2020 2024 final lcr study results
play

2020 & 2024 Final LCR Study Results Big Creek/Ventura Area - PowerPoint PPT Presentation

2020 & 2024 Final LCR Study Results Big Creek/Ventura Area Nebiyu Yimer Regional Transmission Engineer Lead Stakeholder Call April 10, 2019 ISO Public ISO Public Big Creek - Ventura Area Transmission System Big Creek Hydro Rector


  1. 2020 & 2024 Final LCR Study Results Big Creek/Ventura Area Nebiyu Yimer Regional Transmission Engineer Lead Stakeholder Call April 10, 2019 ISO Public ISO Public

  2. Big Creek - Ventura Area Transmission System Big Creek Hydro Rector Sub-Area Rector Springville Vestal Vestal Sub-Area Sycamore Midway (PG&E) Omar Magunden Big Creek – Ventura LCR Area Lebec Whirlwind (PEF) Victorville Edmonston Pastoria (LADWP) Windhub (CDWR) Moorpark Goleta Warne Bailey Sub-Area Antelope Sub-Area (CDWR) Goleta Santa Clara Pardee Vincent PDCI to Celilo Mandalay (LADWP/BPA) Santa Clara Moorpark Legend Sub-Area 230 kV Sylmar 500 kV line (LADWP) 230 kV line Ormond Slide 2 ISO Public

  3. Major transmission projects • Big Creek Corridor Rating Increase Project (ISD-04/01/2020) • Pardee-Moorpark No. 4 230 kV Transmission Project (ISD- 12/31/2020) Slide 3 ISO Public

  4. Resource Assumptions • Mandalay retired • Ormond Beach will be retired by 12/31/2020 • Ellwood is assumed to be retired beyond 2020 when its current contract expires • The Las Flores Canyon Cogeneration Facility (EXGEN) has been OOS since 2015 and is assumed to be unavailable. Slide 4 ISO Public

  5. Load and Resources Load (MW) Generation NQC (MW) 2024 2020 2020 2024 Gross Load 4,882 5,170 Market/Net Seller 4,290 2,720 AAEE* -47 -158 Solar 304 304 Behind the meter PV* -323 -493 Muni 342 342 Net Load 4,512 4,519 QF 63 60 Transmission Losses 75 70 LTPP Pref. Res & ES 0 2 Existing 20-minute Demand Pumps 369 369 100 100 Response Load+Losses+Pumps 4,956 4,958 Total Qualifying Capacity 5,099 3,528 * The AAEE and BTM PV values shown may not include amounts associated with the Saugus Substation as the CEC’s definition of the Big Creek Ventura Area does not include the substation Slide 5 ISO Public

  6. Rector Sub-Area Requirements LCR (MW) Category Limiting Facility Contingency 2020 2024 LCR for Rector is satisfied by the LCR of the larger Vestal B/C 0 0 sub-area ISO Public Slide 6

  7. Vestal Sub-Area Requirements LCR (MW) Category Limiting Facility Contingency 2020 2024 Magunden – Magunden – Springville #1 230 kV B/C Springville #2 230 kV 425 461 line with Eastwood out of service line Eastwood Big Creek Hydro Rector Springville Vestal Omar Magunden ISO Public Slide 7

  8. Goleta Sub-Area Requirements LCR (MW) Category Limiting Facility Contingency 2020 2024 17 MW plus Santa Clara – Goleta 230 kV line with Goleta 230 kV bus largest B largest resource at Goleta out of 0 (Low voltage) resource at service Goleta (1) Overlapping outage of Santa Clara – Goleta and Moorpark – Santa Clara Goleta 230 kV bus 27 MW 1) C 0 (2020) or Vincent – Santa Clara 230 (Low voltage) kV lines (2024) (2) (1) Generic distributed resources delivered at Goleta are assumed to meet the local capacity deficiency. (2) The worst TPL 001-4 (Category P6) contingency is overlapping outage of Santa Clara shunt capacitor and the Santa Clara – Goleta 230 kV line. This would require 52 MW of local capacity. However, this contingency is not a current LCR criteria contingency. Santa Clara Goleta Vincent Cat. C 230 kV 230 KV 500/230 kV Pardee 230 kV Largest RFP Unit Cat. B Mandalay 230 kV Moorpark 230 kV Ormond 230 kV ISO Public Slide 8

  9. Santa Clara Sub-Area Requirements LCR (MW) Category Limiting Facility Contingency 2020 2024 B None None 0 0 Pardee – Santa Clara 230 kV line followed by Moorpark – Santa Clara 288-298 (1) 309-348 (2) D Voltage Collapse #1 and #2 230 kV DCTL (1) The low and high ends of the LCR range are determined by assuming generic resources are located at Goleta (38 MW) or Santa Clara (48 MW), respectively to meet the local capacity deficiency. (2) The low and high ends of the LCR range are determined by assuming generic resources are located at Goleta (112 MW) or Santa Clara (151 MW), respectively to meet the local capacity deficiency. Vincent Goleta Santa Clara 500/230 kV 230 KV 230 kV Pardee 230 kV Mandalay 230 kV Moorpark 230 kV Ormond ISO Public 230 kV Slide 9

  10. Moorpark Sub-Area Requirements LCR (MW) Category Limiting Facility Contingency 2020 2024 B None None 0 0 Pardee – Moorpark #1 230 kV line followed by Pardee – Moorpark #1 D Voltage Collapse 514 0 and #2 230 kV DCTL Vincent Goleta Santa Clara 500/230 kV 230 KV 230 kV Pardee 230 kV Mandalay 230 kV Moorpark 230 kV Ormond 230 kV ISO Public Slide 10

  11. Overall Big Creek-Ventura Area Requirements LCR (MW) Category Limiting Facility Contingency 2020 2024 One Sylmar – Pardee 230 kV line with Sylmar – Pardee #1 or Ormond Beach (2020) or Pastoria B 2,154 2,083 #2 230 kV line combined cycle module (2024) out of service. Overlapping outage of Lugo – Sylmar-Pardee #1 or C Victorville 500 kV line and one 2,410 2,577 #2 230 kV line Sylmar – Pardee 230 kV line Eldorado – Lugo 500 kV Planned Outage Sensitivity Assessment LCR (MW) Category Limiting Facility Contingency 2020 2024 Overlapping outage of Lugo – Sylmar-Pardee #1 or C Victorville 500 kV line and one 3,500 N/A #2 230 kV line Sylmar – Pardee 230 kV line ISO Public Slide 11

  12. Overall Big Creek-Ventura Area Constraints Big Creek Hydro Rector Springville Vestal Sycamore Midway (PG&E) Omar Magunden Big Creek – Ventura LCR Area Lebec Whirlwind (PEF) Victorville Edmonston Pastoria (LADWP) Windhub (CDWR) Warne Bailey Antelope (CDWR) Goleta Santa Clara Pardee Vincent PDCI to Celilo Mandalay (LADWP/BPA) Moorpark Legend 230 kV Sylmar (LADWP) 500 kV line 230 kV line Ormond Slide 12 ISO Public

  13. Big Creek Area Total LCR Need Existing Generation Capacity Needed (MW) Deficiency (MW) Total MW Need 2020 LCR Need Category B (Single) 2,154 0 2,139 ≥38 2,410 Category C (Multiple) 2,448 Existing Generation Capacity Needed (MW) Deficiency (MW) Total MW Need 2024 LCR Need ≥17 Category B (Single) 2,083 2,100 ≥112 2,577 Category C (Multiple) 2,689 Slide 13 ISO Public

  14. SCE Area Load Profile (CEC) 1.000 0.994 1.00 1.000 0.985 0.971 0.972 0.967 0.988 0.983 0.95 0.935 0.954 0.954 0.913 0.943 0.90 0.878 0.910 0.888 0.847 0.85 Fraction of Peak Load 0.843 0.818 0.796 0.790 0.80 0.75 0.730 0.761 0.718 0.750 0.70 0.673 0.706 0.672 0.65 0.634 0.660 0.628 0.614 0.599 0.630 0.60 0.572 0.576 0.559 0.605 0.555 0.555 0.582 0.55 0.558 0.543 0.535 0.534 0.520 0.522 0.50 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time of Day (PPT, Hour Ending) 2020 Peak Day (9/1/2020) 2024 Peak Day (9/3/2024) Peak LCA and Sub-Area Load, MW (excludes losses) Year Rector Vestal Goleta Santa Clara Moorpark BCV 2020 810 1315 320 898 1780 4881 2024 810 1307 316 891 1767 4888 ISO Public Slide 14

  15. Changes Compared to Last year’s LCR Results - 2020 2019 2020 Sub-Area Reason for LCR Change Load LCR Load LCR (MW) (MW) (MW) (MW) Rector 900 - 810 - Not binding Vestal 1,520 621 1,315 425 Load decreased Goleta 360 N/A 320 0 New sub-area Santa Clara 864 237 898 288-298 Load increased Moorpark 1,722 433 1,780 514 Load increased Overall Big 5,162 2,614 4,956 2,410 Load decreased Creek Ventura* * Load values include losses Slide 15 ISO Public

  16. Changes Compared to Last Year’s LCR Results - 2024 2023 2024 Reason for LCR Sub-Area Load LCR Load LCR Change (MW) (MW) (MW) (MW) Rector 887 - 810 - Not binding Vestal 1,481 621 1,307 461 Load decreased ≥ 27(20)** Goleta 346 N/A 316 New sub-area 316-358 309-348 Santa Clara 927 891 Load decreased (122-164)** (112-151)** Moorpark 1,768 0 1767 0 No change Overall Big 5,169 2,690 4,958 2,577 Load decreased Creek Ventura* * Load values include losses ** Values in parenthesis show deficiency Slide 16 ISO Public

  17. Changes Compared to Draft LCR Results - 2020 Preliminary Final Sub-Area Reason for LCR Change Load LCR Load LCR (MW) (MW) (MW) (MW) Rector 835 - 810 - No change Vestal 1,355 467 1,315 425 Load decreased Goleta 332 8 320 0 Load decreased 234 288-298 Santa Clara 833 898 Load increased (0) ** (38-48)** Moorpark 1,740 499 1,780 514 Load increased Overall Big 4,942 2,390 4,956 2,410 Load increased Creek Ventura* * Load values include losses ** Values in parenthesis show deficiency Slide 17 ISO Public

  18. Changes Compared to Draft LCR Results - 2024 Preliminary Final Reason for LCR Sub-Area Load LCR Load LCR Change (MW) (MW) (MW) (MW) Rector 807 - 810 - Vestal 1,303 450 1,307 461 ≥ 32 (25)** ≥ 27 (20)** Goleta 318 316 Minor changes in load and LCR 313-351 309-348 Santa Clara 895 891 (117-155)** (112-151)** Moorpark 1768 0 1767 0 Overall Big Creek 4,947 2,567 4,958 2,577 Ventura* * Load values include losses ** Values in parenthesis show deficiency Slide 18 ISO Public

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend