City of Oak Ridge Water Supply, Treatment & Distribution New - - PowerPoint PPT Presentation

city of oak ridge water supply treatment distribution
SMART_READER_LITE
LIVE PREVIEW

City of Oak Ridge Water Supply, Treatment & Distribution New - - PowerPoint PPT Presentation

City of Oak Ridge Water Supply, Treatment & Distribution New Water Treatment Plant - Pilot Testing Completed - Preliminary Engineering Report Pending end of June - Design Next Step - WIFIA Application - July 2018 submittal date -


slide-1
SLIDE 1

City of Oak Ridge

slide-2
SLIDE 2

Water Supply, Treatment & Distribution

 New Water Treatment Plant

  • Pilot Testing Completed
  • Preliminary Engineering Report – Pending end of June
  • Design – Next Step
  • WIFIA Application - July 2018 submittal date
  • DWSRF – Design loan tentatively approved for $3.2M

 West Tennessee Avenue Water Main Replacement Project

  • Construction is on-going
  • 581 LF of 12” diameter and 140 LF of 8” Diameter installed to date

 Hydraulic Model

  • Model is completed
  • Will be used to determine sizing of mains
  • WDS Master Plan
  • DWSRF – waiting to see if funding is available
slide-3
SLIDE 3

Water Supply & Distribution – cont.

 Leak Detection Study

 System Wide Study Completed (approx. 300 miles of mains)  64 leaks discovered  238 gallons per minute  342,720 gallons per day = 125,092,800 gallons per year  Repairs of leaks on-going  Delaware tank bypass valve found open resulting in the

recirculation of water through the tank

 220 GIS mapping errors found

slide-4
SLIDE 4

Wastewater Treatment & Collection

 Turtle Park By-Pass Pumping Project – completed  Turtle Park Pump Station Rehab – ongoing  Turtle Park Sewer Shed II Rehab – ongoing approximately 85%

completed

 Palisades Lift Station No. 3 Replacement - completed  PLC upgrades to 3 WWTP substations – completed  WWTP electrical upgrades - completed  TPWWTP – NPDES Permit Renewal – on-going  RRWWTP – NPDES Permit Renewal – on-going

slide-5
SLIDE 5

Streets

 MLD paving is completed  Delaware Avenue paving pending

  • Subsurface drainage work is needed prior to paving (July)

 Pothole repair contract

  • Approximately 150 associated work orders

 Asphalt

  • Starting to select FY19 paving projects
slide-6
SLIDE 6

Energy Savings Project

 Lighting Upgrades

  • Municipal Building
  • CSC
  • Fire Stations 1-4
  • Recreation Center
  • WWTP
  • Scarboro Community Center
  • Animal Shelter

 HVAC & Control Upgrades

  • Recreation Center
  • CSC
  • Library
slide-7
SLIDE 7

Facilities

 Minor Repairs Completed

Leaky roofs

Plumbing issues

HVAC

  • Misc. repairs

 Municipal Ladies Room Renovation  Municipal Men’s Room Renovation – FY19  Roofing Study - $12M in repairs needed over the next

10 to 12 years

 ADA Transition Plan

New ADA Coordinator

Buildings

Streets

slide-8
SLIDE 8

Grant Funded Projects

 ORT/Tulane & ORT/E. Division (80/20)

  • Contract awarded
  • Preconstruction meeting – June 20th

 ORT Multi-modal Sidewalk Project (95/5)

  • K&H are in the preliminary design phase
  • Anticipated construction 2019

 Roundabout

  • TDOT – Design phase on-going
  • TDOT funding for construction is pending
slide-9
SLIDE 9

Stormwater

 Stormtile Repair (Union Valley Road)

  • Contract bidding pending
  • Estimated repair $75,000 to $100,000

 Infrastructure Mapping

  • 90% of field data collected, approx. 50% converted to GIS

 Stormwater Assessment Management Program

  • Developed a call-in tracking system
  • Developed SOP of City’s stormwater responsibilities as advised by MTAS
  • 201 total call-ins for FY18 (114 closed, 87 open)
  • Current level of service – emergency based only

 Training

  • BZA - Conducted 3 trainings with help from MTAS
  • PWD & Parks 48 personnel trained on BMP

 Community Outreach

  • Clinch River clean up (20 volunteers, 2 truckloads of trash collected)
  • Tree give away, rain barrel workshop, Adopt-A-Stream Program
slide-10
SLIDE 10

Fleet

10 20 30 40 50 60 70 80 90 1948-1985 1980-1989 1990-1994 1995-1999 2000-2004 2005-2009 2010-2014 2015-2019 1 2 16 43 58 85 55 7 NUMBER OF VEHICLES VEHICLE YEAR

Sorted by “Vehicle” Classification

  • Approx. 45% over 14 years old (120 Vehicles)
  • 75% of fleet is 9+ years old