Following Through: Oak Ridges Cleanup Program Continues Forward - - PowerPoint PPT Presentation
Following Through: Oak Ridges Cleanup Program Continues Forward - - PowerPoint PPT Presentation
Following Through: Oak Ridges Cleanup Program Continues Forward Laura Wilkerson, Deputy Manager Oak Ridge Office of Environmental Management Our work supports critical Departmental missions in Oak Ridge Complete cleanup of Oak Ridge
Our work supports critical Departmental missions in Oak Ridge
2 · energy.gov/EM
Complete cleanup of Oak Ridge Reservation to:
- Protect the region’s health
and environment
- Make clean land available
for future use
- Ensure DOE’s ongoing vital
missions Our vision is a remediated, modernized, andreindustrialized Oak Ridge Reservation
Oak Ridge includes three distinct sites with a variety of cleanup challenges
3 · energy.gov/OREM
OREM’s guiding principles are leading to cleanup successes across Oak Ridge OREM Guiding Principles:
- Remain investment worthy
- Maintain an unwavering commitment to safety
- Finish what we start
- Reduce risk to protect people and
the environment
4 · energy.gov/OREM
Accomplishing our goals has resulted in annual budget increases
Dollars in millions
Appropriation Account FY15 Enacted Budget FY16 Enacted Budget FY17 Enacted Budget FY18 Enacted Budget FY19 Enacted Budget Defense Environmental Cleanup 239.5 251.6 278.8 417.8 424.0 Non-Defense Environmental Cleanup – Historic Preservation 2.5 6.0 6.0 8.0 10.0 UE D&D Fund 189.6 211.6 213.5 214.0 212.3 Total Oak Ridge $431.2 $469.2 $498.3 $639.8 $646.3
Oak Ridge’s cleanup program employs more than 2,255 direct contractors and 75 federal employees.
5 · energy.gov/OREM
A view of ETTP before we began transforming the site
6 · energy.gov/OREM
We have made tremendous progress toward
- ur vision for ETTP
7 · energy.gov/OREM
We are nearing our Vision 2020 goal
8 · energy.gov/OREM
Today, ETTP is ready for private sector development
- 1,200+ acres of land
transferred to date
- 600+ additional acres
approved for transfer
- 14 buildings transferred
totaling 332,000 ft2
- 20 private companies
- perating at ETTP
- Site infrastructure, roads
and emergency services transferred to the City of Oak Ridge
Access to abundant power
9 · energy.gov/OREM
Large parcels of land are available
We are working to commemorate the accomplishments of Manhattan Project workers
10 · energy.gov/OREM
There are decades of work for the EM program at Y-12 and ORNL
Excess Facilities at Y-12 Excess Facilities at ORNL
- ORNL and Y-12 have 220+ excess contaminated buildings
- Oak Ridge contains 66 of DOE’s 254 high-risk facilities– far more thanany
- ther DOE site
- Wide range of physical, chemical, and nuclear hazards that present riskto
critical ongoing research and national securitymissions
11 · energy.gov/OREM
Through Congressional support, we are ramping up cleanup efforts and dispositioning legacy waste at ORNL
- Facility modifications to enable processing of
remaining U-233 inventory in design phase
LGWO Life-Extension Activities Transuranic Waste Processing and Shipments
- Funding from Congress has allowed us to begin
work at ORNL excess facilities earlier than originally anticipated
- We are beginning risk reduction and stabilization
projects primarily in the Central Campus Area
- Transuranic waste inventory processing and
disposition underway
Building 3026
12 · energy.gov/OREM
Our work enhances safety and enables future growth at ORNL
13 · energy.gov/OREM
- Funding from Congress
has allowed us to begin work at Y-12 earlier than
- riginally anticipated
- At Y-12, we are beginning
mercury risk reduction and preparing the remaining five Biology Complex buildings for demolition
Through Congressional support, we are ramping up cleanup efforts at Y-12
14 · energy.gov/OREM
Our work enhances safety and enables future growth at Y-12
15 · energy.gov/OREM
We are constructing key infrastructure to enable large-scale cleanup at Y-12
- Site preparation for the Mercury Treatment Facility is complete
- APTIM-North Wind Construction awarded contract, and construction willbegin
this year
- It will pave the way for demolition of the large, contaminated buildings atY-12
Crews constructing the retaining walls for the Mercury Treatment Facility
16 · energy.gov/OREM
Sufficient waste disposal capacity is crucial to begin the next phase of cleanup
The current onsite disposal facility, the Environmental Management Waste Management Facility
- Our current engineered disposal facility is more than 70 percent full, andwe
need additional capacity to complete cleanup at ORNL andY-12
- We concluded the Public Comment Period for the proposed new facilityin
January, and we are working with EPA and TDEC to move forward on the project.
17 · energy.gov/OREM
- With cleanup at ETTP concluding, we are working to identify areas to
locate our workforce
- Estimate needing a 20-acre area for hundreds of employees that will
be working on ORNL and Y-12’s cleanup scope
- Partnering with the Office of Science and NNSA to find the best
location and solution
We are planning the logistical and operational set-up for the next phase of cleanup
We are awarding contracts to perform the next phase of cleanup
- Oak Ridge Reservation Cleanupcontract
- Scope covers EM activities at Y-12, ORNL, andETTP
- Draft Request for Proposal being developed
- Characterization and D&D contract
- Evaluating proposals. Expect to make multiple awards
in Spring 2019
- Engineering Technical Services contract
- Procurement planning ongoing. Contract provides nuclear safety services to our
cleanup program
- DOE Information Center &Site Specific Advisory Board contract
- Procurement Planning ongoing, 8(A) opportunity.
Contact Natasha White: Natasha.White@orem.doe.gov. For additional information: https://www.emcbc.doe.gov/seb/orrcc/
19 · energy.gov/OREM
Our work is removing economic barriers and enabling DOE’s important ongoing missions
- Work at the East Tennessee Technology Park is transforming the
former uranium enrichment complex into a private industrial park
- Cleanup at Y-12 and the Oak Ridge National Laboratory is
eliminating risks, supporting modernization, opening clean land for future missions, and enabling these sites to remain at the forefront of their respective fields
New Hope Center at Y-12 Oak Ridge National Laboratory Heritage Center Industrial Park at ETTP
Questions?
21 · energy.gov/OREM