Local Capacity Requirements (LCR) for Year 2009 Local Capacity - - PowerPoint PPT Presentation

local capacity requirements lcr for year 2009 local
SMART_READER_LITE
LIVE PREVIEW

Local Capacity Requirements (LCR) for Year 2009 Local Capacity - - PowerPoint PPT Presentation

Local Capacity Requirements (LCR) for Year 2009 Local Capacity Requirements (LCR) for Year 2009 Study Results for the Big Creek/ Ventura and LA Study Results for the Big Creek/ Ventura and LA Basin Areas Basin Areas LCR Stakeholder Meeting,


slide-1
SLIDE 1

Local Capacity Requirements (LCR) for Year 2009 Local Capacity Requirements (LCR) for Year 2009 Study Results for the Big Creek/ Ventura and LA Study Results for the Big Creek/ Ventura and LA Basin Areas Basin Areas

Yi Zhang Regional Transmission Engineer Department of Planning and Infrastructure Development California Independent System Operator (CAISO) LCR Stakeholder Meeting, April 10th, 2008, Folsom CA

slide-2
SLIDE 2

2

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Changes since last Stakeholder meeting

Big Creek/Ventura:

Change the Antelope-Pardee sub-area need into second worst for BC/Ventura. Update QF units in Ventura. ATP (Antelope Transmission Project) Segments 1, 2 and 3 modeled. (Includes the opening of the existing Antelope-Vincent and Antelope- Mesa 230 kV lines)

LA Basin:

New sub-area El Nido Change Barre LCR in order to correctly account for the NQC available.

slide-3
SLIDE 3

3

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Table of Contents Table of Contents

Big Creek/Ventura LCR Study Rector sub-area Vestal sub-area Big Creek – Ventura

  • Antelope – Vincent
  • Sylmar - Pardee

LA Basin LCR Study El Nido sub-area Barre sub-area LA Basin

slide-4
SLIDE 4

4

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Big Creek/ Ventura Boundary Transmission Lines Big Creek/ Ventura Boundary Transmission Lines

Vincent-Antelope #1 230 kV Line (out of service) Vincent-Antelope #2 230 kV Line (new) Mesa-Antelope 230 kV Line (out of service) Sylmar-Pardee #1 230 kV Line Sylmar-Pardee #2 230 kV Line Eagle Rock-Pardee #1 230 kV Line Vincent-Pardee 230 kV Line Vincent-Santa Clara 230 kV Line

slide-5
SLIDE 5

5

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Big Creek/ Ventura Area 2009 Load & Resources Big Creek/ Ventura Area 2009 Load & Resources

Available Generation

Load

QF/Wind (MW) Muni (MW) Nuclear (MW) Market (MW)

  • Max. Qualifying Capacity

(MW) Available Gen 909 22 4201 5132

Load (MW) Pump Load (MW) Transmission Losses (MW) Total (MW) 4415 405 151 4971

slide-6
SLIDE 6

6

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Big Creek/ Ventura Area Big Creek/ Ventura Area

Lugo Substation Victorville Substation Pardee Substation Sylmar Substation Magunden Substation Vestal Substation Rector Substation

slide-7
SLIDE 7

7

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Rector Sub Rector Sub-

  • area LCR Study

area LCR Study

Most critical contingency:

  • The loss of one of the Vestal-Rector 230kV lines followed by the

loss of Eastwood generation Limiting components:

  • Thermally overload the remaining Vestal-Rector 230 kV line.

LCR:

  • 603 MW (includes 15 MW QF/Wind generation)
slide-8
SLIDE 8

8

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Vestal Sub Vestal Sub-

  • area LCR Study

area LCR Study

Most critical contingency:

  • The loss of one of the Magunden-Vestal 230kV lines followed by

the loss of Eastwood generation Limiting components:

  • Thermally overload the remaining Magunden-Vestal 230 kV line.

LCR:

  • 733 MW (includes 122 MW of QF/Wind generation)
slide-9
SLIDE 9

9

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Big Creek/ Ventura Area LCR Study Big Creek/ Ventura Area LCR Study (Worst constraint) (Worst constraint)

Category B LCR:

  • Most critical contingency:
  • The loss of Ormond Beach #2 unit followed by the loss of Sylmar-Pardee #1
  • r #2 230 kV line
  • Limiting components:
  • Thermally overload the remaining Sylmar-Pardee #1 or #2 230 kV line

(emergency rating 1195MVA/3000 Amps modeled in the base case).

  • LCR:
  • 3178 MW (includes 836 MW of QF, 22 MW of Muni and 73 MW of wind

generation) Category C LCR:

  • Second Most critical contingency:
  • The loss of Lugo-Victorville 500 kV followed by the loss of Sylmar-Pardee #1
  • r #2 230 kV line
  • Limiting components:
  • Thermally overload the remaining Sylmar-Pardee #1 or #2 230 kV line

(emergency rating 1195MVA/3000 Amps modeled in the base case).

  • LCR:
  • 3136 MW (includes 836 MW of QF, 22 MW of Muni and 73 MW of wind

generation)

slide-10
SLIDE 10

10

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Changes since the 2008 LCR study

Total Big Creek/Ventura LCR has decreased

  • Load forecast is up by 26 MW
  • Detailed sub-area analysis has been presented
  • One new peaker modeled in the area
  • New project Antelope Transmission Project (New Segments 1, 2

and 3 plus the opening of the existing Antelope-Vincent and Antelope-Mesa 230 kV lines) has reduced the LCR

  • Overall the LCR has decreased by 480 MW
slide-11
SLIDE 11

11

Stakeholder Meeting, April 10th, 2008 – LCR 2009

LA Basin Area

slide-12
SLIDE 12

12

Stakeholder Meeting, April 10th, 2008 – LCR 2009

LA Basin Area Boundary Transmission Lines LA Basin Area Boundary Transmission Lines

San Onofre - San Luis Rey #1, #2, & #3 230 kV Lines San Onofre - Talega #1 & #2 230 kV Lines Lugo - Mira Loma #1, #2 & #3 500 kV Lines Sylmar - Eagle Rock 230 kV Line Sylmar - Gould 230 kV Line Vincent - Mesa Cal 230 kV Line Antelope - Mesa Cal 230 kV Line Vincent - Rio Hondo #1 & #2 230 kV Lines Eagle Rock - Pardee 230 kV Line Devers - Palo Verde 500 kV Line Devers - Coachelv 230 kV Line Mirage - Ramon 230 kV Line Mirage - Julian Hinds 230 kV Line

slide-13
SLIDE 13

13

Stakeholder Meeting, April 10th, 2008 – LCR 2009

LA Basin Area 2009 Load & Resources LA Basin Area 2009 Load & Resources

QF/Wind (MW) Muni (MW) Nuclear (MW) Market (MW)

  • Max. Qualifying

Capacity (MW) Available Gen 908 788 2246 8222 12164

Load (MW) Pump Load (MW) Transmission Losses (MW) Total (MW) 19612 22 202 19836

Available Generation

Load

slide-14
SLIDE 14

14

Stakeholder Meeting, April 10th, 2008 – LCR 2009

El Nido Sub-area

Critical contingency: The loss of La Fresa-El Nido #1 and #2 230 kV Limited component: La Fresa-La Cienega 230 kV line LCR: Assumed that firm load shed can be done manually within 15 minutes after the contingency: 297 MW in 2009 (includes 1 MW of QF generation) If the load shed is not possible: 347 MW in 2009 (includes 1 MW of QF generation).

El Segundo Chevmain LA Fresa El Nido Laguna Bell Hinson Redondo LA Cienega

slide-15
SLIDE 15

15

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Barre Barre Sub Sub-

  • area

area

Barre Substation Ellis Substation Huntington Beach Generation Santiago Substation San Onofre Substation

slide-16
SLIDE 16

16

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Barre Barre Sub Sub-

  • area LCR Study

area LCR Study

Most critical contingency:

  • The loss of the Ellis-Barre 230kV line followed by the double line
  • utage of Songs-Santiago 230kV lines

Limiting components:

  • Voltage collapse in the Barre sub-area

LCR:

  • 4173 MW (includes 491 MW of QF/Wind, 383 MW of Muni and 0

MW of nuclear generation)

slide-17
SLIDE 17

17

Stakeholder Meeting, April 10th, 2008 – LCR 2009

LA Basin LCR Study LA Basin LCR Study

Most Critical Contingency:

  • The loss of one of the SONGS units, followed by the loss of Palo

Verde-Devers 500 kV line Limiting Components:

  • South of Lugo operating rating (6400 MW with new Rancho Vista

500kV substation) LCR:

  • 10225 MW (includes 908 MW of QF/Wind, 788 MW of Muni and

2246 MW of nuclear generation)

slide-18
SLIDE 18

18

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Changes since the 2008 LCR study

Total LA Basin LCR has slightly increased

  • Load forecast is up by 188 MW
  • New sub-area analysis El Nido presented
  • Two new peakers modeled in the area
  • New project Rancho Vista 500 kV Substation
  • Voltage collapse in the Barre area (a non-linear problem) has

increased substantially (about 1000 MW) for a rather small change in load and as a result resources in that sub-area need to be on-line when the LA Basin calculation is done. They displace some resources that would otherwise be much more effective to the

  • verall problem the South of Lugo constraint
  • Overall the LCR has increased by 95 MW
slide-19
SLIDE 19

19

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Stakeholder Comments Stakeholder Comments

Your comments and questions are welcome Your comments and questions are welcome

For written comments, please send to: RegionalTransmission@caiso.com