Treasure Island Development Program Wastewater Treatment Plant - - - PowerPoint PPT Presentation

treasure island development program
SMART_READER_LITE
LIVE PREVIEW

Treasure Island Development Program Wastewater Treatment Plant - - - PowerPoint PPT Presentation

Treasure Island Development Program Wastewater Treatment Plant - Planning Update February 8, 2017 Treasure Island Development Authority Agenda Background Information WWTP Planning Process Status Update Draft MOU Between TIDA and


slide-1
SLIDE 1

Treasure Island Development Authority

Treasure Island Development Program

Wastewater Treatment Plant - Planning Update February 8, 2017

slide-2
SLIDE 2

Treasure Island Development Authority

Agenda

 Background Information  WWTP Planning Process – Status Update  Draft MOU Between TIDA and SFPUC  Process Technology  Schedule and Next Steps  Discussion

2

slide-3
SLIDE 3

Treasure Island Development Authority

Background Information

slide-4
SLIDE 4

Treasure Island Development Authority

Development Plan

  • 8,000 Homes
  • 140,000 sf New Commercial

and Retail Space

  • 100,000 square feet New

Office Space

  • Three Hotels, up to 500 Hotel

Rooms

  • 300 acres of Parks and Public

Open Space

US Coast Guard US DOL Job Corps Center

slide-5
SLIDE 5

Treasure Island Development Authority

Land Use Plan from D4D

NEW WWTP SITE

The WWTP as depicted is approximately 5.74 acres, and the PUC lot is approximately 5.88 acres

slide-6
SLIDE 6

Treasure Island Development Authority 6

Definitions

  • Plan anticipates new Wastewater Treatment Facilities delivering

recycled water for distribution across island for irrigation and building systems

slide-7
SLIDE 7

Treasure Island Development Authority

DDA & Related Documents

Document Requirements or Purpose

  • EDC MOA

TIDA and Navy Agreement: Navy keeps (E) WWTP through 2020

  • DDA INFRASTRUCTURE

PLAN

TIDA and TICD (Developer) Agreement (Section 7.10): contemplates that the SFPUC will provide a new or upgraded wastewater treatment plant as needed to meet the flow and treatment requirements of the Project projected for each Major Phase; TICD prepares pad; TIDA readies land; SFPUC builds (N) Plant and deconstructs (E) Plant when ready

  • Draft PUC-TIDA WWTP

MOU

TIDA and SFPUC Agreement: Provides parameters and responsibilities for operating (E) WWTP and designing and constructing (N) Plant

  • EIR

WWTP parcel is described as 4-6 acres (not to exceed 6 acres)

slide-8
SLIDE 8

Treasure Island Development Authority

Land Transfer - Upcoming

slide-9
SLIDE 9

Treasure Island Development Authority

WWTP Planning Process

slide-10
SLIDE 10

Treasure Island Development Authority

Agency Permit

  • RWQCB – Regional Water

Quality Control Board

  • NPDES or WDR for discharge water quality
  • Establishes required performance criteria for

WWTP operation

  • BCDC -- Bay Conservation

and Development Commission

  • Outfall, if required
  • USACOE -- U.S. Army Corps
  • f Engineers
  • Construction permits for wastewater facilities

discharging to Waters of the U.S.

  • USFWS, F&G -- U.S. Fish &

Wildlife Service, California Dept of Fish & Game, Coastal Conservancy, etc.

  • Environmental Permits required for

Wastewater Treatment Facility, including WWTP and Outfall and Recycled Water Facility, if discharging to Waters of the U.S.

Permits

slide-11
SLIDE 11

Treasure Island Development Authority

Phases and Elements of WWTP Planning

  • 1. Pre- Solicitation Phase
  • a. Finalize TIDA-SFPUC MOU
  • b. Confirm Study Area
  • c. Determine Regulatory Objectives – Preliminary RWQCB Permit
  • d. Evaluate and Determine Procurement Method
  • 2. Solicitation Phase
  • a. Request for Bids – Design or Design/Build Team
  • b. SFPUC – TIDA Steering Committee
  • 3. Implementation Phase
  • a. Design
  • b. Construct
  • c. Operate New Plant
  • d. Decommission Old Plant
slide-12
SLIDE 12

Treasure Island Development Authority

Study: Determine treatment process, footprint, delivery method

Delivery Method: Design and bid (or D / B ?) contract to construct new plant

Target: Operational by 2022

Funding: SFPUC has budgeted $63M over 3 years beginning FY 16/17

New WWTP – Determine Needs and Approach

slide-13
SLIDE 13

Treasure Island Development Authority

Step 3 Design and Construct Step 2 Award Design-Build Team Step 1 Study and RFP

New WWTP – Delivery Method?

DESIGN – BUILD

Step 4 Construction Step 3 Bid and Award Step 2 Design Step 1 Study

DESIGN – BID – BUILD VS.

slide-14
SLIDE 14

Treasure Island Development Authority

Draft MOU Between SFPUC and TIDA

slide-15
SLIDE 15

Treasure Island Development Authority

Key Elements of the WWTP MOU Between SFPUC and TIDA

 Responsibility of Parties

  • Design and Construct
  • Ownership
  • Operations & Maintenance
  • Permits

 Capacity Requirements

  • Average Dry Weather Flow (ADWF)
  • Peak Dry Weather Flow (PDWF)
  • Peak Wet Weather Flow (PWWF)
  • Recycled Water Flow

 Conditions Precedent to Construction

  • Site Preparation and delivery
  • Regulatory and Environmental Permit Approvals

 Real Property Considerations

slide-16
SLIDE 16

Treasure Island Development Authority

SFPUC MOU for WWTP

DDA calls for TIDA and SFPUC to negotiate a Memorandum

  • f Understanding ("SFPUC MOU") that includes:

(i) the terms upon which SFPUC will provide a new or upgraded wastewater treatment plant for which the SFPUC will be responsible for the financing and construction; (ii) a process for SFPUC to provide a service plan in response to each Major Phase Application, including milestones such as target dates for planning, design, regulatory approvals and entitlements and permits necessary to meet the proposed service plan; (iii) a meet and confer process among the Authority, Master Developer and the SFPUC if the SFPUC fails to meet the milestones in the SFPUC MOU (iv)a meet and confer process among the Authority, Master Developer and the SFPUC if timing of the WWTP interferes with Subdivision Map or Building Permit approvals.

16

slide-17
SLIDE 17

Treasure Island Development Authority

Process Technology

slide-18
SLIDE 18

Treasure Island Development Authority

Alternatives Proposed for Evaluation in the Scoping Study

  • Pretreatment / Primary treatment technology alternatives
  • Secondary treatment technology alternatives
  • Conventional activated sludge (CAS)
  • Options for sequencing batch reactors (SBRs)
  • Options for membrane bioreactors (MBRs)
  • Options for biological aerated filters (BAFs)
  • Tertiary treatment
  • Options for constructed wetlands
  • Biosolids treatment technology alternatives (to produce

Class A biosolids)

slide-19
SLIDE 19

Treasure Island Development Authority

Alternatives Proposed for Evaluation in the Scoping Study

  • Biosolids thickening technology alternatives
  • Options for rotary drums
  • Options for gravity belts
  • Biosolids dewatering technology alternatives
  • Options for screw presses
  • Options for belt presses
  • Options for centrifuges
  • Biosolids drying alternatives (natural gas or digester gas, or solar

assisted dryers)

  • Odor control technology alternatives:
  • Options for chemical scrubbers
  • Options for biofilters
  • Options for polishing media filters
slide-20
SLIDE 20

Treasure Island Development Authority

Alternatives Proposed for Evaluation in the Scoping Study

  • Disinfection technology alternatives (must meet Title 22 CCR

disinfected tertiary recycled water treatment requirements):

  • Options for chlorination with dechlorination of any effluent not

recycled

  • Options for UV disinfection with chlorination of effluent sent to the

RWF

  • Disinfected tertiary recycled water filtration treatment

technology alternatives (must meet Title 22 CCR filtered wastewater treatment requirements):

  • Options for granular media filtration
  • Options for cloth media filtration
  • Options for membrane filtration
slide-21
SLIDE 21

Treasure Island Development Authority

WWTP Planning Area

PLANNING AREA For NEW WWTP SITE

slide-22
SLIDE 22

Treasure Island Development Authority

Schedule and Next Steps

slide-23
SLIDE 23

Treasure Island Development Authority

WWTP Schedule

New Plant by Year 2022 Existing Plant conveyed to TIDA at end of 2020

slide-24
SLIDE 24

Treasure Island Development Authority

Next Steps in WWTP Delivery

MOU

 Take to TIDA Board & SFPUC Commission in March 2017

PLANNING

SFPUC hiring Project Manager for TI WWTP – expected February 2017

Prepare CER – Conceptual Engineering Report

  • Determine Procurement Method
  • Determine Treatment Process
  • Determine Site Footprint

Prepare and Issue RFP – for Design Engineer OR Design-Build Team DESIGN & CONSTRUCTION (Design/Build or Design-Bid-Build)

Design

Construction

Start-up and Commissioning

De-Commission Existing Plant

slide-25
SLIDE 25

Treasure Island Development Authority

Discussion