The Oak Ridge Environmental Management Program Progress and - - PowerPoint PPT Presentation

the oak ridge environmental management program progress
SMART_READER_LITE
LIVE PREVIEW

The Oak Ridge Environmental Management Program Progress and - - PowerPoint PPT Presentation

The Oak Ridge Environmental Management Program Progress and Opportunities Mark Whitney Manager February 20, 2014 www.energy.gov/EM 1 Mission Complete the cleanup of the Oak Ridge Reservation to: Protect the regions health and


slide-1
SLIDE 1

www.energy.gov/EM 1

The Oak Ridge Environmental Management Program Progress and Opportunities

February 20, 2014

Mark Whitney

Manager

slide-2
SLIDE 2

www.energy.gov/EM 2

Complete the cleanup of the Oak Ridge Reservation to:

  • Protect the region’s health and

environment

  • Make clean land available for

future use

  • Ensure U.S. Department of Energy’s

(DOE) ongoing vital missions

Mission

slide-3
SLIDE 3

www.energy.gov/EM 3

ORNL Y-12 ETTP

Work is Organized by Cleanup Portfolios:

  • East Tennessee Technology Park (ETTP)
  • Y-12 National Security Site (Y-12)
  • Oak Ridge National Laboratory (ORNL)

Program Overview

slide-4
SLIDE 4

www.energy.gov/EM 4

Challenges

  • Diverse, complex projects
  • Declining budgets
  • Regulatory commitments
  • Densely populated area
  • High levels of rainfall
  • Ongoing DOE missions with

billions in investment

  • Balancing competing priorities

350 390 430 470 510 550 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 $ in millions

Historical Base Funding Profiles

slide-5
SLIDE 5

www.energy.gov/EM 5

East Tennessee Technology Park

  • Approximately 2,200 acres
  • More than 600 buildings
  • Radiological contaminants

(primarily uranium) and wide range of chemical constituents

  • DOE legacy cleanup complete
  • History commemorated
  • Private-sector industrial park

AFTER BEFORE

slide-6
SLIDE 6

www.energy.gov/EM 6

Accomplishments

  • K-25 demolition completed
  • K-27 NaF traps removed and more than 100,000

feet of process pipe vented and purged

  • K-33 demolition complete
  • Fire Water Tower demolition complete

Goals

  • Complete demolition of K-27 building
  • Prepare for demolition of remaining facilities and

soil/sediment remediation

  • Continue reindustrialization to accelerate cleanup

and support economic diversity

ETTP Cleanup and S&M K-27 Building K-25 Building

Near-Term Plan at ETTP

slide-7
SLIDE 7

www.energy.gov/EM 7

Y-12 National Security Complex

  • Approximately 800 acres
  • Nearly 100 excess buildings totaling

3.8 million square feet

  • 2 million pounds of mercury lost

dating back to 1950s – 1960s

  • DOE legacy cleanup complete
  • High security footprint reduced
  • Modernized Y-12 incorporating

new facilities

BEFORE AFTER

slide-8
SLIDE 8

www.energy.gov/EM 8

Accomplishments

  • Conceptual design of Outfall 200

Mercury Treatment Facility nearing completion

  • Recovery Act projects completed

Goals

  • Finalize Mercury Remediation

Strategy

  • Design/construct/operate Outfall 200

Mercury Treatment Facility

  • Proceed with planning for new

Environmental Management Disposal Facility

Near-Term Plan at Y-12

Outfall 200 Existing Onsite Landfill (EMWMF)

slide-9
SLIDE 9

www.energy.gov/EM 9

Oak Ridge National Laboratory

  • Approximately 4,400 acres
  • Over 300 excess buildings totaling

1.5 million square feet

  • Predominately radiological

contaminants (Transuranics, Strontium, & Cesium)

  • DOE legacy cleanup complete
  • Modernized central campus

contributing to Science mission

AFTER BEFORE

slide-10
SLIDE 10

www.energy.gov/EM 10

Accomplishments

  • ZPR plate transfers complete and preparations

underway for CEUSP shipments (U-233 material)

  • Central Characterization Project returns to

Transuranic Waste Processing Center

  • Completing final documentation for Recovery

Act projects

Goals

  • Complete processing of solid transuranic waste and

ship off-site for disposal

  • Design/construct/operate transuranic sludge

processing facility

  • Complete U-233 Direct Disposition Campaign and

process remaining 50% of inventory

Near-Term Plan at ORNL

Loading Zero Power Reactor Plates (U-233 Disposition)

TRU Waste Processing Center

slide-11
SLIDE 11

www.energy.gov/EM 11

  • Planning for three new capital asset, construction line item projects

₋ Sludge Processing Facility – Facility design ~2015 ₋ Outfall 200 Mercury Treatment Facility – Construction start ~2017 ₋ Environmental Management Disposal Facility – Construction start ~2018

  • Re-competing the Transuranic Waste Processing Center contract for debris

processing

  • Planning to compete for TRU sludge design contract and a separate contract

for construction/operations

  • Future characterization tasks – 2014-2015

₋ Outfall 200 footprint characterization ₋ EMDF preliminary site characterization ₋ Offsite groundwater characterization

Upcoming Opportunities