installed

for the decision making process.

In case of larger population difficult to provide key information manually;

therefore reasonable

– application of data based systems – development of algorithms

Algorithms and method for

– determining near-term action and annual business planning – forecasting the technical and financial effect due to system ageing

Approach based on condition and importance

slide-8
SLIDE 8

RWE Transportnetz Strom 04.2009 PAGE 8

Assessment of condition and importance parameters (1)

Assessment of condition parameters

1. Equipment level regarding equipment specific condition parameters, assessment by school marks

static condition quantities: technology, type related service experience (e. g. after sales service quality, maintenance costs), individual failure rates dynamic condition quantities: age of equipment, individual condition ascertained by inspection and condition checks, interval to next planned maintenance activity

2. Equipment condition parameters accumulated on bay level, weighted according the value of different equipment 3. Assessment on station level → bay condition parameters and on system level → station condition parameters, weighted average mean value

slide-9
SLIDE 9

RWE Transportnetz Strom 04.2009 PAGE 9

Assessment of condition parameters on different levels

  • Subst. A..Z

bay 1

  • Subst. A
  • Subst. B

circuit breaker disconn. arrester protect.

transf.

  • inst. transf.

infrastruct. UPS

  • subst. contr.

bay 2

infrastructure

Equiment level Bay level Substation level System level Condition assessment Condition parameters static quantities dynamic quantities

slide-10
SLIDE 10

RWE Transportnetz Strom 04.2009 PAGE 10

Assessment of condition and importance parameters (2)

Assessment of importance parameters

– Reliability analysis of the different substations – Derived from short circuit power of the station in question weighted by a factor reflecting the relevance of the station in the system

Condition and importance parameters normalised to 100

For reliability analysis failure rates to be

  • regarded. However,

failure rates still considered with condition parameters

slide-11
SLIDE 11

RWE Transportnetz Strom 04.2009 PAGE 11

replacement necessary need for action to be checked maintenance accor- ding to strategy

10 20 30 40 50 60 70 80 90 100 10 20 30 40 50 60 70 80 90 100

small <<<

importance

>>> high good <<< condition >>> bad 380 kV 220 kV 110 kV

Condition and importance on equipment level

Example: Circuit breakers

slide-12
SLIDE 12

RWE Transportnetz Strom 04.2009 PAGE 12

20 40 60 80 30 40 50 60 70 80 importance condition

C tot C pri C sec C pri >50 C sec >50

Condition and importance parameters of a population of 380 kV stations

B C A

slide-13
SLIDE 13

RWE Transportnetz Strom 04.2009 PAGE 14

10 20 30 40 50 60 401 402 403 404 407 409 410 411 bay condition 10 20 30 40 50 60 401 402 403 404 407 409 410 411 bay condition

Condition on station level and bay level – condition above 50 –

20 40 60 80 100 TE1 TE1 TE1 LS WI WU TD2 ATD equipment condition

slide-14
SLIDE 14

RWE Transportnetz Strom 04.2009 PAGE 15

Decision-making process for substation renovation and equipment end of life assessment

  • 1. Introduction
  • 2. Basic methodology
  • 3. Ascertainment of actual condition
  • 4. Determination of other c - parameters
  • 5. Assessment of end of service life
  • 6. Combination of parameters for decision making
  • 7. Conclusion
slide-15
SLIDE 15

RWE Transportnetz Strom 08-2008 PAGE 16

Qualified assessment of actual condition of switching equipment

  • Qualified condition assessment needs knowledge of the equipment

under consideration and the physical background ⇒ experienced and highly skilled personnel.

  • In case of a large amount of different pieces of equipment and of

different types ⇒ high expenditure for training of specialised personnel

New approach: Application of an “automated, user instructed and data based inspection and diagnosis system” (ADS)

  • ADS system in use for HV CBs since several years, for DSs under

development

slide-16
SLIDE 16

RWE Transportnetz Strom 08-2008 PAGE 17

Basic design of “ADS“ system

(automated, user instructed and data based inspection and diagnosis)

SF6-Check Contact travel Contact resistance

static & dynamic

diagnosis box

process control data acquisition data transfer

diagnosis plug

control & supervision of switching process & drive

User assistance

Maintenance expert may control and supervise the process by remote access UMTS

Im Um 1), 2), 3) adaptive sensors 1) 3) 2)

slide-17
SLIDE 17

RWE Transportnetz Strom 08-2008 PAGE 18

ADS Features

  • Diagnostic box → four inputs to record different diagnostic quantities
  • Sequence of the inspection process is automated:
  • After input of the general data of the breaker to be inspected →

maintenance personnel instructed what actions are to be done

  • All quantities are measured & analysed automatically, all results are

stored in a data base

Reliable, objective & qualified assessment of the actual condition

  • f the equipment under consideration
  • Depending on the measuring results and the condition check →

information, if and what corrective measures have to be taken.

