Hilltop Tacoma Link Extension
System Expansion Committee
06/11/2020
Hilltop Tacoma Link Extension System Expansion Committee 06/11/2020 - - PowerPoint PPT Presentation
Hilltop Tacoma Link Extension System Expansion Committee 06/11/2020 Why we are here Hilltop Tacoma Link Extension Update Information only briefing of current project status Todays Proposed Board Actions To inform the System
06/11/2020
2
recommendations to Board to increase the project budget and increase contingency for construction and professional services contracts
3
4
Facility expansion
5
supplement to address updated estimate at completion. Project Baseline Budget $217.3 Committed $202.7 Incurred $118.6
93% 55%
6
20% likelihood of meeting project budget 80% likelihood of meeting revenue service date Contingency forecast – minimum level by Q3 2019
Develop Recovery Plan
7
Contractor and City of Tacoma stakeholders Developed Recovery Plan
increase
8
2018 2020 2022
City of Tacoma Pre-construction utility relocations
Sound Transit
Heavy utility work OMF construction Civil and systems construction** System testing and pre-revenue service Construction includes: *Water main, sanitary and storm sewer relocations and new water service connections. **Operations and Maintenance Facility, stations, artwork, track, traction power substations, contact system poles, signalized intersections and repaved roadway.
9
10
11
12
13
14
virtual meetings, email, phone, mailed notification, social media, weekly construction alerts to about 5,000 subscribers
activities -- business visits, stakeholder briefings, community meetings, and events
15
16
For at-grade construction in City ROW, the agency should consider: Design
requirements for subsurface investigations during planning and design Construction
community and/or improve schedule performance
18
19
Hilltop Tacoma Link Extension: Baseline Budget: $217.3M
ALLOCATION $ COMMITMENTS
$217.35M Project Development
Illustrative - Not to Scale
Approved Today’s Action Future Action
Construction
20
Hilltop Tacoma Link Extension: Board approves $35.4M for increase in baseline budget
ALLOCATION $ COMMITMENTS
$252.75M Project Dev.
Illustrative - Not to Scale
Approved Today’s Action Future Action
Construction
21
contingency in the amount of $27,400,000
design services during construction in the amount of $1,000,000
construction management consultant services in the amount of $2,070,000
for Tacoma Link LRV engineering and inspection consultant services in the amount of $1,997,814
22
Hilltop Tacoma Link Extension: Baseline Budget: $252.7M
ALLOCATION $ COMMITMENTS
$252.7M Project Dev.
Illustrative - Not to Scale
Approved Today’s Action Future Action
Construction
23
Hilltop Tacoma Link Extension: Board approves Motion No. 31 through Motion No. 34
ALLOCATION $ COMMITMENTS
$252.7M Project Dev.
Illustrative - Not to Scale
Approved Today’s Action Future Action
Construction
24
Project Name Project Budget (in millions) Project % Complete Projected Budget Surplus (in millions) Northgate Link $1,899.8 94.9% $52.5 plus project reserve of $50 Hilltop Tacoma Link $217.3 55.8%
East Link $3,677.2 78.2% Trending below budget Lynnwood Link Federal Way Link Downtown Redmond Link $6,753.1 Too early to project OMF East $449.2 83.6% Trending below budget Other Projects at or Near Completion Surplus varies by project