treatment plant
play

TREATMENT PLANT PHASE II What is the Phase II Wastewater Treatment - PowerPoint PPT Presentation

TOWN OF FRONT ROYAL WASTEWATER TREATMENT PLANT PHASE II What is the Phase II Wastewater Treatment Plant Upgrade Project? Didnt we just complete an Upgrade? PHASE II WASTEWATER TREATMENT WHY WERE THESE ITEMS DELETED PROJECT IS ITEMS


  1. TOWN OF FRONT ROYAL WASTEWATER TREATMENT PLANT PHASE II

  2. What is the Phase II Wastewater Treatment Plant Upgrade Project? Didn’t we just complete an Upgrade?

  3. PHASE II WASTEWATER TREATMENT WHY WERE THESE ITEMS DELETED PROJECT IS ITEMS REMOVED FROM THE FROM THE CURRENT DESIGN? CURRENT DESIGN OF THE FACILITY.

  4. COST! GHD the design engineers in the upgrade project which began in 2012 put a lot of costly processes that the Town did not need or could not afford at the time.

  5. Original Cost Estimates For GHD’s Design Exceeded $60,000,000 Guidance From The Town Manager & Director of Environmental Services Requested The Cost Of The Project Be Reduced to $40,000,000 Or The Upgrade Project Would Be Postponed

  6. The Town Was Challenged To Make This Much Needed Project Happen!

  7. Processes To Be Removed And Slated For The Phase II Project How This Decision Was Made 1. Eliminate the unnecessary items from the project and have a facility to meet it’s future needs & meet the DEQ’s Regulations 2. What other factors were taken in consideration to how to reduce the cost of the Upgrade Project

  8. • Previously in the past especially the Plant Upgrade in 1992 increased the Plant’s pumping Why Not capacity from 8.0 MG to 12.0 MG Consider The I & I Consent • This extra pumping capacity met the DEQ’s requirements Order Into and keep the Town in the Design? compliance for a short while. But as time went on the sanitary sewer system continue to grow and age.

  9. How Do You Do That? • If the Town could significantly reduce the I & I coming to the Wastewater Plant some of the costly processes originally proposed could be postponed or eliminated if the Town could finally address the cloud hanging over them associated with the I & I. • Reducing this flow not only cuts down on operational costs such as chemical & electrical usage and but keeps the Town in compliance with its Discharge Permit with the DEQ. • Money spent on I & I rehabilitation of the sanitary collection system would reduce the compliance and treatment problems rather than spending nearly an additional $18 million dollars just to treat ground and surface water that has plagued the Town for years

  10. Factors To Determine Prior and during the design of this project the Town had already been placed in Consent Order of the What Processes to Virginia Department of Environmental Quality to resolve it’s current I & I issues with the Eliminate sanitary sewage collection system

  11. Processes To Keep the existing Influent Pumping Station as it currently is that can pump 12.0 MGD and eliminate Be Removed the proposed piggyback Pump Station which would And Slated have increased the facility’s Pumping Capacity to 17.0 MGD. In 2012 the Daily Average Flow was For The Phase 3.25 MGD. II Project

  12. Flow Equalization Capacity Improvements Processes To Be 3.75 MG Storm Lagoon to be used Removed in High Flow Events And Slated For The Phase #2 Grit Removal Unit. Each Grit Removal Unit is capable of handling II Project 12.0 MGD. So only 1 Grit Removal Unit would be constructed

  13. Parallel Effluent Line & Effluent Pump Station Processes To Be Removed The existing Effluent Line of the Waste Water Plant could not And handle 17.0 MG Slated For The Phase A Effluent Pump Station would be needed when a 100 year II Project flood event would ever happen

  14. By removing these processes saved the Town $16,920,00 that made the Total Cost Savings upgrade project take place! Eliminated From Phase I Note: None of these Of The Project processes were WQIF Grant Eligible.

  15. Wastewater Treatment Plant Final Cost Total cost of the Upgrade Project was $44,500,00 Warren County funded the Septage Receiving Station at $2,450,000 The facility received a WQAF Grant that funded over $13,000,000 of debt that did not have to be repaid for the Nutrient Removal & Related Processes. The recent Wastewater Plant Upgrade final cost came to $29,000,000 & the DEQ provided a 20 Year Interest Free Loan.

  16. 95% OF 5.300 MG IS 5.035 MG If this happens in a 3 month period we wilI required to have a plan!

  17. PHASE II COST ESTIMATES • In the 2019-20 Capital Improvement Budget $3,000,000 was proposed to do the Phase II Design. • The 2020-21 Capital Improvement Budget $18,000,000 is proposed to implement the Phase II Construction.

  18. • Continue to seek out and eliminate sources of I & I of the sanitary collection. Repairing and maintaining How To this infrastructure will save the Town money in from costly Plant Upgrades Avoid and keep the Wastewater Plant operating effectively in a cost effective Phase II manner

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend