alimerv team
play

ALIMERV TEAM ZOG PROCTOR MEMBERS POPINARA MORRIS VINCENT - PowerPoint PPT Presentation

ALIMERV TEAM ZOG PROCTOR MEMBERS POPINARA MORRIS VINCENT SCHNEPS SCANCARELLO ARCH 2330 | Building Technology III FINAL TEAM BUILDING Fall 2016 PRESENTATION Prof. Paul King PROJECT SELECTION & ANALYSIS Include one slide that


  1. ALIMERV TEAM ZOG PROCTOR MEMBERS POPINARA MORRIS VINCENT SCHNEPS SCANCARELLO ARCH 2330 | Building Technology III FINAL TEAM BUILDING Fall 2016 PRESENTATION Prof. Paul King

  2. PROJECT SELECTION & ANALYSIS Include one slide that shows the selected project Quickly evaluate the existing building for:  Structure – does the building show structure?  Floor to Floor – does the building have appropriate floor to floors?  Mechanical – does the building show vertical and horizontal route for mechanical systems and indicate the location of a mechanical room?  Egress – does the building include two means of egress and are they properly located? Are they in fire rated enclosures? Does the building include an elevator?  Assembly – do the drawings indicate building assembly materials? Can you determine what the façade is made of? Credit Initials

  3. PROJECT SELECTION & ANALYSIS PROJECT SELECTION & ANALYSIS ZP ZP

  4. PROJECT SELECTION & ANALYSIS The structural grid is not shown but you get a clear understanding how everything is aligned, however for the selections highlighted in the figure to the right, one cannot know for sure if those are columns or if they act as mullions. Note that the area shaded in red should contain a expansion joint because that certain area of the building extends to the higher floors while other areas do not. This becomes more clear in the floor plans and sections. ZP

  5. PROJECT SELECTION & ANALYSIS Floor to floor are about 12 feet which are perfect for a design but can cause problems when thinking about a split level as you see here highlighted in red. The area highlighted in yellow shows the vertical circulation. Its important to note that you do have the right amount of egress stairs but they are not enclosed properly. Also vertical and horizontal mechanical shafts are not included in section drawings, however they exist in the floor plan. (Locker room floor) ZP

  6. PROJECT SELECTION & ANALYSIS Problems with Egress Stairs. 1. Stairs are not enclosed properly. 2. Door directions are all wrong except in the first floor plan where they lead you out of the building. 3. There are no doors leading you out of the building in the bottom stair therefor , its not considered an egress if you cant exit out of the stairs (CASE). 4. Some stairs lead directly to rooms/office space. 5. Stairs do not contain doors wherever you see a red question mark. 6. Not clear if area highlighted in green is an elevator or a vertical shaft. ZP

  7. PROJECT SELECTION & ANALYSIS Problems with Circulation In the floor plan you can see the pool is located in the first floor as soon as you enter. That can be a problem for the circulation and also for design purpose. Would someone want to go to the locker room floor , change then come back up to swim. Pool is also too small according to code, an Olympic sized swimming pool should contain minimum dimensions of ZP

  8. STRUCTURAL PROPOSAL Show a typical floor plan and a section from your Revit drawings. The section should be cut where it gives a clear indication of structure and special conditions like long spans. If your team has all used the same solution then you only need to show one slide, that can be shared by the team. If different team members proposed different solutions then each team member shows their own slide. Floor plan: Highlight (use color - green) the proposed structural grid, show column locations and provide dimensions. Section: Highlight (use color - green) the floor slabs and the floor to floor dimensions. Slab should indicate appropriate thickness Credit Initials

  9. STRUCTURAL PROPOSAL Spans between grid line A-B and 1-2 are 8’, to show the cantilevered split level. B-C span 32’ C-D span 36’ (for pool and skylight, also nothing supported above) D-E span 28’. 2-3 spans 18’ and the rest of the grid lines all span 20’. ZP

  10. STRUCTURAL PROPOSAL Typical Floor Plan contains a central courtyard you can look down in the pool. Its missing a garden which is now moved on the roof of the first floor. Also you can see the placing of the Rockwall climbing has changed to help circulation through and around. ZP

  11. STRUCTURAL PROPOSAL Basement to first floor = 12’ 1 st floor to second floor= 14’ 2 nd Floor to 3 rd Floor= 16’ 2.5-3.5 = 14’ 3 rd Floor to 4 th Floor= 14’ ZP

  12. STRUCTURAL PROPOSAL The basement has a double height area for the pool, therefore columns must be placed on the perimeter. MS

  13. STRUCTURAL PROPOSAL Basement to 1 st floor = 12’ 1 st floor to 2 nd floor= 12’ 2 nd Floor to 3 rd Floor= 12’ 2.5-3.5 = 12’ 3 rd Floor to 4 th Floor= 12’ MS

  14. STRUCTURAL PROPOSAL A to B = 8’ 1” B to C = 32’ 0” C to D = 32’ 0” D to E = 24’ 6” E to F = 7’ 6” 1 to 2 = 8’ 0” 2 to 3 = 12’ 0” 3 to 4 = 20’ 0” 4 to 5 = 20’ 0” 5 to 6 = 20’ 0” 6 to 7 = 20’ 0” VS

  15. STRUCTURAL PROPOSAL Floor to Floor Heights Basement – First First – Second Second – Third Third – Fourth Fourth – Roof Roof – Parapet VS

  16. MECHANICAL PROPOSAL Show a typical reflected ceiling plan and a section from your Revit drawings. The section should be cut where it will clearly show the vertical and horizontal distribution of mechanical systems. If your team has all used the same solution then you only need to show one slide, that can be shared by the team. If different team members proposed different solutions then each team member shows their own slide. Floor plan: Highlight (use color-orange) the location of the mechanical room &vertical distribution shafts. You may require two plans, one typical and a second that shows the mechanical room. Indicate (use color-red) the two hour rated shaft enclosures. Section: Highlight (use color-orange) the distribution of mechanical systems. Be certain that the section is cut where it shows vertical mechanical shafts and horizontal distribution of mechanical systems. Credit Initials

  17. MECHANICAL PROPOSAL ZP

  18. MECHANICAL PROPOSAL Lighting Fixtures Air Return Air Supply Sprinklers MS

  19. MECHANICAL PROPOSAL ZP

  20. EGRESS PROPOSAL Show a typical floor plan and a section from your Revit drawings. The section should be cut where it will clearly shows the vertical stairs. You may require more than one. If your team has all used the same solution then you only need to show one slide, that can be shared by the team. If different team members proposed different solutions then each team member shows their own slide. Floor plan: Highlight (use color-yellow) the location of the stairs and elevators and the egress corridors. Indicate (use color-red) 1 hour rated corridors &the 2 hour rated stair enclosures. Be certain that all doors open in the direction of egress. Section: Highlight (use color-yellow) the stairs. Indicate the horizontal routes and vertical routes for egress. Credit Initials

  21. EGRESS PROPOSAL Basement to Level 4 Section Level 1 to 2.5 Section First Floor Level Plan MS

  22. COMPOSITE MATERIALS PROPOSAL Show exterior elevations or perspectives. Label materials that you have chosen for your solutions. Materials divide into two categories, large expanses of glass or curtain walls and solid materials. Provide labels to indicate the different materials that will be investigated by your team. For example on the curtain wall you can label the different solutions that the team has chosen, stick system with mullions, butt glazing with cable or rods, window wall etc. For the solid portions of the façade list the different solutions that your team has chosen, precast concrete, metal panels, stone panels or veneer, rain screen etc. This slide is a compilation of the teams solutions. Each team member will show their individual solutions again during the individual presentations. Credit Initials

  23. TEAM MEMBER NAME HERE ARCH 2330 | Building Technology III INDIVIDUAL DETAILS PRESENTATION Fall 2016 Prof. Paul King

  24. FAÇADE DEVELOPMENT AND DETAILS Show wall sections, section details and plan details of your façade construction. Remember that you should show matching plan section and elevation details at appropriate scales. Wall sections are to be ½” or ¾” scale with partial elevations at the same scale. Details are to be drawn at 1 ½” or 3” = 1’-0” scale. All details are to be fully annotated including labels and dimensions using detail items. Start with one image of the full size sheet showing the layout. Plot the detail sheet to PDF > export as an image and include it here in PowerPoint. Color code your details to indicate the following: Structure – green color • Water proofing – blue color • Fire Stopping – red color • Thermal Insulation- yellow color • Composite (shows all together) • First show the detail (matching plan and section and elevation works best) with no color. Then show the same slide with one color at a time. Highlight both the annotation and show structure (green), water proofing (blue), fire stopping (red), thermal insulation (yellow). Then show the detail with all colors. This is likely 6 slides – one for the full sheet and one for each system (structure, water proofing, fire stopping, thermal and composite) Credit Initials

  25. CURTAIN WALL DETAIL MS

  26. STRUCTURE MS

  27. WATER PROOFING MS

  28. FIRE STOPPING MS

  29. THERMAL MS

  30. COMPOSITE MS

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend