Services for the Yerba Buena Island Westside Bridges Project RFQ - PowerPoint PPT Presentation

Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal Conference SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY July


  1. Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal Conference SA SAN N FRAN ANCI CISCO SCO COUN OUNTY Y TRAN ANSPO SPORT RTATIO TION N AUTH UTHORIT RITY July ly 20, 2018

  2. Today’s Agenda  Project Background  RFQ Scope of Services  SOQ Evaluation  SOQ Requirements  RFQ Key Information  Q&A 2

  3. Project Location

  4. Project Setting

  5. Site Conditions – Treasure Island Road  Steep Terrain  Limited Access 5

  6. Seismic Strategy – Retrofit & Replacement

  7. Structure No. 1 (Retrofit))

  8. Site Conditions – Retrofit Bridges  Steep Terrain  Erosion / Slides 8

  9. Structure No. 4 (Retrofit)

  10. Structure No. 7A / 7B (Retrofit)

  11. Structure No. 8 (Retrofit)

  12. Site Conditions – Replacement Structures 12 12

  13. Structure 2 (Demolish)

  14. Structure 3 (Demolish)

  15. Structure 6 (Demolish)

  16. Replacement Project 16 16

  17. Replacement Project 17 17

  18. Replacement Project 1 8

  19. TIMMA Tolling 1 9

  20. Road Closures to Expedite Construction  Close Westside I-80 Ramps  Close Treasure Island Road between Macalla Road and Forest Road Intersections 20 20

  21. Project Challenges that warrant CMGC Delivery ► Geotechnical – Unstable Soil Swale ► Steep terrain – Construction Access ► Complex Bridge/Wall Foundation Construction ► Rock Anchor (110’ long) Tie-back Retaining Walls ► Environmental constraints – Birds, Plants, etc. ► Storm water - proximity to SF Bay CABLE HOUSE ► Cost Containment 21 21

  22. CM Responsibilities and Services  RFQ pages 33-34:  Construction Manager Responsibilities  Cost-Related Preconstruction Services  Schedule-Related Preconstruction Services  Administrative-Related Preconstruction Services 22 22

  23. RFQ Scope of Services  Pre-construction Tasks (RFQ page 105):  Task 1: Project Team Kickoff Workshop  Task 2: Initial Approach to Cost Meeting  Task 3: Partnering  Task 4: Project Meetings and Document Review  Task 5: Risk Management  Task 6: Innovation Management  Task 7: Project Construction Schedule Development  Task 8: Project Construction Cost Estimate Development  Task 9: Development of Subcontracting Plan  Task 10: Development of DBE Goal Plan  Task 11: Preconstruction Field Work  Task 12: Construction Agreed Price Bid(s) of Fixed Unit Price Bid 23 23

  24. RFQ Evaluation Criteria  Scored SOQ Categories (RFQ page 25):  Proposer Organization and Key Personnel  Firm Experience and Past Performance  Project Understanding and Approach 24 24

  25. SOQ Format Requirements  SOQ organization (RFQ page 37):  Transmittal Letter and Appendix C – Form G  Six text sections: ▪ Section 1 – Legal Structure ▪ Section 2 – Financial Capacity ▪ Section 3 – Safety Program ▪ Section 4 – Firm Experience and Past Performance ▪ Section 5 – Proposer Organization and Key Personnel ▪ Section 6 – Project Understanding and Approach (max 15 pages)  Appendices: Appendix A – Resumes ▪ ▪ Appendix B – Legal Documents *Cover letter, each section and two appendices shall be combined in one three-ring binder 25 25

  26. SOQ Submission Requirements  Submitted by 8/10; 2:00 p.m. (RFQ page 23):  One unbound original of SOQ & cost proposal  Four bound hard copies of proposal & cost proposal  One electronic copy of proposal & cost proposal  Exhibits ▪ Appendix C, Forms A-M (Forms H and I sealed separately) ▪ Appendices D and E (sealed separately from cost proposal) 26 26

  27. RFQ Key Information  Funding:  Federal Highway Bridge Program and State Prop 1B Funds  Budget:  Pre-construction Services Contract Limit: $675,000  Estimated Construction Contract Value: $55,300,000  DBE Goal: Will be established near end of final design  Schedule:  Pre-construction Contract Award: October 2018  Anticipated Award of Construction Contract: December 2019  Substantial Completion of Project: August 2021 27 27

  28. RFQ Key Information  Important Dates:  July 24 (5:00 pm): Written questions due to info@sfcta.org  July 30: SFCTA posts responses to questions  August 10 (2:00 pm): Proposals due to SFCTA’s offices  August 20: Invitations to interview sent  August 27-31: Interviews tentatively scheduled 28 28

  29. CM/GC Contractor Services for YBI Westside Bridges Retrofit Project Project Name: Yerba Buena Island (YBI) Westside Bridges Retrofit Description: Construction Manager/General Contractor (CM/CG) contractor services for YBI Westside Bridges Retrofit Estimated Contract: $675,000 Preconstruction Services; $55.3M Construction Funding Source: Federal Highway Bridge Program and State Prop 1B Funds Projected DBE Goal: DBE will be established near end of final design. DBE certified by California Unified Certification Program (CUCP) for Construction Phase RFQ Issuance: July 10, 2018 Project Schedule: Preconstruction Services: October 2018 thru December 2019 Construction: January 2020 thru August 2021 Project Contact: Eric Cordoba, eric.cordoba@sfcta.org Service Specialties: Preconstruction Services and Construction of: undercrossing structure, bridge retrofit, retaining walls, bridge demolition, roadway realignment 29 29

  30. Questions? SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.