Hopewell Water Treatment Plant Virginia’s 1st Design-Build Water Treatment Plant Retrofit Project
Dave Johnson – PC Construction Laurence Zimmermann – Gannett Fleming Michael Youshock – VA American Water Ryan Ural – American Water
Hopewell Water Treatment Plant Virginias 1 st Design-Build Water - - PowerPoint PPT Presentation
Hopewell Water Treatment Plant Virginias 1 st Design-Build Water Treatment Plant Retrofit Project Dave Johnson PC Construction Michael Youshock VA American Water Laurence Zimmermann Gannett Fleming Ryan Ural American Water
Dave Johnson – PC Construction Laurence Zimmermann – Gannett Fleming Michael Youshock – VA American Water Ryan Ural – American Water
VAW is a subsidiary of American Water, the largest investor owned water/wastewater utility in the US. Provides water service to approximately 57,000 customers Operations in 4 districts in VA: Alexandria, Prince William, Warsaw & Hopewell.
Alexandria Prince William Warsaw HOPEWELL Richmond
Service to 9,300 customers, incl several large industries & Fort Lee military base. Treatment capacity: 36 MGD Plant produces potable and non-potable (industrial) grades
Source water: Appomattox River
(tidal tributary of James River)
Plant produces 2 grades of water: potable (Domestic) & non-potable (Industrial) Numerous facilities operating, nearing 100 years of service. Tidal source water, widely varying raw water quality characteristics. 6 Industrial customers use 80-85% of all water produced. Wide swing in usage patterns & limited tolerance of service disruptions.
Industrial wood tub filters at end of useful life, difficult to repair. Potable plant operating at 12 MGD firm capacity during peak months. Need additional space for office staff & maintenance facility. Existing operator’s laboratory outdated and not efficient.
REPLACEMENTS & UPGRADES IN AN ACTIVE WATER PLANT VERY TIGHT BUDGET – LARGE SCOPE OF WORK OLD FACILITY (“This Old House” for Water Treatment Plants) PROJECT SCHEDULE & TIMING
DOMESTIC SYSTEM
Increase potable system capacity to 15 MGD reliable (18 MGD total) Upgrade sedimentation basins & install tube settlers Add 2 new domestic filters & 4 new GAC vessels Add 2.5 MG clearwell Add/replace high service pumps Chemical feed improvements Administration & maintenance building additions Control & instrumentation improvements
INDUSTRIAL SYSTEM
Demolition of Industrial Wood Tub Filters Replace existing wood tubs with 4 high rate multi-media filters Wastewater improvements
Repair sed basins & install tube settlers ADDED SCOPE: Increase emergency generator power 2 new domestic filters 4 new GAC vessels New 2.5 MG clearwell Add & replace high service pumps Admin building addition Chemical feed improvements Demolish tub filters 4 new industrial filters Demolish old lab, build new one
Existing facilities failing & needed expansion of plant capacity.
Complex tie-ins required to minimize impact on operations Detailed coordination required from design to start-up.
RFQ sent to pre-qual list of engineers & contractors VAW/AW evaluated interested D/B teams. AW sent RFP to shortlisted teams. VAW/AW received proposals: costs & fees in separate sealed envelope Quals-based evaluation by Owner (with score card) Cost & Fees opened & evaluated. VAW/AW reached consensus on “best match” to project
June 2008 – American Water issues RFP July 2008 – Proposals received September 2008 – Notice of Award November 2008 – Notice to Proceed May 2009 – 60% Target Cost: $16.2M July 2009 – Groundbreaking Ceremony April 2011 – Substantial Completion June 2011 – Anticipated Final Completion December 2011 – Actual Final Completion*
12VAC5-590-190. Permits.
Construction permit issued by State Health Commissioner required prior to construction or modification of water infrastructure.
12VAC5-590-200. Procedure for obtaining a construction permit.
Requires coordination between Owner, Engineer & VA Dept of Health (VDH)
VAW’s project schedule was very ambitious with regard to start of construction & acquisition of permits.
Virginia Waterworks Regulations
To assure timely acquisition of Permits, the Owner & D/B Team met with representatives of the Virginia Dept of Health (VDH) & the City of Hopewell These meetings allowed us to:
individuals within the permitting agencies (useful when permitting questions arose)
One potential pitfall identified by VDH related to the new tube settlers proposed for the domestic sed basin. Typically, the Department requires pilot testing to substantiate the requested design parameters. Discussion with VDH allowed VAW to provide documentation indicating similar installations with these ratings in support of the permit. Once provided, the documentation was accepted and this part of the project moved forward.
During preliminary design phase, it was determined that substantial reductions in construction time could be achieved by obtaining the VDH permit in two phases:. The first would be for the 2.5 MG tank whose design required minimal time, along with reduced permit review
design was completed and submitted for permit approval. Early issuance of the tank permit allowed for its
Well into the construction of the project, it was decided to improve the standby power supply system that was currently on site. A study was conducted to establish the size of the new generator, followed by purchase & installation of the unit. The D/B process gave the Owner a means of adding this to the project at a competitive price.
Pilot filter testing of Industrial water resulted in the reduction of planned filters - from five to four.
VALUE ENGINEERING OPPORTUNITY
Improvements to the domestic sedimentation basin required the plant to continue to meet customer water demands while having approximately 50% of its pre-treatment capacity off line. All other process improvements were completed prior to initiating this outage. This included placing both the new domestic & industrial filters on-line prior to starting this work.
D/B approach facilitated good partnership between all parties from beginning to end. Upgrades to operating facility fairly well coordinated with all parties Critical tie-ins completed with minimal impact on
Value added items identified throughout process, allowed for additional scope (generator). Project completed under budget & on schedule*.
Ensure well defined scope, incl. change orders. Better defined contingency: Change Order vs. Contingency vs. Omissions Understand permitting constraints, requirements for permits & timeframes involved. Coordination with 3rd parties – Security system vendor, coordination with internal functions, GC & electrical sub.