Treasure Island Development Authority
Treasure Island Development Program
Wastewater Treatment Plant - Planning Update February 8, 2017
Treasure Island Development Program Wastewater Treatment Plant - - - PowerPoint PPT Presentation
Treasure Island Development Program Wastewater Treatment Plant - Planning Update February 8, 2017 Treasure Island Development Authority Agenda Background Information WWTP Planning Process Status Update Draft MOU Between TIDA and
Treasure Island Development Authority
Wastewater Treatment Plant - Planning Update February 8, 2017
Treasure Island Development Authority
Background Information WWTP Planning Process – Status Update Draft MOU Between TIDA and SFPUC Process Technology Schedule and Next Steps Discussion
2
Treasure Island Development Authority
Treasure Island Development Authority
and Retail Space
Office Space
Rooms
Open Space
US Coast Guard US DOL Job Corps Center
Treasure Island Development Authority
NEW WWTP SITE
The WWTP as depicted is approximately 5.74 acres, and the PUC lot is approximately 5.88 acres
Treasure Island Development Authority 6
recycled water for distribution across island for irrigation and building systems
Treasure Island Development Authority
Document Requirements or Purpose
TIDA and Navy Agreement: Navy keeps (E) WWTP through 2020
PLAN
TIDA and TICD (Developer) Agreement (Section 7.10): contemplates that the SFPUC will provide a new or upgraded wastewater treatment plant as needed to meet the flow and treatment requirements of the Project projected for each Major Phase; TICD prepares pad; TIDA readies land; SFPUC builds (N) Plant and deconstructs (E) Plant when ready
MOU
TIDA and SFPUC Agreement: Provides parameters and responsibilities for operating (E) WWTP and designing and constructing (N) Plant
WWTP parcel is described as 4-6 acres (not to exceed 6 acres)
Treasure Island Development Authority
Treasure Island Development Authority
Treasure Island Development Authority
Agency Permit
Quality Control Board
WWTP operation
and Development Commission
discharging to Waters of the U.S.
Wildlife Service, California Dept of Fish & Game, Coastal Conservancy, etc.
Wastewater Treatment Facility, including WWTP and Outfall and Recycled Water Facility, if discharging to Waters of the U.S.
Treasure Island Development Authority
Treasure Island Development Authority
Study: Determine treatment process, footprint, delivery method
Delivery Method: Design and bid (or D / B ?) contract to construct new plant
Target: Operational by 2022
Funding: SFPUC has budgeted $63M over 3 years beginning FY 16/17
Treasure Island Development Authority
Step 3 Design and Construct Step 2 Award Design-Build Team Step 1 Study and RFP
DESIGN – BUILD
Step 4 Construction Step 3 Bid and Award Step 2 Design Step 1 Study
DESIGN – BID – BUILD VS.
Treasure Island Development Authority
Treasure Island Development Authority
Responsibility of Parties
Capacity Requirements
Conditions Precedent to Construction
Real Property Considerations
Treasure Island Development Authority
DDA calls for TIDA and SFPUC to negotiate a Memorandum
(i) the terms upon which SFPUC will provide a new or upgraded wastewater treatment plant for which the SFPUC will be responsible for the financing and construction; (ii) a process for SFPUC to provide a service plan in response to each Major Phase Application, including milestones such as target dates for planning, design, regulatory approvals and entitlements and permits necessary to meet the proposed service plan; (iii) a meet and confer process among the Authority, Master Developer and the SFPUC if the SFPUC fails to meet the milestones in the SFPUC MOU (iv)a meet and confer process among the Authority, Master Developer and the SFPUC if timing of the WWTP interferes with Subdivision Map or Building Permit approvals.
16
Treasure Island Development Authority
Treasure Island Development Authority
Class A biosolids)
Treasure Island Development Authority
assisted dryers)
Treasure Island Development Authority
disinfected tertiary recycled water treatment requirements):
recycled
RWF
technology alternatives (must meet Title 22 CCR filtered wastewater treatment requirements):
Treasure Island Development Authority
PLANNING AREA For NEW WWTP SITE
Treasure Island Development Authority
Treasure Island Development Authority
New Plant by Year 2022 Existing Plant conveyed to TIDA at end of 2020
Treasure Island Development Authority
MOU
Take to TIDA Board & SFPUC Commission in March 2017
PLANNING
SFPUC hiring Project Manager for TI WWTP – expected February 2017
Prepare CER – Conceptual Engineering Report
Prepare and Issue RFP – for Design Engineer OR Design-Build Team DESIGN & CONSTRUCTION (Design/Build or Design-Bid-Build)
Design
Construction
Start-up and Commissioning
De-Commission Existing Plant
Treasure Island Development Authority