Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal Conference SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY July
Today’s Agenda
2
Project Background RFQ Scope of Services SOQ Evaluation SOQ Requirements RFQ Key Information Q&A
Project Location
Project Setting
Site Conditions – Treasure Island Road
5
Steep Terrain Limited Access
Seismic Strategy – Retrofit & Replacement
Structure No. 1 (Retrofit))
Site Conditions – Retrofit Bridges
8
Steep Terrain Erosion / Slides
Structure No. 4 (Retrofit)
Structure No. 7A / 7B (Retrofit)
Structure No. 8 (Retrofit)
Site Conditions – Replacement Structures
12 12
Structure 2 (Demolish)
Structure 3 (Demolish)
Structure 6 (Demolish)
Replacement Project
16 16
Replacement Project
17 17
Replacement Project
1 8
TIMMA Tolling
1 9
Road Closures to Expedite Construction
20 20
Close Westside I-80 Ramps Close Treasure Island Road between Macalla
Road and Forest Road Intersections
21 21
CABLE HOUSE
Project Challenges that warrant CMGC Delivery
► Geotechnical – Unstable
Soil Swale
► Steep terrain –
Construction Access
► Complex Bridge/Wall
Foundation Construction
► Rock Anchor (110’ long)
Tie-back Retaining Walls
► Environmental constraints
– Birds, Plants, etc.
► Storm water - proximity to
SF Bay
► Cost Containment
CM Responsibilities and Services
22 22
RFQ pages 33-34:
Construction Manager Responsibilities Cost-Related Preconstruction Services Schedule-Related Preconstruction Services Administrative-Related Preconstruction Services
RFQ Scope of Services
23 23
Pre-construction Tasks (RFQ page 105):
Task 1: Project Team Kickoff Workshop Task 2: Initial Approach to Cost Meeting Task 3: Partnering Task 4: Project Meetings and Document Review Task 5: Risk Management Task 6: Innovation Management Task 7: Project Construction Schedule Development Task 8: Project Construction Cost Estimate Development Task 9: Development of Subcontracting Plan Task 10: Development of DBE Goal Plan Task 11: Preconstruction Field Work Task 12: Construction Agreed Price Bid(s) of Fixed Unit Price Bid
RFQ Evaluation Criteria
24 24
Scored SOQ Categories (RFQ page 25):
Proposer Organization and Key Personnel Firm Experience and Past Performance Project Understanding and Approach
SOQ Format Requirements
25 25
SOQ organization (RFQ page 37):
Transmittal Letter and Appendix C – Form G Six text sections: ▪ Section 1 – Legal Structure ▪ Section 2 – Financial Capacity ▪ Section 3 – Safety Program ▪ Section 4 – Firm Experience and Past Performance ▪ Section 5 – Proposer Organization and Key Personnel ▪ Section 6 – Project Understanding and Approach (max 15 pages)
Appendices: ▪ Appendix A – Resumes ▪ Appendix B – Legal Documents *Cover letter, each section and two appendices shall be combined in one three-ring binder
SOQ Submission Requirements
26 26
Submitted by 8/10; 2:00 p.m. (RFQ page 23):
One unbound original of SOQ & cost proposal Four bound hard copies of proposal & cost proposal One electronic copy of proposal & cost proposal Exhibits ▪ Appendix C, Forms A-M (Forms H and I sealed separately) ▪ Appendices D and E (sealed separately from cost proposal)
RFQ Key Information
27 27
Funding:
Federal Highway Bridge Program and State Prop 1B Funds
Budget:
Pre-construction Services Contract Limit: $675,000 Estimated Construction Contract Value: $55,300,000
DBE Goal: Will be established near end of final design Schedule:
Pre-construction Contract Award: October 2018 Anticipated Award of Construction Contract: December 2019 Substantial Completion of Project: August 2021
RFQ Key Information
28 28
Important Dates:
July 24 (5:00 pm): Written questions due to info@sfcta.org July 30: SFCTA posts responses to questions August 10 (2:00 pm): Proposals due to SFCTA’s offices August 20: Invitations to interview sent August 27-31: Interviews tentatively scheduled
CM/GC Contractor Services for YBI Westside Bridges Retrofit Project
Project Name: Yerba Buena Island (YBI) Westside Bridges Retrofit Description: Construction Manager/General Contractor (CM/CG) contractor services for YBI Westside Bridges Retrofit Estimated Contract: $675,000 Preconstruction Services; $55.3M Construction Funding Source: Federal Highway Bridge Program and State Prop 1B Funds Projected DBE Goal: DBE will be established near end of final design. DBE certified by California Unified Certification Program (CUCP) for Construction Phase RFQ Issuance: July 10, 2018 Project Schedule: Preconstruction Services: October 2018 thru December 2019 Construction: January 2020 thru August 2021 Project Contact: Eric Cordoba, eric.cordoba@sfcta.org Service Specialties: Preconstruction Services and Construction of: undercrossing structure, bridge retrofit, retaining walls, bridge demolition, roadway realignment