2017 ONE OF THE WORLDS FASTEST -GROWING GOLD PRODUCERS CAUTIONARY - - PowerPoint PPT Presentation

2017
SMART_READER_LITE
LIVE PREVIEW

2017 ONE OF THE WORLDS FASTEST -GROWING GOLD PRODUCERS CAUTIONARY - - PowerPoint PPT Presentation

SEPTEMBER ACQUIRE | DISCOVER | FINANCE | BUILD | OPERATE 2017 ONE OF THE WORLDS FASTEST -GROWING GOLD PRODUCERS CAUTIONARY STATEMENT 2 This presentation includes certain forward -looking information and forward -looking


slide-1
SLIDE 1

SEPTEMBER 2017 ACQUIRE | DISCOVER | FINANCE | BUILD | OPERATE

ONE OF THE WORLD’S FASTEST-GROWING GOLD PRODUCERS

slide-2
SLIDE 2

CAUTIONARY STATEMENT

This presentation includes certain “forward-looking information” and “forward-looking statements” (collectively “forward-looking statements”) within the meaning of applicable securities legislation, including projections of future financial and operational performance; statements with respect to future events or future performance; production estimates and guidance, including the Company’s projected gold production of between 530,000 to 570,000 ounces in 2017 and projected gold production of between 925,000 and 975,000 ounces in 2018; projected

  • perating and production costs and guidance; estimates of capital expenditures and planned investments and budgets, including exploration budgets; and statements regarding anticipated exploration, development, construction, production, permitting and other activities of the

Company, including: the Fekola Project being approximately 3 months ahead of schedule and beginning production in October 2017; Fekola achieving commercial production before the end of 2017, on budget and being fully funded; Fekola being a low-cost mine and anticipated stockpiling there; the State of Mali exercising its option to acquire an additional 10% interest in the Fekola Project, for an aggregate 20% interest; timing and completion of the Fekola mill expansion and the resulting potential production increase and throughput of up to 5 Mtpa in the initial years of production, and the potential to increase estimated production at Fekola; the potential to extend the current Fekola Life of Mine by 3 years and 900,000 ounces if the known Fekola Mine resource for Fekola is included; potential for Fekola Project to host additional large Fekola-style gold deposits; Kiwi zone increasing the initial Fekola Mine life and potentially increasing the size of the Fekola open pit; potential for underground mining at Fekola Deeps; completion of geotechnical, hydrogeological and design studies for the Wolfshag zone and life of mine production plans for the Otjikoto Mine; completion of an initial mineral resource for the Toega zone by the end of 2017 and the potential for additional mineralization there; the audit by the DENR in relation to the Masbate Mine and the final outcome thereof and operations at Masbate continuing uninterrupted; the production estimates for Masbate which are prepared on such basis initiating an enhanced mill expansion study at Masbate; the completion of a new resource for the new zone gold discovery near the El Limon mill; the completion of a Mining Tailing Study at El Limon; deliveries of ounces under the Prepaid Sales arrangements; optimizing production at existing mines; exploration plans; exploration and development upside; future cash flows; planned updates to studies and models; availability of financings; expectations of future growth and profitability; maintenance of a strong cash position; continued minimization of share dilution; pursuit of accretive acquisitions; and the adequacy of capital for continued operations. Estimates of mineral resources and reserves are also forward-looking statements because they constitute projections, based on certain estimates and assumptions, regarding the amount of minerals that may be encountered in the future and/or the anticipated economics of production, should a production decision be made. All statements in this presentation that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, although not always, identified by words such as “expect”, “plan”, “anticipate”, “project”, “target”, “potential”, “schedule”, “forecast”, “budget”, “estimate”, “intend” or “believe” and similar expressions or their negative connotations, or that events or conditions “will”, “would”, “may”, “could”, “should” or “might” occur. Forward-looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond B2Gold’s control, including risks associated with the volatility of metal prices and the Company’s common shares; risks and dangers inherent in exploration, development and mining activities; uncertainty of reserve and resource estimates; risk of not achieving production, cost or other estimates; risk that actual production, development plans and costs differ materially from the estimates in the Company’s feasibility studies; risks related to ore purchase commitments; the ability to obtain and maintain any necessary permits, consents or authorizations required for mining activities; risks related to environmental regulations or hazards and compliance with complex regulations associated with mining activities; the ability to replace mineral reserves and identify acquisition opportunities; availability of financing and financing risks; risks related to operations in foreign and developing countries and compliance with foreign laws; risks related to remote operations and the availability adequate infrastructure, fluctuations in price and availability of energy and other inputs necessary for mining operations; regulatory, political and country risks; the final outcome of the DENR audit; as well as other factors identified and as described in more detail under the heading “Risk Factors” in B2Gold’s most recent Annual Information Form and B2Gold’s other filings with Canadian securities regulators and the U.S. Securities and Exchange Commission (the “SEC”), which may be viewed at www.sedar.com and www.sec.gov, respectively. The list is not exhaustive of the factors that may affect the Company’s forward-looking statements. There can be no assurance that such statements will prove to be accurate, and actual results, performance or achievements could differ materially from those expressed in, or implied by, these forward-looking statements. Accordingly, no assurance can be given that any events anticipated by the forward-looking statements will transpire or occur. The Company’s forward-looking statements reflect current expectations regarding future events and operating performance and speak only as of the date hereof and the Company does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. For the reasons set forth above, undue reliance should not be placed on forward-looking statements. Non-IFRS Measur asures : This presentation includes certain terms or performance measures commonly used in the mining industry that are not defined under International Financial Reporting Standards (“IFRS”), including “cash operating costs” and “all-in sustaining costs” (or “AISC”). Non-IFRS measures do not have any standardized meaning prescribed under IFRS, and therefore they may not be comparable to similar measures employed by other companies. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS and should be read in conjunction with B2Gold’s consolidated financial statements. Readers should refer to B2Gold’s management discussion and analysis, available under B2Gold’s corporate profile at www.sedar.com and at www.sec.gov or on its website at www.b2gold.com, under the heading “Non-IFRS Measures” for a more detailed discussion of how B2Gold calculates such measures and a reconciliation of certain measures to IFRS terms. National al Instr trum ument 43 43-101 01: Tom Garagan, Senior Vice President of Exploration, a Qualified Person as defined by National Instrument 43-101, has approved the scientific and technical information concerning B2Gold Corp. discussed herein. Cauti tionary Note te to to Unite ted State tes Inve vesto tors: As a Canadian issuer that is eligible to use the U.S./Canada Multijurisdictional Disclosure System (MJDS), the Company is permitted to prepare its public disclosures and this presentation in accordance with Canadian securities laws, which differ in certain respects from U.S. securities

  • laws. In particular, this presentation uses the terms “mineral resource”, “measured mineral resource”, “indicated mineral resource” and “inferred mineral resource”. While these terms are recognized and required by Canadian securities laws, they are not recognized by the United

States Securities and Exchange Commission (“SEC”) and are not normally permitted to be disclosed in SEC filings by U.S. companies. U.S. investors are cautioned not to assume that any part of a “mineral resource”, “measured mineral resource”, “indicated mineral resource” or an “inferred mineral resource” will ever be converted into a “reserve.” In addition, “reserves” reported by the Company under Canadian standards may not qualify as reserves under SEC standards. Under SEC standards, mineralization may not be classified as a “reserve” unless the mineralization can be economically and legally extracted or produced at the time the “reserve” determination is made. Accordingly, information contained or referenced in this presentation containing descriptions of the Company’s mineral deposits may not be compatible to similar information made public by U.S. companies subject to the reporting and disclosure requirements of U.S. federal securities laws, rules and regulations. “Inferred mineral resources” have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Historical results or feasibility models presented herein are not guarantees or expectations of future performance. Currency: All amounts in this presentation are expressed in United States dollars, unless otherwise stated. THIS PRESENTATION IS NOT INTENDED AS, AND DOES NOT CONSTITUTE, AN OFFER TO SELL SECURITIES OF THE COMPANY. The Toronto Stock Exchange and the NYSE MKT LLC have not reviewed and do not accept responsibility for the accuracy or adequacy of this presentation, which has been prepared by the Company.

2

slide-3
SLIDE 3

Corp rpor

  • rate

te Strategy: tegy: To continue growing a profitable and responsible gold producer through accretive acquisitions, exploration and execution, irrespective of the gold price

3

ONE OF THE WORLD’S FASTEST- GROWING WING GOLD PROD ODUCERS UCERS Proven Management and Technical Teams

  • Former management and technical teams of Bema Gold Corporation
  • Highly experienced in-house technical and on-site operational teams
  • In-house project due diligence, development and construction teams
  • Proven history of acquiring, discovering, financing, building and operating profitable gold mines

around the world

  • Track record of building shareholder value

Growing, Profitable, Low-Cost Gold Producer

  • 5 operating gold mines: 2 in Nicaragua, 1 in the Philippines, 1 in Namibia and 1 in pre-production in Mali
  • Unparalleled production growth
  • Mill construction is complete at the Fekola Mine in Mali, more than 3 months ahead of schedule. Gold is

in the circuit and the first gold pour is anticipated by mid-October 2017

  • The Fekola Mine is projected to achieve commercial production by year-end 2017
  • Solid financial and cash position
  • Proven financing history and capability
  • Significant organic growth potential through exploration and development upside

CORPORATE OVERVIEW

slide-4
SLIDE 4

1. Refer to slide 13 for details

4

MINE & PROJECT LOCATIONS

slide-5
SLIDE 5

5

Consolidated AISC (/oz)

INCREASING PRODUCTION, DECREASING COSTS

Annual Gold Production Growth (oz), All-in Sustaining Costs (“AISC”)/oz1

  • 1. See “Non-IFRS measures” on slide 2
  • 2. Estimated pre-commercial

production at the Fekola Mine A – Actual E – Estimated: Based on current assumptions

slide-6
SLIDE 6

6

Source: Canaccord Genuity (as at September 18, 2017) 2016 A & 2018 E per public disclosure (latest MD&A) 2018 E production per Street Research Consensus for B2Gold peers Peers defined as 2016 A gold production of >500 Koz and selected senior producers

B2Gold outperforms its peers with production growth of 68% from 2016 A to 2018 E

B2GOLD VS. PEERS

Projected Production Growth Profile

slide-7
SLIDE 7

1. Source: Canaccord Genuity (as at September 7, 2017, and indexed to September 15, 2015) Prices shown are closing prices in Canadian dollars

BTO PERFORMANCE VS. S&P TSX

Gold Index & Gold Price (2 Year)

7

GDXJ Rebal balan ancing g (Mar arch – June e 2017)

slide-8
SLIDE 8
  • RCF for an aggregate of $500 M

(can be increased to $600 M)1

8

Utilizing operating cash flow and innovative, non-equity financings to fund the construction of the Fekola Mine

  • Cash proceeds received up-front in return for
  • bligation to deliver ounces later

Revolving Credit Facility (“RCF”) Gold Prepayment Arrangements

FULLY- FUNDED GROWTH

Open-pit mining at the Fekola Mine, Mali – Phase 1

1. As at July 7, 2017 2. At the end of Q2 2017, Euro 36.4 M was available for future drawdowns

  • Euro 71.4

4 M Equipment Facility with Caterpillar Financial SARL2

  • Cash at the end of Q2 2017 was $88.2

.2 M

Fekola Mine Fleet and Equipment Facility Solid Financial and Cash Position

slide-9
SLIDE 9

9

Commitment to Execution

HEALTH, SAFETY & ENVIRONMENT (“HSE”) PERFORMANCE

An industry leader in HSE performance1

  • Masbate Mine – 657

657 days without a loss time injury (“LTI”)

  • Otjikoto Mine – 239

239 days without a LTI

  • Fekola Project – 450

450 days without a LTI

  • 50%

% reduct ctio ion n in loss time injury frequency rate (“LTIFR”) at La Libertad Mine: 2016 to 2017 [1.7 vs. 0.8]

  • 35% reduction

ion in LTIFR at El Limon Mine: 2016 to 2017 [2.6 vs. 1.7] Initiated implementation in 2013 of internal HSE Standards and Management Systems:

  • In accordance with international best practice
  • Externally audited
  • Focused on continuous improvement
  • Initiated external reporting of HSE performance

Recently-published 2016 Responsible Mining Report: Raising the Bar

1. As at July 31, 2017

slide-10
SLIDE 10

10

  • Consolidated gold production of

254,18 184 oz (4% above budget)

  • Consolidated cash operating

costs1 at $596/oz (12% below budget)

  • Consolidated AISC at $929/oz

(20% below budget)

  • Consolidated gold revenue of

$310.6 .6 M on sales of 251,674

  • z at an average price of

$1,234/oz

First Half (“FH”) 2017

1. Non-IFRS measures. See “Non-IFRS measures” on slide 2 2. Including estimated pre-commercial production from the Fekola Mine of between 50,000 – 55,000 oz 3. Based on the new Fekola life of mine plan

  • Consolidated gold production guidance

is forecast to be between 530,000 – 570,000 oz2

  • Consolidated cash operating costs are

forecast to be between $610 – $650/oz

  • z
  • Consolidated AISC are forecast to be

between $940 –$970/oz

  • z

Full Year (“FY”) 2017 Guidance

  • New consolidated gold production

guidance is forecast to be between 925,000 – 975,000 oz (projected significant increase of approximately 70% from 2016 to 2018)

  • New consolidated cash operating

costs and AISC are forecast to decrease in 2018 (v 2017) to approximately $525/oz

  • z and

$800/oz

  • z, respectively)
  • Expected dramatic increase in cash

flow from operations for 2018 and beyond based on current assumptions

FY 2018 Guidance3

PRODUCTION & COST OVERVIEW

slide-11
SLIDE 11

11

PROVEN CONSTRUCTION TEAM

Successfully Constructed 5 Mines for Bema Gold & B2Gold on Schedule & Budget

2001 01 Julietta Mine, Russia

(Bema Gold)

2007 07 Kupol Mine, Russia

(Bema Gold)

2010 10 La Libertad Mine, Nicaragua

(B2Gold)

2014 14 Otjikoto Mine, Namibia

(B2Gold)

2017 17 Fekola Mine, Mali

(B2Gold)

slide-12
SLIDE 12

12

Mali, i, West t Africa ica

MINING IN MALI

Fekola Project Mali is Africa’s 3rd largest gold producer 8 mines operating in a prolific 40+ Moz district (which includes the Fekola Mine) located in a stable region unaffected by the current conflict in the far northeast

  • f the country

Democratic government widely praised for transparency Government very supportive of mining:

  • No restrictions on foreign investment or capital

flows in and out of Mali

  • 20% government ownership of the Fekola Mine
  • B2Gold recently signed shareholders and fiscal

stability (mining convention) agreements with the Government of Mali for the Fekola Mine

slide-13
SLIDE 13

13

FEKOLA MINE UPDATE

Construction of the mill is complete and ore processing has commenced, more than 3 months ahead of the original construction schedule, and is on budget. Gold is in the circuit and the first gold pour is anticipated by mid-October 2017 The Company expects to achieve commercial production and produce between 50 – 55 Koz by the end of 2017. In 2018, the Fekola Mine is now forecast to produce between 400 – 410 Koz of gold. With projected cash operating costs at $354/oz and AISC at $609/oz The throughput for the Fekola gold plant was originally designed at 4 million tonnes per annum (“Mtpa”) with a +25% design capacity (allowing for the potential of future throughput expansion) Given the exploration success and potential for growth, the B2Gold team also expanded the plant to 5 Mtpa during the construction phase rather than after commencement of

  • perations

The original Optimized Feasibility Study (“OFS”) budget was $462 M1 and the expansion to 5 Mtpa was completed for an additional $18 M in capex To date, more than 1.8 million tonnes (“Mt”) of ore has been mined and placed on the stockpiles, which is at, or above, the modelled grade

1. Excludes pre-construction early works costs of $41 M and Fadougou village relocation costs of $20 M

slide-14
SLIDE 14

In September 2017, B2Gold completed a new LOM plan for the Fekola Mine that:

  • Confirmed the original reserve and resource

described in the OFS (June 2015)

  • Optimized the production profile
  • Increased mill throughput to 5 Mtpa

14

FEKOLA MINE

Comparison of the OFS & New Life of Mine (“LOM”) Plan

Paramete eters1 OFS – 4 Mtpa pa (June e 2015 15) New LOM – 5 Mtpa (Septe ptembe ber 2017) 7) LOM (years) 12.5 10 Gold Production: LOM (Koz) 276 345 Gold Production Years: 1-3 (Koz) 333 400 Gold Production Years: 1-7 (Koz) 350 374 Cash Operating Costs: LOM (US$/oz) 552 428 Cash Operating Costs: Years 1-3 (US$/oz) 464 357 Cash Operating Costs: Years 1-7 (US$/oz) 418 391 AISC: LOM (US$/oz) 752 664 AISC: Years 1-3 (US$/oz) 717 604 AISC: Years 1-7 (US$/oz) 661 643 Reserve (Moz)2 3.45 3.45 M&I Resource (Moz)2 4.50 4.50 Inferred Resource (Moz)2 0.25 0.25

If the known Fekola resource (indicated and inferred) beyond the projected Fekola Mine reserve pit is included (subject to further drilling), the LOM could be extended by approximately 3 years and 900 Koz. Approximately 2/3 of the known resource is in the indicated category. The current resource to date does not include any of the drilling that has been completed in 2017

1. Gold production, cash operating costs and AISC are presented on an average annual basis 2. Refer to slides 42 – 46 for Mineral Reserves & Resources summary, and respective footnotes

slide-15
SLIDE 15

15

FEKOLA PROPERTY EXPLORATION

Upside Potential B2Gold’s exploration team believes that the Fekola Property has the potential to host additional large Fekola-style gold deposits; work-to-date has identified multiple targets To date1, B2Gold has drilled approximately 2,800 aircore, reverse circulation and diamond drill holes, totalling 180,000 m Based on the positive exploration drill results to date, the exploration budget for Mali in 2017 (Fekola Mine area and regional exploration) has been increased by approximately $3.8 M to $15.4 M. The budget in 2018 is expected to be at similar levels Fekola la Mine e Area ea Explo lorat ration: ion: Kiwi & F Fekola la Deeps ps Zones Recent drilling results in the Kiwi and Fekola Deeps zones continue to extend the mineralization to the north of the existing resource with the potential to extend the Fekola pit further to the north and mine a portion of Kiwi and Fekola Deeps zones by open pit In addition, the drill results to date from the Fekola Deeps zone also indicate the potential for underground mining at Fekola Deeps

1. Since B2Gold acquired the Fekola Project in October 2014

slide-16
SLIDE 16

16

FEKOLA MINE EXPLORATION UPSIDE

Kiwi & Fekola Deeps Zones: Schematic Long Section

slide-17
SLIDE 17

17

Upside Potential

FEKOLA REGIONAL EXPLORATION

Fekola la Regional ional Explo loratio ration: n: Anaconda

  • nda-Ad

Adde der r Zone Anaconda-Adder are significant zones of saprolite-hosted gold mineralization across several targets, which extend 1.5 km along strike, and are 250 m wide and 40 m deep (vertical) On June 15, 2017, B2Gold announced the initial Mineral Resource estimate for the Anaconda area of the Fekola Project as well as new exploration drill results from Anaconda and from beneath the saprolite The initial Inferred Mineral Resource estimate is 21.59 Mt at 1.11 grams per tonne (“g/t”) gold for 767 Koz. The estimate is reported within a series of pit shells and above a 0.35 g/t gold cutoff grade Saprolite-hosted gold mineralization remains open and B2Gold’s exploration group is continuing to explore the edges of the known zones to test for additional saprolite-hosted mineralized zones Several mineralized structures intersected by drilling in the unoxidized material underneath the saprolite resource have indicated the potential to host Fekola-style mineralization–drilling is ongoing to further test these zones

Map showing priority exploration targets at the Anaconda-Adder zone

slide-18
SLIDE 18

Jabali Antenna resettlement Project, Nicaragua

2017 Saring ngaya ya Award rd in the Philippines for the Masbate operations’ contribution to environmental protection, conservation and management of the regions surrounding the Masbate mine — DENR1 2015 Social l Respo ponsib nsibilit ility y Award rd in Nicaragua for B2Gold’s work on the Jabali Antenna resettlement project — APEN 2014 National

  • nal CSR Award

rd in Nicaragua for B2Gold’s Economic Empowerment and Impact in the Community — uniRSE3 2014 SNIEDA4 Awards ds in Namibia:

  • “Enterprise of the Year”
  • “Environment Awareness”

1. The Department of Environment and Natural Resources 2. Nicaraguan Association of Producers and Exporters 3. Nicaraguan Union for Corporate Social Responsibility 4. Sam Nujoma Innovative Enterprise Development Awards

18

Strong Commitment to CSR

B2Gold nursery, Nicaragua Otjikoto Nature Reserve, Namibia

CORPORATE SOCIAL RESPONSIBILITY (“CSR”) AWARDS

2016 Friend nd of the Enviro ironm nmen ent t Award rd in Nicaragua for B2Gold's commitment to source water protection and environmental management — APEN2

Mangrove reforestation program, the Philippines

slide-19
SLIDE 19

Opera ratio ions: ns: Continue to optimize operations at existing mines Fekola la Mine: e: Pour first gold by mid-October 2017 Fekola la Mine: e: Achieve commercial production by year-end 2017 Fekola la Mine e Explo lorat ration ion Upside de: : Continue drilling to convert MI&I resources into 2P reserves to extend mine life Fekola la Mine e Area ea Explo lorat ration: ion: Continue drilling at the Kiwi and Fekola Deeps zones to extend the potential mineralization beyond the current known resource Fekola la Regional ional Explo loratio ration: Continue drilling on the Anaconda-Adder zones to increase the known resource and test mineralized structures below for potential Fekola-style zones Toega Prospect: ect: Complete the initial resource estimate and continue drilling to further test the potential of Toega El Limon n Mine: e: Continue exploration drilling and complete initial resource for the newly- discovered zone near the mine El Limon n Mine: e: Initiate mining tailings study Growth: : Continue near mine and greenfields exploration programs, and evaluate other growth opportunities

19

FOCUS FOR THE NEXT 12 MONTHS

Pathway to Continued Growth

slide-20
SLIDE 20

APPENDIX

20

slide-21
SLIDE 21

November 2006 December 2007 October 2008 March 2009

B2Gold Corp. was founded as a private company by the former management and technical teams of

  • Bema. The Company started as a junior exploration

company with zero gold production Completed a C$100 M IPO

  • n the TSX-V (“BTO”)

Graduated to the TSX Became a gold producer when the Company acquired El Limon gold mine and La Libertad gold project in Nicaragua

February 2010

La Libertad gold mine commenced commercial production Acquired the Otjikoto gold project in Namibia

December 2011 January 2013

Acquired the Masbate gold mine in the Philippines

June 2013

Listed on the NYSE MKT (“BTG”)

December 2013

Acquired the Kiaka gold project in Burkina Faso

October 2014

Acquired the world-class Fekola gold project in Mali

December 2014

Celebrated the Company’s first gold pour at the Otjikoto Mine (mine construction was on budget and ahead of schedule)

March 2015

The Otjikoto Mine achieved commercial production

June 2015

Approved Fekola OFS, and commenced construction of the Fekola Mine

October 2017

The Fekola Mine is scheduled to enter production on budget and is more than 3 months ahead of schedule

December 2017

The Fekola Mine is scheduled to achieve commercial production by year-end 2017, which will bring B2Gold’s projected consolidated gold production to 925 – 975 Koz in 2018

B2GOLD HISTORY

Experienced Management Team

B2Gold Corp. was founded as a private company by the former management and technical teams of

  • Bema. The Company started as a junior exploration

company with zero gold production Completed a C$100 M IPO

  • n the TSX-V (“BTO”)

Graduated to the TSX

21

slide-22
SLIDE 22

Nicara aragua: gua:

  • Reforestation
  • Water Treatment
  • Anti-epidemic Prevention
  • La Libertad

rtad & Sa Santo Doming ngo

  • Dairy

ry Chillin ling g Centre re

  • Alfa

a & O Omega ga Sewing ng Shop The Philippin ppines: :

  • Mangrove Reforestation
  • Health: TB focus
  • Education
  • Capsay

say Egg Producers ers Association (“CEPA”) Namib ibia ia: :

  • SMEs Compete
  • LifeLine/ChildLine
  • Little Shop of Physics
  • Otjiko

koto

  • Nature

re Reserv erve e & the Namib ibian ian Chamber ber of Environme ronment nt Mali: i:

  • Relocation of Fadougou

Village

  • Adéqu

équation ation Formatio ion- Emploi

  • i dans

ns le Cèrcle le de Keniéba (“AFECK”) Project

22

Responsible Mining: Raising the Bar

Dairy Chilling Centre, Nicaragua Otjikoto Nature Reserve, Namibia Skills for employment initiative, Mali

KEY CSR INITIATIVES

CEPA, the Philippines

slide-23
SLIDE 23

23

Mali, i, West t Africa ica

MINING IN MALI

Fekola Project: Further Details

slide-24
SLIDE 24

24

FEKOLA MINE

Flowchart

slide-25
SLIDE 25

25

Photo Cation Here

FEKOLA MINE

Fekola Plant has a design throughput of 5 Mtpa (607 tonnes per hour) Overall plant recovery designed to be 92.5% Includes:

  • Primary single stage gyratory

crusher

  • SABC grinding circuit
  • Residence time for leaching is 24

hours Design Details (i)

Recently-taken photograph looking southwest at the Fekola gold plant

slide-26
SLIDE 26

26

FEKOLA MINE

Gyratory crusher: 42” x 65” SAG mill: 36’ diameter (“dia”) x 20’ Ball mill: 24’ dia x 38’ Leach tank: 17.2 m dia x 18 m Number of leach tanks: 6 Leach tank residence time: 24 hours Design Details (ii)

Looking northwest at the Fekola gold plant

slide-27
SLIDE 27

The mill was constructed by B2Gold’s world-class construction team with the same attention to detail and safety as all of its other projects:

  • More than 1,300 employees during peak construction
  • More than 1,100 Malians (the remaining employees are from 23 different countries)

Earthworks:

  • Almost 5 M cubic metres (“m3“) of material has been moved and placed to construct

the project

  • Completion of a fully-lined (670,000 square metres of lining) tailings facility (1,230,000

m3 of material placed for dam embankment)

27

FEKOLA MINE CONSTRUCTION

Construction Details: By Numbers1

1. All data through August 2017

slide-28
SLIDE 28

28

FEKOLA PLANT CONSTRUCTION

The mill construction was completed more than 3 months ahead of schedule (including the expansion) and the plant is expected to produce gold in mid- October 2017 The mill is expected to ramp up to commercial production by year-end 2017 Key successes include:

  • 43,000 tonnes (“t”) of material shipped to site via Senegal (2 border

crossings)

  • Amount of concrete poured: 35,000 m3
  • Amount of steel constructed: 2,600 t
  • Amount of piping installed: 58 km
  • Platework constructed: 573 t
  • Fabricated tanks: 1.3 t

1. All data through August 2017

Construction Details: By Numbers1

Fekola mill with power plant in the background, Fekola Mine SAG mill, Fekola Mine

slide-29
SLIDE 29

The Philipp ippin ines, es, Southe theast st Asia

29

MINING IN THE PHILIPPINES

Masbate Mine Long mining history Strong mineral potential Favorable investment / tax regime: 30% corporate tax, 2% excise tax, income tax holiday for B2Gold expired on June 30, 2017 Masbate Mine is the largest employer and contributor to GDP on Masbate Island

slide-30
SLIDE 30

30

REGULATORY UPDATE

1. The Department of Environment and Natural Resources

B2Gold is recognized as one of the most responsible mining companies in the Philippines. The company believes it is in compliance with the laws and regulations in the Philippines and will continue to operate responsibly and work closely with local communities and all levels of government In 2016, the DENR1 announced preliminary audit results based on environmental, health and safety and social criteria for open-pit mining companies, including the Masbate Mine B2Gold provided a comprehensive response to the findings and recommendations from the Masbate Mine audit and believes that all points have been appropriately addressed with no material environmental or social issues raised In February 2017, the DENR announced further results of its mining audit and the Masbate Mine was not among the mines announced to be suspended or closed. Operations at the Masbate Mine continued uninterrupted throughout the period and the Company continues to work closely with the DENR While there has been controversy surrounding open-pit mining in the Philippines, the President has recently stated publicly that he supports lawful, responsible mining and that compliant companies should be given permits

slide-31
SLIDE 31

31

MASBATE MINE

Profile1 FH 2017 gold production of 102,492 oz (9% above budget) FH 2017 cash operating costs at $520/o /oz (22% below budget) FH AISC 2017 at $838/o /oz (21% below budget) Improvement against budget mainly due to better than expected throughput and recoveries driven by higher than expected oxide ore from the Colorado open pit FY 2017 gold production is now expected to be at the high end of the revised guidance range of 180–185 Koz (original guidance 175–185 Koz) Initiating an enhanced mill expansion study

Location Philippines P&P gold reserves 2.68 Moz M&I gold resources 3.65 Moz Inferred gold resources 0.24 Moz 2017 E gold production 180–185 Koz 2017 E cash op. costs (/oz) $595–$635 2017 E AISC (/oz) $935–$975 2018 E gold production 175–185 Koz 2017 exploration budget $5.06 M 2017 capex $57.46 M

1. Refer to slides 42 – 46 for Mineral Reserves & Resources summary, and respective footnotes

slide-32
SLIDE 32

32

Namibia ibia, , Southw thwes estern tern Africa ica

MINING IN NAMIBIA

Population of 2.3 M (2011 World Bank estimate) Strong history of mining Mining plays a vital role in the Namibian economy Stable government Encourages foreign investment Mining corporate tax rate: 37.5%, NSR 4% Favourable tax treatment on capital expenditures Good national infrastructure 3 km from paved National Highway B1 Otjikoto Mine Infrastructure

  • Good water supply on site
  • Self generating power supply
  • Deep-water port access (Walvis Bay)

Otjikoto Mine

slide-33
SLIDE 33

33

OTJIKOTO MINE

Profile1

Ownership 90% Location Namibia P&P gold reserves 0.99 Moz M&I gold resources 1.23 Moz Inferred gold resources 0.30 Moz 2017 E gold production 170–180 Koz 2017 E cash op. costs (/oz) $480–$520 2017 E AISC (/oz) $725–$765 2018 E gold production 150–160 Koz 2017 exploration budget $5.07 M 2017 capex $49.74 M

FH 2017 gold production of 83,937 oz (17% above budget) FH 2017 cash operating costs at $467/o /oz (26% below budget) FH 2017 AISC at $721/o /oz (41% below budget) Positive results are due to better than expected grade and ore tonnage from the Wolfshag

  • pen pit and higher than expected mill throughput

Forecast gold production is weighted towards the second half of the year 2017 gold production is expected to be at the high end of the revised guidance range of 170 –180 Koz (original guidance 165–175 Koz) Evaluating the open pit and underground interface to determine the optimal mine plan and project economics for the Wolfshag open pit expansion

1. Refer to slides 42 – 46 for Mineral Reserves & Resources summary, and respective footnotes

slide-34
SLIDE 34

34

Nicaragua, ragua, Centr tral l America rica

MINING IN NICARAGUA

Long mining history with a strong Mining Law Rated the safest country in Central America Modern infrastructure and easily accessible Democratic Republic Government supportive of foreign investment Tax regime: 3% NSR and 30% Net Profits Tax Currency pegged to USD, no foreign currency risk La Libertad & El Limon Mines (i)

slide-35
SLIDE 35

35

MINING IN NICARAGUA

B2Gold is one of the major employers in Nicaragua with more than 3,000 employees and contractors B2Gold is the largest exporter of gold in the country and the largest individual exporting company in the country Major contributor to local and national economy, one of the largest tax payers Strong commitment to social programs

Nicaragua, ragua, Centr tral l America rica

La Libertad & El Limon Mines (ii)

slide-36
SLIDE 36

36

LA LIBERTAD MINE

Profile1

Ownership 100% Location Nicaragua P&P gold reserves 0.12 Moz M&I gold resources 0.21 Moz Inferred gold resources 0.46 Moz 2017 E gold production 90–100 Koz 2017 E cash op. costs (/oz) $795–$835 2017 E AISC (/oz) $1.075–$1,115 2018 E gold production 140–150 Koz 2017 exploration budget $7.16 M 2017 capex $26.52 M

FH 2017 gold production of 51,154 oz (7% below budget) FH 2017 cash operating costs at $778/o /oz z (9% above budget) FH 2017 AISC at $965/o /oz (4% above budget) Looking forward, focus is on:

  • Accelerated development of the new San Juan and Mojon open pits
  • Accelerated development of the Jabali open pit and underground

Continue infill and exploration drilling

1. Refer to slides 42 – 46 for Mineral Reserves & Resources summary, and respective footnotes

slide-37
SLIDE 37

37

EL LIMON MINE

Profile1 FH 2017 gold production of 16,601 oz (31% below budget) FH 2017 cash operating costs at $1,149/ 9/oz

  • z (46% above budget)

FH 2017 AISC at $1,727/oz

  • z (30% above budget)

Improved control of underground water has been achieved with the successful rehabilitation

  • f a key dewatering well enabling the development of the lower levels of Santa Pancha 1

which should improve access to higher grade ore Additional mining equipment has resulted in improved haul fleet availability allowing for more tonnage to be delivered to the mill Expecting to complete an initial resource for the newly-discovered zone near the mine (Q4 2017) Completing a study to determine the economic viability of the mining tailings project

Ownership 95% Location Nicaragua P&P gold reserves 0.15 Moz M&I gold resources 0.41 Moz Inferred gold resources 0.14 Moz 2017 E gold production 40–50 Koz 2017 E cash op. costs (/oz) $815–$855 2017 E AISC (/oz) $1,415–$1,455 2018 E gold production 60–70 Koz 2017 exploration budget $6.96 M 2017 capex $12.98 M

1. Refer to slides 42 – 46 for Mineral Reserves & Resources summary, and respective footnotes

slide-38
SLIDE 38

38

Population of 20.1 M Landlocked country with principal contributions to GDP being agriculture and mining 5th largest gold producer in Africa (41.6 t in 2016) and 19th largest global producer 8 gold development projects in the pipeline 7 gold mines have been built in the past 12 years Gold accounts for 1/3 of export revenues in Burkina Faso Attractive exploration destination on the prolific West African Shield

Geology map of Burkina Faso

BURKINA FASO

Kiaka Project & Toega Prospect

Burk rkin ina Faso,

  • ,

West t Africa ica

slide-39
SLIDE 39

39

Profile1

KIAKA PROJECT

One of the largest undeveloped gold resources in West Africa Prior to the Kiaka acquisition in December 2013, B2Gold determined that the Kiaka deposit would require higher gold prices or nearby exploration success to become economically viable Low acquisition cost of approximately $48 M in B2Gold shares Optionality on gold price and exploration upside Mining permit received in Q4 2015 Decree formalizing the Kiaka exploitation permit issued in July 2016

Ownership 81% Location Burkina Faso P&P gold reserves n/a M&I gold resources 3.94 Moz Inferred gold resources 0.82 Moz 2017 E exploration budget $10.16 M2

1. Refer to slides 42 – 46 for Mineral Reserves & Resources summary, and respective footnotes 2. The majority of the Burkina Faso exploration budget is for the Toega Prospect

slide-40
SLIDE 40

40

Kiaka Regional Exploration

TOEGA PROSPECT

On February 13, 2017, B2Gold announced positive exploration drill results at the new Toega prospect near the Kiaka deposit and has increased the footprint of known mineralization at Toega – additional drill results are expected to be released in Q4 2017 Drilling is ongoing with the objectives of expanding known mineralization at Toega and stepping out to test for additional mineralization at other targets in the region Mineralization remains open down dip and down plunge at Toega Based on the positive results to date and due to the increased size of the Toega zone, the Company now expects to release the initial mineral resource for Toega before year-end 2017 B2Gold has commenced metallurgical testing and studies to support permitting

slide-41
SLIDE 41

Country try Proje ject Totals ls % Mali Fekola/Regional $15,355,296 29.2% Burkina Faso Kiaka/Regional $10,157,392 19.3% Nicaragua La Libertad $7,161,165 12.7% Namibia Otjikoto $5,071,581 9.6% The Philippines Masbate $5,055,463 9.6% Nicaragua El Limon $6,964,254 9.4% Finland Various $2,622,047 5.0% Ghana Bui $1,045,717 2.0% USA Rockland $874,307 1.7% Colombia AGA $398,700 0.8% Nicaragua Nica Regional $374,631 0.7% Total $55,0 ,080 80,55 ,553 100.0 .0%

2017 Summary

41

EXPLORATION BUDGET

slide-42
SLIDE 42

1. Refer to following slide for Footnotes

As of December 31, 2016

42 Mine Tonnes es (t) Gold ld Grade ade (g/t

t Au)

Contained tained Gold ld Ounce ces (oz)

z)

Contained tained Gold ld Kilogr

  • grams (kg)

g)

Fekola 43,800,000 2.37 3,340,000 103,900 Masbate 95,290,000 0.88 2,683,000 83,500 Otjikoto 23,140,000 1.33 986,000 30,700 La Libertad 1,910,000 1.94 119,000 3,700 El Limon 1,130,000 4.20 152,000 4,700 Tot

  • tal

al Probab able le Minera eral l Reserv serves s

(incl ncludes Stockpiles)

7,281,0 81,000 00 226,50 500

PROBABLE MINERAL RESERVE ESTIMATES1

slide-43
SLIDE 43

1. Mineral Reserves have been classified using the 2014 CIM Definition Standards for Mineral Resources and Mineral Reserves. All tonnage, grade and contained metal content estimates have been rounded; rounding may result in apparent summation differences between tonnes, grade, and contained metal content. 2. Fekola Project: Mineral Reserves are reported on a 90% attributable basis; the remaining 10% interest will be held by the State of Mali. We expect that the State of Mali will exercise its right to acquire an additional 10% interest in the Fekola Project. For further details of

  • ur interest in the Fekola Project, see the heading “Material Properties – Fekola Project – Property Description, Location and Access” of the Company’s Annual Information Form. The Mineral Reserves have an effective date of December 31, 2016. The Qualified Person for

the estimate is Peter Montano, P.E., who is our Project Director. Mineral Reserves are based on a conventional open pit mining method, gold price of US$1,250/oz, metallurgical recovery of 92.7%, and average operating cost estimates of US$2.90/t mined (mining), US$20.25/t processed (processing) and US$3.72/t processed (general and administrative). Reserve model dilution and ore loss was applied through whole block averaging such that at a 0.8 g/t Au cutoff there is a 2.8% increase in tonnes, a 3.1% reduction in grade and 0.5% reduction in ounces when compared to the Mineral Resource model. An additional 5% dilution and 2% ore loss was applied during pit optimization and scheduling. Mineral Reserves are reported above a cutoff grade of 0.8 g/t Au. 3. Masbate Gold Project: Mineral Reserves are reported on a 100% attributable basis. Pursuant to the ore sales and purchase agreement between Filminera Resources Corporation(“Filminera”) and Philippine Gold Processing & Refining Corporation (“PGPRC”), our wholly-

  • wned subsidiary, PGPRC has the right to purchase all ore from the Masbate Gold Project. The Mineral Reserves have an effective date of December 31, 2016. The Qualified Person for the estimate is Kevin Pemberton, P.E., who is our Chief Mine Planning Engineer. Mineral

Reserves are based on a conventional open pit mining method, gold price of US$1,250/oz, modeled metallurgical recovery (resulting in average LOM metallurgical recoveries by pit that range from 65% to 82%), and operating cost estimates of US$1.50/t mined (mining), a variable ore differential cost by pit (average cost is US$0.17), US$9.36–10.18/t processed (processing) and US$2.30–3.84/t processed (general and administrative). Dilution and ore loss were applied through block averaging such that at a cutoff of 0.45 g/t Au, there is a 5% increase in tonnes, a 6% reduction in grade and 1% reduction in ounces when compared to the Mineral Resource model. Mineral Reserves are reported at cutoffs that range from 0.46–0.49 g/t Au. 4. Otjikoto Mine: Mineral Reserves are reported on a 90% attributable basis; the remaining 10% interest is held by EVI Mining (Proprietary) Ltd., a Namibian empowerment company (“EVI”). The Mineral Reserves have an effective date of December 31, 2016. The Qualified Person for the estimate is Peter Montano, P.E., who is our Project Director. Mineral Reserves that will be mined by open pit methods assume a gold price of US$1,250/oz, metallurgical recovery of 98%, and operating cost estimates of US$1.75/t mined (mining), US$13.00/t processed (processing) and US$3.00/t processed (general and administrative). Dilution and ore loss was applied through block averaging such that at a cutoff of 0.45 g/t Au, there is a 1% decrease in tonnes, a 4% reduction in grade and 5% reduction in

  • unces when compared to the Mineral Resource model. Mineral Reserves are reported at a cutoff of 0.45 g/t Au.

5. La Libertad Mine: Mineral Reserves are reported on a 100% attributable basis, and have an effective date of December 31, 2016. The Qualified Person for the estimate is Kevin Pemberton, P.E., who is our Chief Mine Planning Engineer. Mineral Reserves are based on a conventional open pit mining method, gold price of US$1,250/oz, metallurgical recoveries that range from 90% to 94%, and operating cost estimates of US$3.88/t mined (mining), US$13.31/t processed (processing) and US$4.13/t processed (general and administrative). Dilution and ore loss was applied to the Jabali material through block averaging such that at a cutoff of 0.75-0.76 g/t Au, there is a 15% increase in tonnes, a 26% reduction in grade and 14% reduction in ounces when compared to the Mineral Resource

  • model. No dilution is applied to spent-ore. Mineral Reserves are reported at cutoffs that range from 0.70–0.76 g/t Au.

6. El Limon Mine: Mineral Reserves are reported on a 95% attributable basis; the remaining 5% interest is held by Inversiones Mineras S.A. (“IMISA”). The Mineral Reserves have an effective date of December 31, 2016. The Qualified Person for the estimate is Kevin Pemberton, P.E., who is our Chief Mine Planning Engineer. Mineral Reserves are based on underground long-hole stoping mining methods, gold price of US$1,250/oz, metallurgical recovery of 93.5%, and operating cost estimates of US$58.05–82.39/t of ore mined (mining), US$26.33/t of ore processed (processing) and US$13.14/t processed (general and administrative). Dilution of 20-30% is applied to most zones in addition to 90% mine recovery for all zones. Mineral Reserves are reported at cutoffs that range from 3.04–3.22 g/t Au. 7. Stockpiles: Mineral Reserves are reported in the totals for the Masbate and Otjikoto mines, and were prepared by mine site personnel at each operation. Ore stockpile balances are derived from mining truck movements to individual stockpiles or detailed surveys, with grade estimated from routine grade control methods. Stockpile cutoffs vary by deposit, from 0.25–0.7 g/t Au. 8. For additional information regarding our mineral projects, including mineral resources and reserves, please refer to our Annual Information Form dated March 31, 2017.

43

NOTES TO MINERAL RESERVE ESTIMATES

slide-44
SLIDE 44

1. Refer to slide 46 for footnotes

As of December 31, 2016

44

MEASURED & INDICATED MINERAL RESOURCE ESTIMATES1

Mine Tonnes (t) Gold Grade (g/t Au) Containe ined Gold Ounces (oz) z) Containe ined Gold Kilograms ms (kg) Measured Kiaka 27,310,000 1.09 953,000 29,600 Gramalote 15,980,000 0.79 406,000 12,600 Total l Measure ured Mineral ral Resourc rces 1,359, 359,000 000 42,300 ,300 Indicated Fekola 65,820,000 2.13 4,499,000 139,900 Masbate 126,820,000 0.89 3,649,000 113,500 Otjikoto 30,410,000 1.26 1,230,000 38,200 La Libertad 2,800,000 2.36 212,000 6,600 El Limon 2,530,000 5.06 411,000 12,800 Kiaka 96,830,000 0.96 2,986,000 92,900 Gramalote 70,230,000 0.48 1,092,000 34,000 Total l Indicated Minera ral l Resourc rces (inclu ludes Stoc

  • ckpiles

iles) 14,079, ,079,000 000 437,900 7,900 Measured and Indicated Fekola 65,820,000 2.13 4,499,000 139,900 Masbate 126,820,000 0.89 3,649,000 113,500 Otjikoto 30,410,000 1.26 1,230,000 38,200 La Libertad 2,800,000 2.36 212,000 6,600 El Limon 2,530,000 5.06 411,000 12,800 Kiaka 124,140,000 0.99 3,938,000 122,500 Gramalote 86,220,000 0.54 1,498,000 46,600 Total l Measure ured and Indicated Minera ral l Resourc rces (inclu ludes Stoc

  • ckpiles

iles) 15,438, ,438,000 000 480,20 0,200

slide-45
SLIDE 45

As of December 31, 2016

45

INFERRED MINERAL RESOURCE ESTIMATES1

Mine Tonnes es (t) Gold ld Grade ade (g/ g/t Au) Contained tained Gold ld Ounce ces (oz) Contained tained Gold ld Kilogr

  • grams (kg)

Fekola 4,430,000 1.73 246,000 7,600 Masbate 10,100,000 0.74 240,000 7,500 Otjikoto 1,720,000 5.42 299,000 9,300 La Libertad 2,900,000 4.94 460,000 14,300 El Limon 1,000,000 4.43 142,000 4,400 Kiaka 27,330,000 0.93 815,000 25,300 Gramalote 143,060,000 0.40 1,841,000 57,200 Total l Infer erred ed Miner eral l Resou

  • urce

ces 4,042 42,00 ,000 125,7 ,700 00

1. Refer to following slide for Footnotes

slide-46
SLIDE 46

46

1. Mineral Resources have been classified using the 2014 CIM Definition Standards for Mineral Resources and Mineral Reserves. Mineral Resources are reported inclusive of those Mineral Resources that have been modified to Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. All tonnage, grade and contained metal content estimates have been rounded; rounding may result in apparent summation differences between tonnes, grade, and contained metal content. 2. Fekola Project: Mineral Resources are reported on a 90% attributable basis; the remaining 10% interest will be held by the State of Mali. We expect that the State of Mali will exercise its right to acquire an additional 10% interest in the Fekola Project. For further details of

  • ur interest in the Fekola Project, see the heading “Material Properties – Fekola Project – Property Description, Location and Access” of the Company’s Annual Information Form. The Mineral Resources have an effective date of December 31, 2016. The Qualified Person

for the estimate is Tom Garagan, P.Geo., who is our Senior Vice President, Exploration. Mineral Resource estimates assume an open pit mining method, gold price of US$1,400/oz, metallurgical recovery of 92.7%, and average operating cost estimates of US$2.90/t mined (mining), US$20.25/t processed (processing) and US$3.72/t processed (general and administrative). Mineral Resources are reported at a cutoff of 0.6g/t Au. 3. Masbate Gold Project: Mineral Resources are reported on a 100% attributable basis. Pursuant to the ore sales and purchase agreement between Filminera and PGPRC, our wholly-owned subsidiary, PGPRC has the right to purchase all ore from the Masbate Gold Project. The Mineral Resources have an effective date of December 31, 2016. The Qualified Person for the estimate is Tom Garagan, P.Geo., who is our Senior Vice President, Exploration. Mineral Resource estimates assume an open pit mining method, gold price of US$1,400/oz, modeled metallurgical recovery (resulting in average LOM metallurgical recoveries by pit that range from 65% to 82%), and operating cost estimates of US$1.50/t mined (mining), a variable ore differential cost by pit (average cost is US$0.17), US$9.36–10.18/t processed (processing) and US$2.30–3.84/t processed (general and administrative). Mineral Resources are reported at an average cutoff of 0.42 g/t Au. 4. Otjikoto Mine: Mineral Resources are reported on a 90% attributable basis; the remaining 10% interest is held by EVI. The Mineral Resources have an effective date of December 31, 2016. The Qualified Person for the estimate is Tom Garagan, P.Geo., who is our Senior Vice President, Exploration. Mineral Resource estimates that are amenable to open pit mining methods assume a gold price of US$1,400/oz, metallurgical recovery of 98%, and operating cost estimates of US$1.75/t mined (mining), US$13.00/t processed (processing) and US$3.00/t processed (general and administrative). Mineral Resources that are amenable to open pit mining are reported at a cutoff of 0.40 g/t Au. Mineral Resources that are amenable to underground mining are reported at cutoff of 3.00 g/t Au. 5. La Libertad Mine: Mineral Resources are reported on a 100% attributable basis, and have an effective date of December 31, 2016. The Qualified Person for the estimate is Brian Scott, P.Geo., who is our Vice President, Geology and Technical Services. Mineral Resource estimates assume an open pit mining method, gold price of US$1,400/oz, metallurgical recoveries that range from 90% to 94%, and operating cost estimates of US$3.88/t mined (mining), US$13.31/t processed (processing) and US$4.13/t processed (general and administrative). Mineral Resources are reported at cutoffs that range from 0.61–2.85 g/t Au. 6. El Limon Mine: Mineral Resources are reported on a 95% attributable basis; the remaining 5% interest is held by IMISA. Mineral Resources have an effective date of December 31, 2016. The Qualified Person for the estimate is Brian Scott, P.Geo., who is our Vice President, Geology and Technical Services. Mineral Resource estimates assume underground long-hole stoping mining methods, a gold price of US$1,400/oz, metallurgical recovery of 93.5%, and operating cost estimates of US$58.05–82.39/t of ore mined (mining), US$26.33/t of ore processed (processing) and US$13.14/t processed (general and administrative). Mineral Resources are reported at cutoffs that range from 2.7–2.9 g/t Au. 7. Kiaka Project: Mineral Resources are reported on an 81% attributable basis; the remaining interest is held by GAMS-Mining F&I Ltd (9%) a Cypriot company, and the Government of Burkina Faso (10%). The Mineral Resource estimate has an effective date of January 8,

  • 2013. The Qualified Person for the estimate is Ben Parsons, MSc, MAusIMM (CP), Principal Consultant for SRK Consulting. Mineral Resources assume an open pit mining method, gold price of US$1,400/oz, metallurgical recovery of 89.8%, and operating cost estimates
  • f US$1.58/t mined (mining), US$11.89/t processed (processing, and general and administrative). Mineral Resources are reported at a cutoff of 0.4 g/t Au.

8. Gramalote Project: Mineral Resources are reported on a 49% attributable basis; the remaining 51% interest is held by AngloGold Ashanti Limited. Mineral Resources have an effective date of October 6, 2015. The Qualified Person for the estimate is Vaughan Chamberlain, FAusIMM, Senior Vice President, Geology and Metallurgy for AngloGold. Mineral Resources assume an open pit mining method, gold price of US$1,400, metallurgical recovery of 95%, and operating cost estimates of US$5.40/t processed (processing) and US$1.19 /t processed (general and administrative). Mineral Resources are reported at a cutoff of 0.1 g/t Au. 9. Stockpiles: Mineral Resources are reported in the totals for the Masbate and Otjikoto mines, and were prepared by mine site personnel at each operation. Ore stockpile balances are derived from mining truck movements to individual stockpiles or detailed surveys, with grade estimated from routine grade control methods. Stockpile cutoffs vary by deposit, from 0.25–0.7 g/t Au. 10. For additional information regarding our mineral projects, including mineral resources and reserves, please refer to our Annual Information Form dated March 31, 2017.

NOTES TO MINERAL RESOURCE ESTIMATES

slide-47
SLIDE 47

47

CONTACT DETAILS

B2Gold Corp

Suite 3100, 595 Burrard Street P.O. Box 49143 Vancouver, BC, Canada, V7X 1J1 Tel: : +1 604 681 8371 Toll Free: e: +1 800 316 8855 Fax: +1 604 681 6209 Email: l: investor@b2gold.com Websit ite: e: www.b2gold.com

Clive Johnson

President, CEO & Director +1 604 681 8371

Ian MacLean

Vice President, Investor Relations +1 604 681 8371

Katie Bromley

Manager, Investor Relations & Public Relations +1 604 681 8371