slide-18
SLIDE 18

RWE Transportnetz Strom 08-2008 PAGE 19

Results of ADS diagnosis on a 245 kV CB with two interrupter units

20 40 60 80 100 130 20 40 60 80 100 130 2 4 6 8 10 12 14 16 20 [mΩ] 2 4 6 8 10 12 14 16 20 [mΩ 10 20 30 40 50 60 70 80 ms 10 20 30 40 50 60 70 80 ms tripping coil current 0.0 0.4 0.8 1.2 1.6 2.0 [A] [mm]

switching off process

resistance unit 1 & 2

0.0 0.4 0.8 1.2 1.6 2.0 [A] 0.0 0.4 0.8 1.2 1.6 2.0 [A]

contact travel

20 25 30 35

20 25 30 35

[mm]

75 µΩ

slide-19
SLIDE 19

RWE Transportnetz Strom 08-2008 PAGE 20

Data recorded and analysed by a single shot

The following data can be recorded and analysed by a single shot: Static and dynamic contact resistance Operating (making or breaking) time of the main and the auxiliary contacts Contact travel, i. e. velocity and damping Current and time characteristic of the tripping coil In case of an hydraulic drive pressure drop of the hydraulic pressure All measured results are recorded and analyzed automatically and afterwards stored in a data base.

slide-20
SLIDE 20

RWE Transportnetz Strom 04.2009 PAGE 21

  • 1. Introduction
  • 2. Basic methodology
  • 3. Ascertainment of actual condition
  • 4. Determination of other c – parameters
  • Maintenance,
  • after sales service
  • 5. Assessment of end of service life
  • 6. Combination of parameters for decision making
  • 7. Conclusion

Decision-making process for substation renovation and equipment end of life assessment

slide-21
SLIDE 21

RWE Transportnetz Strom 04.2009 PAGE 22

Average overall maintenance costs of 420 kV CBs per CB-year

0,2 0,4 0,6 0,8 1 1,2 1,4 1,6

major event minor event visual inspection special measure planed maint. condition acquisition Average overall maintenance cost per CB-year (in % of new CB cost)

A80s B80s C63s D63s E63s F63s G63s H63s I63o

slide-22
SLIDE 22

RWE Transportnetz Strom 04.2009 PAGE 23

Assessment of after sales service quality (CBs)

Manpower for installation Installation time feasibility of CB reuse Feedback with manufacturer Stuff availability for failure removal Assembly time in case of failure Availability of spare parts Stuff availability for maintenance Quality

  • f maintenance

Cost of maintene- nance package Time of unavaila- bility during maintenance Assessment results

Weight [%]

1.8 8.0 8.0 15.6 8.0 11.6 13.5 5.5 9.8 15.9 3.3 100

Range

1-6 1-6 1-6 1-6 1-6 1-6 1-6 1-6 1-6 1-6 1-6 0-100 Type A80s

3 5 1 2 1 3 1 1 1 3 3 21.6

Type B80s

5 5 6 5 5 5 5 5 5 4 5 78.6

Type C63s

2 2 1 2 1 2 1 1 1 2 2 10.8

Type D63s

5 5 6 2 1 3 1 1 1 3 3 30.6

Type E63s

3 5 1 3 3 2 2 3 3 2 2 31.7

Type F63s

3 5 1 5 5 2 2 3 5 1 1 42.5

Type G63s

5 5 1 5 5 2 2 3 5 1 1 43.2

Type H63s

3 5 1 5 5 3 3 3 5 3 4 53.8

Type I63o

5 5 6 5 5 5 3 3 5 6 6 76.9

Weighting by a decision matrix Best service Worst service 100

slide-23
SLIDE 23

RWE Transportnetz Strom 04.2009 PAGE 24

  • 1. Introduction
  • 2. Basic methodology
  • 3. Ascertainment of actual condition
  • 4. Determination of other c - parameters
  • 5. Assessment of end of service life
  • 6. Combination of parameters for decision making
  • 7. Conclusion

Decision-making process for substation renovation and equipment end of life assessment

slide-24
SLIDE 24

RWE Transportnetz Strom 04.2009 PAGE 25

Average failure rates of 420 kV CBs

5 10 15 20 25 30 35 40 A80s B80s C63s D63s E63s F63s G63s H63s I63o

Average failure rate per 100 CB-years

slide-25
SLIDE 25

RWE Transportnetz Strom 04.2009 PAGE 26

Ageing given by related failure frequency (RFF)

Confidence (98%) Failure event years of service

Example of a certain 420 kV CB type

10 20 30 40 50 60 70 80 90 100 4 8 12 16 20 24 years of service at failure occurrence RFF [%] 20 40 60 80 100 120 years of service

Typical ageing process

– Linear loss of basic substance – Exponentially increasing related failure frequency – Worse service experience for older equipment RFF: Failures per year related to 100 CB years [%]

slide-26
SLIDE 26

RWE Transportnetz Strom 04.2009 PAGE 27

Related failure Frequency (RFF) of 420 kV CBs

Failure Frequency (RFF) of 420 kV circuit breakers with 95% confidence interval

RFF [ % ] /

10 20 30 40 50 60 70 80 90 100 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32

