Water Treatment Facility Public Involvement Meeting NTC W ausau, WI March 6, 2019 Upgrade Aging Infrastructure Meter Shop 1961 (58 years old) 1974 (45 years old) 1984 (35 years old) 1999 (20 years old) | 9 | Improve Water Quality


slide-1
SLIDE 1

Water Treatment Facility

Public Involvement Meeting – NTC W ausau, WI March 6, 2019

slide-2
SLIDE 2

Upgrade Aging Infrastructure

| 9 |

1974 (45 years old) 1961 (58 years old) 1984 (35 years old) 1999 (20 years old)

Meter Shop

slide-3
SLIDE 3

Improve Water Quality

| 1 |

0.00 0.02 0.04 0.06 0.08 0.10 0.12 System (Existing) Pilot Treatment (Future)

Manganese

EPA Aesthetic Goal

5 10 15 20 25 System (Existing) Pilot Treatment (Future)

Color

Color TOC

EPA Aesthetic Goal for Color

1 2 3 4 5 6 7 8 Well 3 Well 6 Well 7 Well 9 Well 10 Well 11

Total Organic Carbon of Wausau Wells

Total Organic Carbon

TOC RANGE OF MOST GROUNDWATERS Median of Surface Waters

slide-4
SLIDE 4

WTP Upgrade Costs

| 12 |

Item Option 1: Upgrade Existing Plant Option 2: Build New Plant at Improved Location Water Treatment Plant1 $27,000,000 $35,000,000 Well & Distribution System Upgrades2 $2,900,000 $5,900,000 Total Capital3 $29,900,000 $40,900,000

2Demo of existing facility and relocation of meter shop not included in Option 2 cost opinion 1Option 2 includes distribution system modifications to connect supply wells to new water treatment plant 3Includes engineering

slide-5
SLIDE 5

Annual Water Fee ($/yr)

All users at 37,300 gpy

50 100 150 200 250 300 350 400 450 500 Current Rate Option 1 Option 2

Residential Water Rate Perspective

| 22 |

~$7.50/mo increase ~$6.00/mo increase

slide-6
SLIDE 6

100.00 100.00

Legend

NAD_1983_HARN_WISCRS_Marathon_County_Feet

Feet Notes

DISCLAIMER: The information and depictions herein are for informational purposes and Marathon County-City of Wausau specifically disclaims accuracy in this reproduction and specifically admonishes and advises that if specific and precise accuracy is required, the same should be determined by procurement of certified maps, surveys, plats, Flood Insurance Studies, or other official

  • means. Marathon County-City of Wausau will not be responsible for any damages which result from third party use of the information and depictions herein or for use which ignores this warning.

THIS MAP IS NOT TO BE USED FOR NAVIGATION 3/6/2019 Map Created:

Parcels Section Lines/Numbers Right Of Ways

slide-7
SLIDE 7

BUREK AV BUGBEE AV E CAMPUS DR

slide-8
SLIDE 8

Water Treatment Plant Renderings

Wausau, WI

slide-9
SLIDE 9
slide-10
SLIDE 10
slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14

Decision Point

| 23 |

A decision between site alternatives will facilitate scoping and kick-off of next key phase of implementation plan