Local Capacity Requirements (LCR) for Year 2009 Local Capacity - - PowerPoint PPT Presentation

local capacity requirements lcr for year 2009 local
SMART_READER_LITE
LIVE PREVIEW

Local Capacity Requirements (LCR) for Year 2009 Local Capacity - - PowerPoint PPT Presentation

Local Capacity Requirements (LCR) for Year 2009 Local Capacity Requirements (LCR) for Year 2009 Study Results for the Sierra and Stockton Areas Study Results for the Sierra and Stockton Areas LCR Stakeholder Meeting, April 10 th , 2008, Folsom CA


slide-1
SLIDE 1

Local Capacity Requirements (LCR) for Year 2009 Local Capacity Requirements (LCR) for Year 2009 Study Results for the Sierra and Stockton Areas Study Results for the Sierra and Stockton Areas

Catalin Micsa Senior Regional Transmission Engineer Department of Planning and Infrastructure Development California Independent System Operator (CAISO) LCR Stakeholder Meeting, April 10th, 2008, Folsom CA

slide-2
SLIDE 2

2

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Sierra and Stockton LCR Areas

Stockton Area

slide-3
SLIDE 3

3

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Changes since last Stakeholder meeting

Sierra:

Updated NQC data Atlantic-Lincoln 115 kV Upgrade - on-line changed from 5/2009 to 12/2009 – not modeled South of Palermo Reconductoring - on-line changed from 5/2009 to 5/2010 – not modeled Rio Oso #1 and #2 230/115 kV Transformer Bank Replacement - on- line changed from 5/2009 to 5/2011 – not modeled

Stockton:

Updated NQC data

slide-4
SLIDE 4

4

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Sierra Area Load and Resources (MW)

Load = 2019 Transmission Losses = 107 Total Load = 2126 Market Generation = 768 Muni Generation = 796 QF Generation = 216 Total Qualifying Capacity = 1780 2009

slide-5
SLIDE 5

5

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Northern Part of Sierra

slide-6
SLIDE 6

6

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Southern Part of Sierra

slide-7
SLIDE 7

7

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Sierra Area Contingencies South of Table Mountain

South of Table Mountain Sub-area

Contingency: Table Mountain-Rio Oso 230 kV & Table Mountain Palermo 230 kV DCTL outage LCR: 1617 MW (includes 216 MW of QF and 796 MW of Muni generation) Limiting component: Thermal overload on the Caribou-Palermo 115 kV line LCR has decreased due to the Table Mountain-Palermo 230 kV line Upgrade (part of the Table Mountain-Rio Oso 230 kV Reconductor and Tower Upgrade Project). If this project is not operational by June 1, 2009 then requirement is higher than 1780 MW the total available resources in the area.

South Of Table Mountain Sub-area – Category B

Contingency: Table Mountain-Rio Oso 230 kV line with Colgate #1 unit out of service LCR: 1159 MW (includes 1012 MW of QF and Muni generation) Limiting component: Thermal overload on Table Mountain-Palermo 230 kV line

slide-8
SLIDE 8

8

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Sierra Area Contingencies Pease & Bogue

Pease Sub-area

Contingency: Palermo-East Nicolaus 115 kV line with one of the Green Leaf II Co-gen unit out of service LCR: 154 MW (includes 90 MW of QF and 20 MW of Deficiency) Limiting component: Thermal overload on the Palermo-Pease 115 kV line

Bogue Sub-area

Contingency: Pease-Rio Oso 115 kV line with Green Leaf I Co-gen unit out of service LCR: 136 MW (includes 47 MW of QF and 44 MW of Deficiency) Limiting component: Thermal overload on the Palermo-Bogue 115 kV line

slide-9
SLIDE 9

9

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Sierra Area Contingencies South of Palermo

South Of Palermo Sub-area

Contingency: Double Circuit Tower Line Table Mountain-Rio Oso and Colgate- Rio Oso 230 kV lines LCR: 1632 MW (includes 364 MW of QF and Muni generation as well as 584 MW of Deficiency) Limiting component: Thermal overload on the Pease-East Nicolaus 115 kV line

South Of Palermo Sub-area – Category B

Contingency: Palermo-Pease 115 kV line with Belden unit out of service LCR: 1191 MW (includes 364 MW of QF and Muni generation as well as 143 MW o Deficiency) Limiting component: Thermal overload on the Pease-East Nicolaus 115 kV line

slide-10
SLIDE 10

10

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Sierra Area Contingencies Colgate

Colgate Sub-area

Contingency: Colgate 230/60 kV transformer followed by Pease-Marysville 60 kV line LCR: 114 MW (includes 41 MW of QF and Muni generation as well as 73 MW of Deficiency) Limiting component: Thermal overload on the Palermo-Colgate 60 kV line

Colgate Sub-area – Category B

Contingency: Colgate 230/60 kV transformer LCR: 55 MW (includes 41 MW of QF and Muni generation as well as 14 MW of Deficiency) Limiting component: Thermal overload on the Palermo-Colgate 60 kV line

slide-11
SLIDE 11

11

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Sierra Area Contingencies Drum-Rio Oso

Drum-Rio Oso Sub-area

Contingency: Rio Oso #2 230/115 kV transformer followed by Rio Oso-Brighton 230 kV line LCR: 676 MW (includes 418 MW of QF and Muni generation) Limiting component: Thermal overload on the Rio Oso #1 230/60 kV Transformer

Drum-Rio Oso Sub-area – Category B

Contingency: Rio Oso #2 230/115 kV transformer LCR: 461 MW (includes 418 MW of QF and Muni generation) Limiting component: Thermal overload on the Rio Oso #1 230/60 kV Transformer

slide-12
SLIDE 12

12

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Sierra Area Contingencies South of Rio Oso

South of Rio Oso Sub-area

Contingency: Rio Oso-Gold Hill 230 line followed by loss of the Gold Hill- Ralston 230 kV line or vice versa LCR: 434 MW (includes 291 MW of QF and Muni generation as well as 67 MW

  • f Deficiency)

Limiting component: Thermal overload on the Rio Oso-Atlantic 230 kV line

South of Rio Oso Sub-area – Category B

Contingency: Rio Oso-Gold Hill 230 line with the Ralston unit out of service LCR: 293 MW (includes 291 MW of QF and Muni generation) Limiting component: Thermal overload on the Rio Oso-Atlantic 230 kV line

slide-13
SLIDE 13

13

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Sierra Area Contingencies Placer

Placer Sub-area

Contingency: Drum-Higgins 115 kV line followed by loss of the Gold Hill- Placer #2 115 kV line LCR: 140 MW (includes 0 MW of QF and Muni generation as well as 116 MW

  • f Deficiency)

Limiting component: Thermal overload on the Gold Hill-Placer #1 115 kV line

Placer Sub-area – Category B

Contingency: Drum-Higgins 115 kV line with the Halsey unit out of service LCR: 37 MW (includes 0 MW of QF and Muni generation as well as 13 MW

  • f Deficiency)

Limiting component: Thermal overload on the Gold Hill-Placer #1 115 kV line

slide-14
SLIDE 14

14

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Sierra Area Contingencies Placerville

Placerville Sub-area

Contingency: Gold Hill-Clarksville 115 kV line followed by loss of the Gold Hill- Missouri Flat #2 115 kV line LCR: 118 MW (includes 0 MW of QF and Muni generation as well as 89 MW of Deficiency) Limiting component: Thermal overload on the Gold Hill-Missouri Flat #1 115 kV line

Placerville Sub-area – Category B

Contingency: Gold Hill-Clarksville 115 kV line with one of the El Dorado units

  • ut of service

LCR: 34 MW (includes 0 MW of QF and Muni generation as well as 5 MW of Deficiency) Limiting component: Thermal overload on the Gold Hill-Missouri Flat #1 115 kV line

slide-15
SLIDE 15

15

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Sierra Area Contingencies Aggregate

QF (MW) Muni (MW) Market (MW)

  • Max. Qualifying

Capacity (MW) Available generation 216 796 768 1780 Existing Generation Capacity Needed (MW) Deficiency (MW) Total MW LCR Category B (Single) 1453 226 1679 Category C (Multiple) 1617 703 2320

Each unit is only counted once, regardless in how many sub-areas it is needed. In order to come up with an aggregate deficiency, where applicable the deficiencies in each smaller sub-area has been accounted for (based on their effectiveness factors) toward the deficiency of a much larger sub-area.

slide-16
SLIDE 16

16

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Changes since the 2008 LCR study

Total Sierra LCR has increased

  • Load forecast is up by 35 MW
  • New project Table Mountain – Rio Oso Reconductor and Tower

Upgrade has reduced the resource needs (therefore lowered procurement)

  • Overall the procurement needed has decreased by 163 MW
  • Deficiency has increased mainly because some project that were
  • riginally modeled in the 2008 base cases now have been delayed

after summer 2009. These projects are:

  • 1. Atlantic-Lincoln 115 kV Upgrade
  • 2. South of Palermo 115 kV Reconductoring
  • 3. New Pease-Marysville # 2 60 kV line
  • Overall the LCR has increased by 228 MW
slide-17
SLIDE 17

17

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Stockton Area Load and Resources (MW)

2009 Load = 1409 Transmission Losses = 27 Total Load = 1436 Market Generation = 265 Muni Generation = 188 QF Generation = 88 Total Qualifying Capacity = 541

slide-18
SLIDE 18

18

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Tesla-Bellota Sub-area

Contingency: Tesla-Tracy 115 kV line and Tesla-Kasson-Manteca 115 kV line. LCR: 524 MW (includes 201 MW of QF and Muni generation as well as 57 MW of Deficiency). Limiting component: Thermal overload on the Manteca-Ingram Creek section of the Tesla-Salado-Manteca 115 kV line.

Tesla-Bellota Sub-area – Category B

Contingency: Tesla-Kasson-Manteca 115 kV line and the loss of Stanisls #1. LCR: 496 MW (includes 201 MW of QF and Muni generation as well as 29 MW of Deficiency). Limiting component: Thermal overload on the Manteca-Ingram Creek section of the Tesla-Salado-Manteca 115 kV line.

Critical Stockton Area Contingencies Tesla-Bellota Sub-area

slide-19
SLIDE 19

19

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Tesla-Bellota 115 kV Area Transmission

Tesla

230 kV 115 kV

Bellota

Stanislaus Tulloch Donnells Beardsley Spring Gap

Comanche

Manteca QF’s Lockeford 115 kV Stockton Salado Kasson River Bank 230 kV 115 kV Stockton Co-gen Critical Outage Tracy GWF Tracy Melones NO

slide-20
SLIDE 20

20

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Stockton Area Contingencies Lockeford Sub-area

Lockeford Sub-area

Contingency: Lockeford-Industrial 60 kV line and Lockeford-Lodi #2 60 kV line LCR: 88 MW (includes 25 MW of QF and Muni generation as well as 63 MW of Deficiency) Limiting component: Thermal overload on the Lockeford-Lodi Jct. Section

  • f the Lockeford-Lodi #3 60 kV line

Lockeford Sub-area – Category B

Contingency: Lockeford-Industrial 60 kV line with Lodi CT out of service LCR: 30 MW (includes 25 MW of QF and Muni generation as well as 5 MW of Deficiency) Limiting component: Thermal overload on the Lockeford-Lodi Jct. Section

  • f the Lockeford-Lodi #3 60 kV line
slide-21
SLIDE 21

21

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Lockeford 60 kV Area Transmission

Bellota 230kV Rio Oso 230kV Camanche Pardee Lockeford 230 kV 60 kV 115 kV 115 kV Victor Lodi Industrial Lodi Jct To Stagg To Weber Mettler Colony Jct Colony Gen. Mills

N.O. N.O.

Lodi CT Mondavi New Hope New Hope Jct Terminous Stcktn JB

N.O.

Stcktn Co-gen

Outage Critical

slide-22
SLIDE 22

22

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Stagg Sub-area

Contingency: Tesla-Stagg 230 kV line and Tesla-Eight Mile 230 kV line LCR: 115 MW (includes 50 MW of Muni generation as well as 65 MW

  • f Deficiency)

Limiting component: Post-contingency steady-state voltages less than 0.92 p.u. at Mosher 60 kV bus

Stagg Sub-area – Category B

Contingency: None LCR: 0 MW Limiting component: None

Critical Stockton Area Contingencies Stagg Sub-area

slide-23
SLIDE 23

23

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Stagg 230 kV Area Transmission

Tesla

230 kV

Gold Hill

Stagg J2

Eight Mile Road

Critical Outage

Lodi Stigg Stagg

230 kV 230 kV 230 kV 230 kV

slide-24
SLIDE 24

24

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Critical Stockton Area Contingencies Aggregate

QF (MW) Muni (MW) Market (MW)

  • Max. Qualifying

Capacity (MW) Available generation 88 188 265 541 Existing Generation Capacity Needed (MW) Deficiency (MW) Total MW LCR Category B (Single) 491 34 525 Category C (Multiple) 541 185 726

Each unit is only counted once, regardless in how many sub-areas it is needed. In order to come up with an aggregate deficiency, where applicable the deficiencies in each smaller sub-area has been accounted for (based on their effectiveness factors) toward the deficiency of a much larger sub-area.

slide-25
SLIDE 25

25

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Changes since the 2008 LCR study

Total Stockton LCR has increased

  • Load forecast is up by 106 MW
  • All the resources were needed in 2008 and there is no change in

2009 as such procurement will not change

  • The Deficiency has decreased significantly due to an updated

model for the capacitors connected directly to the distribution banks at Stagg 230 kV bus

  • Overall the total LCR has decreased by 60 MW
slide-26
SLIDE 26

26

Stakeholder Meeting, April 10th, 2008 – LCR 2009

Stakeholder Comments Stakeholder Comments

Your comments and questions are welcome Your comments and questions are welcome

For written comments, please send to: RegionalTransmission@caiso.com