the oak ridge environmental management program progress
play

The Oak Ridge Environmental Management Program Progress and - PowerPoint PPT Presentation

The Oak Ridge Environmental Management Program Progress and Opportunities Mark Whitney Manager February 20, 2014 www.energy.gov/EM 1 Mission Complete the cleanup of the Oak Ridge Reservation to: Protect the regions health and


  1. The Oak Ridge Environmental Management Program Progress and Opportunities Mark Whitney Manager February 20, 2014 www.energy.gov/EM 1

  2. Mission Complete the cleanup of the Oak Ridge Reservation to: • Protect the region’s health and environment • Make clean land available for future use • Ensure U.S. Department of Energy’s (DOE) ongoing vital missions www.energy.gov/EM 2

  3. Program Overview Work is Organized by Cleanup Portfolios: • East Tennessee Technology Park (ETTP) • Y-12 National Security Site (Y-12) • Oak Ridge National Laboratory (ORNL) Y-12 ETTP ORNL www.energy.gov/EM 3

  4. Challenges • • Diverse, complex projects High levels of rainfall • • Declining budgets Ongoing DOE missions with billions in investment • Regulatory commitments • Balancing competing priorities • Densely populated area Historical Base Funding Profiles 550 510 $ in millions 470 430 390 350 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 www.energy.gov/EM 4

  5. East Tennessee Technology Park BEFORE AFTER • • Approximately 2,200 acres DOE legacy cleanup complete • • More than 600 buildings History commemorated • • Radiological contaminants Private-sector industrial park (primarily uranium) and wide range of chemical constituents www.energy.gov/EM 5

  6. Near-Term Plan at ETTP ETTP Cleanup and S&M Accomplishments • K-25 demolition completed • K-27 NaF traps removed and more than 100,000 feet of process pipe vented and purged • K-33 demolition complete K-25 Building • Fire Water Tower demolition complete Goals • Complete demolition of K-27 building • Prepare for demolition of remaining facilities and soil/sediment remediation K-27 Building • Continue reindustrialization to accelerate cleanup and support economic diversity www.energy.gov/EM 6

  7. Y-12 National Security Complex BEFORE AFTER • • Approximately 800 acres DOE legacy cleanup complete • • Nearly 100 excess buildings totaling High security footprint reduced 3.8 million square feet • Modernized Y-12 incorporating • 2 million pounds of mercury lost new facilities dating back to 1950s – 1960s www.energy.gov/EM 7

  8. Near-Term Plan at Y-12 Outfall 200 Accomplishments • Conceptual design of Outfall 200 Mercury Treatment Facility nearing completion • Recovery Act projects completed Goals Existing Onsite Landfill (EMWMF) • Finalize Mercury Remediation Strategy • Design/construct/operate Outfall 200 Mercury Treatment Facility • Proceed with planning for new Environmental Management Disposal Facility www.energy.gov/EM 8

  9. Oak Ridge National Laboratory BEFORE AFTER • • Approximately 4,400 acres DOE legacy cleanup complete • • Over 300 excess buildings totaling Modernized central campus 1.5 million square feet contributing to Science mission • Predominately radiological contaminants (Transuranics, Strontium, & Cesium) www.energy.gov/EM 9

  10. Near-Term Plan at ORNL TRU Waste Processing Center Accomplishments • ZPR plate transfers complete and preparations underway for CEUSP shipments (U-233 material) • Central Characterization Project returns to Transuranic Waste Processing Center • Completing final documentation for Recovery Act projects Goals • Complete processing of solid transuranic waste and ship off-site for disposal • Design/construct/operate transuranic sludge processing facility • Complete U-233 Direct Disposition Campaign and process remaining 50% of inventory Loading Zero Power Reactor Plates (U-233 Disposition) www.energy.gov/EM 10

  11. Upcoming Opportunities • Planning for three new capital asset, construction line item projects ₋ Sludge Processing Facility – Facility design ~2015 ₋ Outfall 200 Mercury Treatment Facility – Construction start ~2017 ₋ Environmental Management Disposal Facility – Construction start ~2018 • Re-competing the Transuranic Waste Processing Center contract for debris processing • Planning to compete for TRU sludge design contract and a separate contract for construction/operations • Future characterization tasks – 2014-2015 ₋ Outfall 200 footprint characterization ₋ EMDF preliminary site characterization ₋ Offsite groundwater characterization www.energy.gov/EM 11

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend