Yerba Buena Island Ramps Improvements Treasure Island Development Authority SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 12 MARCH 2014 14 YBI Ramps Project Overview Reconstruct WB On & Off-Ramps Project is separate and


  1. Yerba Buena Island Ramps Improvements Treasure Island Development Authority SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 12 MARCH 2014 14

  2. YBI Ramps Project Overview • Reconstruct WB On & Off-Ramps • Project is separate and independent of the SFOBB project • Construction phase funded with Federal (Highway Bridge Program) & State (Prop 1B-Seismic Retrofit) funds - $77.5M YBI Project – Off-Ramp YBI Project - On-Ramp YBI Project – Macalla Road SFOBB Project SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 2

  3. YBI Ramps Current Status • Plans, Specifications, & Estimates (PS&E) & Right of Way Certification complete – March 2013 • Construction funds approved $77.5M – July 2013 • Executed TIDA Agreements & Construction Management services contract - July 2013 • Transportation Authority will administer the construction contract with Caltrans & TIDA oversight • Contract to Golden State Bridge – December 2013 SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 3

  4. YBI Ramps Construction Contract Advertisement • Invitation for Bids - September 3, 2013 • 14 Builders Exchanges & Plan Rooms • Legal ad San Francisco Chronicle and Examiner • Ads - multiple minority & industry publications • Mandatory Pre-Bid meeting – September 17, 2013 • 12.5% Disadvantaged Business Enterprise (DBE) goal SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 4

  5. YBI Ramps Construction Contract Advertisement • Bid Opening November 5, 2013 • Walsh Construction Company - $46,183,331.00; - 4.50% DBE commitment • Golden State Bridge, Inc. - $49,305,345.50; - 13.83% DBE commitment • M.C.M. Construction, Inc. - $52,492,422.00; - 3.93% DBE commitment • Engineer’s Estimate - $53,384,963 SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 5

  6. YBI Ramps Construction Contract Advertisement • Walsh Construction Company failed to meet DBE goal or demonstrate adequate Good Faith Effort (GFE) • Good Faith Effort Reconsideration - November 27, 2013 • Walsh Construction Company - Non-Responsive Bid • Local Agency Public Construction Act (California Public Contract Code Sections 20100) • Golden State Bridge Inc. lowest responsible/responsive bidder @ $49,305,345.50. • Awarded to Golden State Bridge December 2013 SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 6

  7. YBI Ramps Construction Contract Advertisement • Golden State Bridge Inc. - DBE participation: 13.83% • Total of 13 DBE firms • 3 San Francisco based • 6 Woman-owned • 3 Asian-owned • 3 African American-owned • 3 Hispanic-owned SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 7

  8. YBI Ramps Construction Contract Advertisement • Golden State Bridge Inc. - DBE subcontractors: • Bradley Tanks, Inc. (BTI); Woman - Asian-Pacific owned • Cal-Con Pumping; Woman owned- SF based • Empire Engineering; African American owned • Norcal Structural; Asian Pacific owned • Municon Consultants; Woman owned – SF based • BioMaAs; African American owned – SF based • Rupert Construction Supply; Woman owned • Western Traffic Supply; Hispanic owned • Oliveira Fence; Woman owned • Roby Trucking; Asian owned • Kustum Steel; Hispanic owned • A B S L Constructors; Hispanic owned • CJC Trucking; Woman - African American owned SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 8

  9. YBI Ramps Construction Contract Allotment • Construction Contract Allotment: • Contractor bid: $49,305,345.50 • Supplemental work budget: $1,751,360 • State/Agency furnished materials: $2,172,200 • Subtotal: $53,228,905.50 • Contingency (20%): $10,645,781 • Total Construction Contract Allotment: $63,874,686 SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 9

  10. Construction Status • Work Commenced January 2014 • 550 working days • Completion estimated Summer 2016 • Upcoming Key Milestones • Macalla and Forest Road Detours- Summer 2014 • Quarters 10 relocation to Clipper Cove – Summer 2014 SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 10

  11. Macalla and Forest Road Detours SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 11

  12. Quarters 10 to be Relocated to Clipper Cove SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 12

  13. Commencement Ceremony SAN FRANCISCO COUNTY TRANSPO PORTATION AUTHORITY 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.