Water Treatment Plant Slow Sand Filter Bed Operations and - - PowerPoint PPT Presentation

water treatment plant slow sand filter bed operations and
SMART_READER_LITE
LIVE PREVIEW

Water Treatment Plant Slow Sand Filter Bed Operations and - - PowerPoint PPT Presentation

Water Treatment Plant Slow Sand Filter Bed Operations and Maintenance Presentation Stayton Water Treatment Plant Located at 200 North First Avenue Water Treatment Plant Configuration Three acre slow sand filter basins Control Room


slide-1
SLIDE 1

Water Treatment Plant Slow Sand Filter Bed Operations and Maintenance Presentation

slide-2
SLIDE 2

Stayton Water Treatment Plant

Located at 200 North First Avenue

slide-3
SLIDE 3

Water Treatment Plant Configuration

  • Three ½ acre slow sand filter basins
  • Control Room
  • Monitors flow in, flow out, head loss, turbidity, and

PH in the ponds

  • Adds 12.5% sodium hypochlorite for disinfection
  • Adds soda ash to minimize corrosion in pipes due to

low PH

  • Clear well
  • Provides contact time to reduce chlorine in water

before leaving plant

slide-4
SLIDE 4

Water Treatment Plant Map

slide-5
SLIDE 5

Slow Sand Filter Configuration

Slow Sand Filter Bed

3 - 4 feet deep typical

Schmutzdecke (cleaning zone)

15-24 inches typical

slide-6
SLIDE 6

Slow Sand Filter Beds

  • Filter Beds 1 and 2 reconstructed in 1993
  • Filter Bed 3 reconstructed in 2010
  • Slow Sand Filter Beds use natural occurring processes

to clean water

  • Tried and true and very reliable system
  • North Santiam River is the source of Stayton water that

flows onto the slow sand filter beds

slide-7
SLIDE 7

Slow Sand Filter Maintenance

  • After a period of time of infiltrating water through the

sand the Schmutzdecke zone becomes less pervious

  • When this occurs maintenance personnel drain the

water from the filter bed and skim off the top 1-inch of sand and remove it from the filter bed

  • Each filter bed is skimmed approximately once every 8-

9 months

slide-8
SLIDE 8

Slow Sand Filter Cleaning

Public Works crew skimming Filter Bed 3 Approximately 1-inch of sand is skimmed off the entire Filter Bed and removed

slide-9
SLIDE 9

Slow Sand Filter Resanding Project

  • In December while cleaning Filter Bed 1, a crew

member noticed pea gravel dispersed around the top

  • f the sand
  • Public Works engineers performed a survey on Filter

Beds 1 and 2

  • Filter Bed 1 is in need of sand immediately
  • Filter Bed 2 will need sand in the next 2 years
  • Filter Bed 3 will need sand in the next 3 years
slide-10
SLIDE 10

Slow Sand Filter Resanding Project

  • Public Works put a Request for Bids out on March 4,

2019

  • The bid opening is March 28th, 2019
  • Engineers Estimate for the project is $650,000 -

$750,000

  • This is an unplanned expense
  • Project funding alternatives will be discussed by Andy

Parks, the City’s Financial Consultant

slide-11
SLIDE 11

Financial Impacts Water System Slow Sand Filter Maintenance Project March 2019

slide-12
SLIDE 12

Stayton Water CIP – Updated with sand filter capital 2019-2028

slide-13
SLIDE 13

Water Fund Financial Projection Key Metrics FY 2019-2028 – full CIP; no borrowing

slide-14
SLIDE 14

Water Fund Financial Projection Key Metrics FY 2019-2028 – full CIP; no borrowing

slide-15
SLIDE 15

Water Fund Financial Projections FY 2019-2028 – full CIP; 5.0% annual rate adjustments through FY 2025; 3.5% after

slide-16
SLIDE 16

Water Fund Financial Projection Key Metrics FY 2019-2028-including full CIP; incremental rates; borrowing

slide-17
SLIDE 17

Stayton Water CIP – scaled back version 2019-2028 (used with 2.0% CPI rate adjustments only)

slide-18
SLIDE 18

Water Fund Financial Projections FY 2019-2028 – scaled back CIP - 2.0% CPI rate adjustments

slide-19
SLIDE 19

Water Fund Financial Projection Key Metrics FY 2019-2028 – 2.0% CPI rate adjustments

  • nly; scaled back CIP
slide-20
SLIDE 20

Summary

  • Rate increases will be necessary to fund present level of service

and maintain sand filters

  • If no borrowing – approximately a 35% increase is needed
  • If borrowing of approximately $3.5 million during next 5 years,

rate increases of approximately 5.0%/year through FY 2025 will be necessary

  • A comprehensive rate study may be desirable
  • Rate components – can be looked at prior to a master plan update
  • Revenue requirements will need to be updated after master plan update
slide-21
SLIDE 21

Water Treatment Plant Slow Sand Filter Resanding Project

  • Questions?