2010 lcr study big creek ventura and la basin
play

2010 LCR Study Big Creek/Ventura and LA Basin Yi Zhang Regional - PowerPoint PPT Presentation

2010 LCR Study Big Creek/Ventura and LA Basin Yi Zhang Regional Transmission Engineer Stakeholder Meeting March 10, 2009 Big Creek/Ventura Area Big Creek/Ventura Area Magunden Rector Substation Substation Vestal Substation Victorville


  1. 2010 LCR Study Big Creek/Ventura and LA Basin Yi Zhang Regional Transmission Engineer Stakeholder Meeting March 10, 2009

  2. Big Creek/Ventura Area Big Creek/Ventura Area Magunden Rector Substation Substation Vestal Substation Victorville Substation Pardee Substation Lugo Substation Sylmar Substation Slide 2

  3. Big Creek/Ventura Boundary Transmission Lines Big Creek/Ventura Boundary Transmission Lines  Vincent-Antelope 230 kV Line  Mesa-Antelope 230 kV Line  Sylmar-Pardee #1 230 kV Line  Sylmar-Pardee #2 230 kV Line  Eagle Rock-Pardee #1 230 kV Line  Antelope-Pardee 230 kV Line  Vincent-Santa Clara 230 kV Line Slide 3

  4. Big Creek/Ventura Area 2010 Load & Resources Big Creek/Ventura Area 2010 Load & Resources Load Load Pump Load Transmission Losses Total (MW) (MW) (MW) (MW) 4744 405 107 5256 Available Generation QF/Wind Muni Nuclear Market Max. Qualifying Capacity (MW) (MW) (MW) (MW) (MW) Available Gen 909 22 0 4229 5160 Slide 4

  5. Rector and Vestal Sub- -areas areas Rector and Vestal Sub Rector: Contingency: Vestal-Rector #1 or #2 230 kV line with Eastwood unit out of service Limiting component: thermal overload the remaining Vestal-Rector #1 or #2 230 kV line LCR Need: 687 MW (includes 15 MW of QF/Wind generation) Vestal: Contingency: Magunden-Vestal #1 or #2 230 kV line with Eastwood unit out of service Limiting components: thermal overload the remaining Magunden- Vestal #1 or #2 230 kV line LCR Need: 810 MW (includes 122 MW of QF/Wind generation) All resources in Rector apply towards the LCR need in Vestal sub-area. Slide 5

  6. Big Creek/Ventura Overall Big Creek/Ventura Overall Category B LCR: Contingency: Sylmar-Pardee #1 or #2 230 kV line with Ormond Beach #2 unit out of service Limiting component: thermal overload the remaining Sylmar-Pardee #1 or #2 230 kV line LCR Need: 3451 MW (includes 836 MW of QF, 22 MW of Muni and 73 MW of wind generation) Category C LCR: Contingency: Lugo-Victorville 500 kV followed by the loss of Sylmar- Pardee #1 or #2 230 kV line or vice versa Limiting components: thermal overload the remaining Sylmar-Pardee #1 or #2 230 kV line LCR Need: 3596 MW (includes 836 MW of QF, 22 MW of Muni and 73 MW of wind generation) Slide 6

  7. Changes since the 2009 LCR study Total Big Creek/Ventura LCR need has increased • Load forecast is up by 319 MW • One new peaker is modeled in this area • Overall the LCR has increased by 418 MW Slide 7

  8. LA Basin Area LA Basin Area Slide 8

  9. LA Basin Area Boundary Transmission Lines LA Basin Area Boundary Transmission Lines  San Onofre - San Luis Rey #1, #2, & #3 230 kV Lines  San Onofre - Talega #1 & #2 230 kV Lines  Lugo - Mira Loma #2, #3 500 kV Lines  Lugo – Rancho Vista #1 500 kV Lines  Sylmar - Eagle Rock 230 kV Line  Sylmar - Gould 230 kV Line  Vincent - Mesa Cal 230 kV Line  Antelope - Mesa Cal 230 kV Line  Vincent - Rio Hondo #1 & #2 230 kV Lines  Eagle Rock - Pardee 230 kV Line  Devers - Palo Verde 500 kV Line  Mirage - Coachelv 230 kV Line  Mirage - Ramon 230 kV Line  Mirage - Julian Hinds 230 kV Line Slide 9

  10. LA Basin Area 2010 Load & Resources LA Basin Area 2010 Load & Resources Load Load Pump Load Transmission Losses Total (MW) (MW) (MW) (MW) 19526 20 519 20065 Available Generation QF/Wind Muni Nuclear Market Max. Qualifying (MW) (MW) (MW) (MW) Capacity (MW) Available Gen 908 788 2246 8259 12201 Slide 10

  11. Western LA Basin Sub- -area area Western LA Basin Sub Contingency: The loss of the Serrano – Villa Park #1 or #2 and Serrano – Lewis 230 kV lines Limiting components: thermal overload of the remaining Serrano – Villa Park #1 or #2 230 kV line LCR Need: 4909 MW (includes 491 MW of QF/Wind, 383 MW of Muni and 2246 MW of nuclear generation) Slide 11

  12. LA Basin Overall LA Basin Overall Contingency: Palo Verde-Devers 500 kV line with SONGS #2 unit out of service Limiting Component: South of Lugo operating rating (6400 MW with new Rancho Vista 500kV substation) LCR Need: 9735 MW (includes 908 MW of QF/Wind, 788 MW of Muni and 2246 MW of nuclear generation) Slide 12

  13. Changes since the 2009 LCR study Total La Basin LCR need is steady • Load forecast is up by 230 MW • Two new peakers modeled in the area • Remove Barre sub-area • Add Western LA Basin sub-area • The total LCR need has increased by 8 MW Slide 13

  14. Stakeholder Comments Stakeholder Comments Your comments and questions are welcome Your comments and questions are welcome For written comments, please send to: RegionalTransmission@caiso.com Slide 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend