local capacity requirements lcr for year 2009 local
play

Local Capacity Requirements (LCR) for Year 2009 Local Capacity - PowerPoint PPT Presentation

Local Capacity Requirements (LCR) for Year 2009 Local Capacity Requirements (LCR) for Year 2009 Study Results for the Big Creek/ Ventura and LA Study Results for the Big Creek/ Ventura and LA Basin Areas Basin Areas LCR Stakeholder Meeting,


  1. Local Capacity Requirements (LCR) for Year 2009 Local Capacity Requirements (LCR) for Year 2009 Study Results for the Big Creek/ Ventura and LA Study Results for the Big Creek/ Ventura and LA Basin Areas Basin Areas LCR Stakeholder Meeting, April 10 th , 2008, Folsom CA Yi Zhang Regional Transmission Engineer Department of Planning and Infrastructure Development California Independent System Operator (CAISO)

  2. Changes since last Stakeholder meeting Big Creek/Ventura: � Change the Antelope-Pardee sub-area need into second worst for BC/Ventura. Update QF units in Ventura. � ATP (Antelope Transmission Project) Segments 1, 2 and 3 modeled. (Includes the opening of the existing Antelope-Vincent and Antelope- Mesa 230 kV lines) LA Basin: � New sub-area El Nido � Change Barre LCR in order to correctly account for the NQC available. Stakeholder Meeting, April 10 th , 2008 – LCR 2009 2

  3. Table of Contents Table of Contents Big Creek/Ventura LCR Study � Rector sub-area � Vestal sub-area � Big Creek – Ventura • Antelope – Vincent • Sylmar - Pardee LA Basin LCR Study � El Nido sub-area � Barre sub-area � LA Basin Stakeholder Meeting, April 10 th , 2008 – LCR 2009 3

  4. Big Creek/ Ventura Boundary Transmission Lines Big Creek/ Ventura Boundary Transmission Lines Vincent-Antelope #1 230 kV Line (out of service) Vincent-Antelope #2 230 kV Line (new) Mesa-Antelope 230 kV Line (out of service) Sylmar-Pardee #1 230 kV Line Sylmar-Pardee #2 230 kV Line Eagle Rock-Pardee #1 230 kV Line Vincent-Pardee 230 kV Line Vincent-Santa Clara 230 kV Line Stakeholder Meeting, April 10 th , 2008 – LCR 2009 4

  5. Big Creek/ Ventura Area 2009 Load & Resources Big Creek/ Ventura Area 2009 Load & Resources Load Load Pump Load Transmission Losses Total (MW) (MW) (MW) (MW) 4415 405 151 4971 Available Generation QF/Wind Muni Nuclear Market Max. Qualifying Capacity (MW) (MW) (MW) (MW) (MW) Available Gen 909 22 0 4201 5132 Stakeholder Meeting, April 10 th , 2008 – LCR 2009 5

  6. Big Creek/ Ventura Area Big Creek/ Ventura Area Magunden Rector Substation Substation Vestal Substation Victorville Substation Pardee Substation Lugo Substation Sylmar Substation Stakeholder Meeting, April 10 th , 2008 – LCR 2009 6

  7. Rector Sub- -area LCR Study area LCR Study Rector Sub Most critical contingency: � The loss of one of the Vestal-Rector 230kV lines followed by the loss of Eastwood generation Limiting components: � Thermally overload the remaining Vestal-Rector 230 kV line. LCR: � 603 MW (includes 15 MW QF/Wind generation) Stakeholder Meeting, April 10 th , 2008 – LCR 2009 7

  8. Vestal Sub- -area LCR Study area LCR Study Vestal Sub Most critical contingency: � The loss of one of the Magunden-Vestal 230kV lines followed by the loss of Eastwood generation Limiting components: � Thermally overload the remaining Magunden-Vestal 230 kV line. LCR: � 733 MW (includes 122 MW of QF/Wind generation) Stakeholder Meeting, April 10 th , 2008 – LCR 2009 8

  9. Big Creek/ Ventura Area LCR Study Big Creek/ Ventura Area LCR Study (Worst constraint) (Worst constraint) Category B LCR: � Most critical contingency: • The loss of Ormond Beach #2 unit followed by the loss of Sylmar-Pardee #1 or #2 230 kV line � Limiting components: • Thermally overload the remaining Sylmar-Pardee #1 or #2 230 kV line (emergency rating 1195MVA/3000 Amps modeled in the base case). � LCR: • 3178 MW (includes 836 MW of QF, 22 MW of Muni and 73 MW of wind generation) Category C LCR: � Second Most critical contingency: • The loss of Lugo-Victorville 500 kV followed by the loss of Sylmar-Pardee #1 or #2 230 kV line � Limiting components: • Thermally overload the remaining Sylmar-Pardee #1 or #2 230 kV line (emergency rating 1195MVA/3000 Amps modeled in the base case). � LCR: • 3136 MW (includes 836 MW of QF, 22 MW of Muni and 73 MW of wind generation) Stakeholder Meeting, April 10 th , 2008 – LCR 2009 9

  10. Changes since the 2008 LCR study Total Big Creek/Ventura LCR has decreased • Load forecast is up by 26 MW • Detailed sub-area analysis has been presented • One new peaker modeled in the area • New project Antelope Transmission Project (New Segments 1, 2 and 3 plus the opening of the existing Antelope-Vincent and Antelope-Mesa 230 kV lines) has reduced the LCR • Overall the LCR has decreased by 480 MW Stakeholder Meeting, April 10 th , 2008 – LCR 2009 10

  11. LA Basin Area Stakeholder Meeting, April 10 th , 2008 – LCR 2009 11

  12. LA Basin Area Boundary Transmission Lines LA Basin Area Boundary Transmission Lines San Onofre - San Luis Rey #1, #2, & #3 230 kV Lines San Onofre - Talega #1 & #2 230 kV Lines Lugo - Mira Loma #1, #2 & #3 500 kV Lines Sylmar - Eagle Rock 230 kV Line Sylmar - Gould 230 kV Line Vincent - Mesa Cal 230 kV Line Antelope - Mesa Cal 230 kV Line Vincent - Rio Hondo #1 & #2 230 kV Lines Eagle Rock - Pardee 230 kV Line Devers - Palo Verde 500 kV Line Devers - Coachelv 230 kV Line Mirage - Ramon 230 kV Line Mirage - Julian Hinds 230 kV Line Stakeholder Meeting, April 10 th , 2008 – LCR 2009 12

  13. LA Basin Area 2009 Load & Resources LA Basin Area 2009 Load & Resources Load Load Pump Load Transmission Losses Total (MW) (MW) (MW) (MW) 19612 22 202 19836 Available Generation QF/Wind Muni Nuclear Market Max. Qualifying (MW) (MW) (MW) (MW) Capacity (MW) Available Gen 908 788 2246 8222 12164 Stakeholder Meeting, April 10 th , 2008 – LCR 2009 13

  14. El Nido Sub-area Critical contingency: The loss of La Fresa-El Nido Chevmain #1 and #2 230 kV El Segundo Limited component: La Fresa-La Cienega 230 kV line LA Fresa LCR: � Assumed that firm load shed Laguna Bell can be done manually within 15 minutes after the contingency: 297 MW in 2009 Hinson (includes 1 MW of QF generation) El � If the load shed is not Redondo Nido possible: 347 MW in 2009 (includes 1 MW of QF LA Cienega generation). Stakeholder Meeting, April 10 th , 2008 – LCR 2009 14

  15. Barre Sub Sub- -area area Barre Barre Substation Ellis Substation Huntington Beach Generation Santiago Substation San Onofre Substation Stakeholder Meeting, April 10 th , 2008 – LCR 2009 15

  16. Barre Sub Sub- -area LCR Study area LCR Study Barre Most critical contingency: � The loss of the Ellis-Barre 230kV line followed by the double line outage of Songs-Santiago 230kV lines Limiting components: � Voltage collapse in the Barre sub-area LCR: � 4173 MW (includes 491 MW of QF/Wind, 383 MW of Muni and 0 MW of nuclear generation) Stakeholder Meeting, April 10 th , 2008 – LCR 2009 16

  17. LA Basin LCR Study LA Basin LCR Study Most Critical Contingency: � The loss of one of the SONGS units, followed by the loss of Palo Verde-Devers 500 kV line Limiting Components: � South of Lugo operating rating (6400 MW with new Rancho Vista 500kV substation) LCR: � 10225 MW (includes 908 MW of QF/Wind, 788 MW of Muni and 2246 MW of nuclear generation) Stakeholder Meeting, April 10 th , 2008 – LCR 2009 17

  18. Changes since the 2008 LCR study Total LA Basin LCR has slightly increased • Load forecast is up by 188 MW • New sub-area analysis El Nido presented • Two new peakers modeled in the area • New project Rancho Vista 500 kV Substation • Voltage collapse in the Barre area (a non-linear problem) has increased substantially (about 1000 MW) for a rather small change in load and as a result resources in that sub-area need to be on-line when the LA Basin calculation is done. They displace some resources that would otherwise be much more effective to the overall problem the South of Lugo constraint • Overall the LCR has increased by 95 MW Stakeholder Meeting, April 10 th , 2008 – LCR 2009 18

  19. Stakeholder Comments Stakeholder Comments Your comments and questions are welcome Your comments and questions are welcome For written comments, please send to: RegionalTransmission@caiso.com Stakeholder Meeting, April 10 th , 2008 – LCR 2009 19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend