City of Oak Ridge Water Supply, Treatment & Distribution New - - PowerPoint PPT Presentation
City of Oak Ridge Water Supply, Treatment & Distribution New - - PowerPoint PPT Presentation
City of Oak Ridge Water Supply, Treatment & Distribution New Water Treatment Plant - Pilot Testing Completed - Preliminary Engineering Report Pending end of June - Design Next Step - WIFIA Application - July 2018 submittal date -
Water Supply, Treatment & Distribution
New Water Treatment Plant
- Pilot Testing Completed
- Preliminary Engineering Report – Pending end of June
- Design – Next Step
- WIFIA Application - July 2018 submittal date
- DWSRF – Design loan tentatively approved for $3.2M
West Tennessee Avenue Water Main Replacement Project
- Construction is on-going
- 581 LF of 12” diameter and 140 LF of 8” Diameter installed to date
Hydraulic Model
- Model is completed
- Will be used to determine sizing of mains
- WDS Master Plan
- DWSRF – waiting to see if funding is available
Water Supply & Distribution – cont.
Leak Detection Study
System Wide Study Completed (approx. 300 miles of mains) 64 leaks discovered 238 gallons per minute 342,720 gallons per day = 125,092,800 gallons per year Repairs of leaks on-going Delaware tank bypass valve found open resulting in the
recirculation of water through the tank
220 GIS mapping errors found
Wastewater Treatment & Collection
Turtle Park By-Pass Pumping Project – completed Turtle Park Pump Station Rehab – ongoing Turtle Park Sewer Shed II Rehab – ongoing approximately 85%
completed
Palisades Lift Station No. 3 Replacement - completed PLC upgrades to 3 WWTP substations – completed WWTP electrical upgrades - completed TPWWTP – NPDES Permit Renewal – on-going RRWWTP – NPDES Permit Renewal – on-going
Streets
MLD paving is completed Delaware Avenue paving pending
- Subsurface drainage work is needed prior to paving (July)
Pothole repair contract
- Approximately 150 associated work orders
Asphalt
- Starting to select FY19 paving projects
Energy Savings Project
Lighting Upgrades
- Municipal Building
- CSC
- Fire Stations 1-4
- Recreation Center
- WWTP
- Scarboro Community Center
- Animal Shelter
HVAC & Control Upgrades
- Recreation Center
- CSC
- Library
Facilities
Minor Repairs Completed
₋
Leaky roofs
₋
Plumbing issues
₋
HVAC
₋
- Misc. repairs
Municipal Ladies Room Renovation Municipal Men’s Room Renovation – FY19 Roofing Study - $12M in repairs needed over the next
10 to 12 years
ADA Transition Plan
₋
New ADA Coordinator
₋
Buildings
₋
Streets
Grant Funded Projects
ORT/Tulane & ORT/E. Division (80/20)
- Contract awarded
- Preconstruction meeting – June 20th
ORT Multi-modal Sidewalk Project (95/5)
- K&H are in the preliminary design phase
- Anticipated construction 2019
Roundabout
- TDOT – Design phase on-going
- TDOT funding for construction is pending
Stormwater
Stormtile Repair (Union Valley Road)
- Contract bidding pending
- Estimated repair $75,000 to $100,000
Infrastructure Mapping
- 90% of field data collected, approx. 50% converted to GIS
Stormwater Assessment Management Program
- Developed a call-in tracking system
- Developed SOP of City’s stormwater responsibilities as advised by MTAS
- 201 total call-ins for FY18 (114 closed, 87 open)
- Current level of service – emergency based only
Training
- BZA - Conducted 3 trainings with help from MTAS
- PWD & Parks 48 personnel trained on BMP
Community Outreach
- Clinch River clean up (20 volunteers, 2 truckloads of trash collected)
- Tree give away, rain barrel workshop, Adopt-A-Stream Program
Fleet
10 20 30 40 50 60 70 80 90 1948-1985 1980-1989 1990-1994 1995-1999 2000-2004 2005-2009 2010-2014 2015-2019 1 2 16 43 58 85 55 7 NUMBER OF VEHICLES VEHICLE YEAR
Sorted by “Vehicle” Classification
- Approx. 45% over 14 years old (120 Vehicles)
- 75% of fleet is 9+ years old