Age (years)

34 36 38 40 Confidenceinterval RFF (minor) RFF (major)

  • Lin. Regression
  • f RFF (major)
  • Exp. Regression
  • f RFF (minor)
  • Exp. Regression
  • f RFF (all CBs)

10 20 30 40 50 60 70 80 90 100 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40

Age (years)

Confidenceinterval RFF (minor) RFF (major)

  • Lin. Regression
  • f RFF

(major)

  • Lin. Regression
  • f RFF

(minor)

  • Exp. Regression
  • f RFF

(all CBs )

RFF [ % ] /

slide-27
SLIDE 27

RWE Transportnetz Strom 04.2009 PAGE 28

20 40 60 80 100 120 140 160 180 200 5 10 15 20 25 30 35 40 45 50 55

Service time [a] utilization factor [%] *)

End of life prognosis due to knowledge of the basic ageing process

after 20 a *) utilization factor => expected life related to nominal service life end of service live earlier end of service live later after 40 a CBs

⇒ In case of accelerated ageing renovation is brought forward, in case of decelerated postponed

slide-28
SLIDE 28

RWE Transportnetz Strom 04.2009 PAGE 29

20 40 60 80 100 120 140 160 180 200 5 10 15 20 25 30 35 40 45 50 55

Service time [a] utilization factor [%] *)

End of life prognosis due to knowledge of the basic ageing process

after 20 a *) utilization factor => expected life related to nominal service life after 40 a CBs DSs arresters

slide-29
SLIDE 29

RWE Transportnetz Strom 04.2009 PAGE 31

End of service life assessment of 380 kV substations*

(equipment with impermissible utilization factor will be exchanged)

Zukun Zense Witte Weste Weiße Wehre Walsu Vöhri Verla Utfor Urber Unna Uentr Uchte Tieng Siers Secht Sankt Roxel Rosen Romme Rath Polsu Paffe Oplad Ohlig Oberz Nordl Niede Niede Nehde Mitte Meppe Menge Meiti Lippb Linde Limbu Liess Leupo Kusen Krupp Krift Koble Knaps Karna Hülle Hohen Hatti Hanek Halfe Gunde Grona Gerst Ennig Eiber Detti Dauer Dahle Büsch Bürst Bisch Arpe Arpe Bisch Bürst Büsch Dahle Dauer Detti Eiber Ennig Gerst Grona Gunde Halfe Hanek Hatti Hohen Hülle Karna Knaps Koble Krift Krupp Kusen Leupo Liess Limbu Linde Lippb Meiti Menge Meppe Mitte Nehde Niede Niede Nordl Oberz Ohlig Oplad Paffe Polsu Rath Romme Rosen Roxel Sankt Secht Siers Tieng Uchte Uentr Unna Urber Utfor Verla Vöhri Walsu Wehre Weiße Weste Witte Zense Zukun Arpe Bisch Bürst Büsch Dahle Dauer Detti Eiber Ennig Gerst Grona Gunde Halfe Hanek Hatti Hohen Hülle Karna Knaps Koble Krift Krupp Kusen Leupo Liess Limbu Linde Lippb Meiti Menge Meppe Mitte Nehde Niede Niede Nordl Oberz Ohlig Oplad Paffe Polsu Rath Romme Rosen Roxel Sankt Secht Siers Tieng Uchte Uentr Unna Urber Utfor Verla Vöhri Walsu Wehre Weiße Weste Witte Zense Zukun Zukun Zense Witte Weste Weiße Wehre Walsu Vöhri Verla Utfor Urber Unna Uentr Uchte Tieng Siers Secht Sankt Roxel Rosen Romme Rath Polsu Paffe Oplad Ohlig Oberz Nordl Niede Niede Nehde Mitte Meppe Menge Meiti Lippb Linde Limbu Liess Leupo Kusen Krupp Krift Koble Knaps Karna Hülle Hohen Hatti Hanek Halfe Gunde Grona Gerst Ennig Eiber Detti Dauer Dahle Büsch Bürst Bisch Arpe

10 20 30 40 50 60 70 80 90 100 10 20 30 40 50 60 70 80 90 100 small<<< importance >>> high small <<< >>> high

actual + 10 a + 5 a + 20 a utilization factor [%] *)

slide-30
SLIDE 30

RWE Transportnetz Strom 04.2009 PAGE 32

Conclusion

For support of the decision making process for substation renovation

the asset management needs simple, but technically justified and effective method for assessment

–of actual conditions of the equipment –end of equipment life

Methods and algorithms described provide qualified information

– for determining near-term action and annual business planning –also for forecasting the technical and financial effect due to system ageing.

slide-31
SLIDE 31

RWE Transportnetz Strom 08-2008 PAGE 33

Thanks for Your attention!

Decision-making process for substation renovation and equipment end of life assessment