Pre-Bid Conference IFB FQ12175/MDG LARGO WATER TREATMENT FACILITY - - PowerPoint PPT Presentation

pre bid conference
SMART_READER_LITE
LIVE PREVIEW

Pre-Bid Conference IFB FQ12175/MDG LARGO WATER TREATMENT FACILITY - - PowerPoint PPT Presentation

Washington Metropolitan Area Transit Authority I FB-FQ12175 Largo Water Treatment Facility Pre-Bid Conference IFB FQ12175/MDG LARGO WATER TREATMENT FACILITY Invitation For Bid (IFB)/Contract Number FQ12175 April 24, 2013 - 10:00 AM CTF


slide-1
SLIDE 1

IFB FQ12175/MDG LARGO WATER TREATMENT FACILITY

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

Pre-Bid Conference

Invitation For Bid (IFB)/Contract Number – FQ12175 April 24, 2013 - 10:00 AM CTF – Room C244

slide-2
SLIDE 2

Opening Remarks

 Silence all Cell phones and pagers 

No Recording

This presentation and attendee list will be provided on WMATA.com website

Safety Tip: “Safety Harnesses – Tie or Die; Take the right precautions to prevent falls”

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-3
SLIDE 3

 Michael D. Glimp, Sr. Contracting Consultant, PRMT  Dembo Singhateh, IRPG  Carla Grano, SAFE  Teairra Swain, DBE PRMT  Lt. Derrick Wigglesworth, MTPD  Carmen Pelham, RISK Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

Introduction of WMATA Personnel

slide-4
SLIDE 4

PURPOSE

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

 To promote a common understanding of:  IFB – Largo Water Treatment Facility

  • Authority’s requirements in Books 1 - 3
  • Solicitation Instructions

 To provide answers to questions regarding the IFB  Networking opportunity

slide-5
SLIDE 5

After today’s conference, if you have additional questions, they must be received via electronic mail by the Contracting Officer. Email your questions to Michael Glimp at mdglimp@wmata.com by COB April 26, 2013.

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

PURPOSE

slide-6
SLIDE 6

The Pre-proposal Conference is for information purposes

  • nly. It may answer some Offeror questions.

Statements or representations made during the Conference are not legally binding. Changes resulting from this Conference or the site visits are official only if issued through an Amendment to the Invitation For Bid (IFB).

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

Disclaimer Regarding Changes to the Solicitation

slide-7
SLIDE 7

All Contractors must register with WMATA at www.wmata.com “New Vendor Registration”. WMATA solicitations are publicized at www.wmata.com

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-8
SLIDE 8

 Bid Form  Representations and Certifications  Unit Price Schedule  Bid Bond  Appendix B: Disadvantaged Business

Enterprise (DBE) Forms One (1) hard copy AND One (1) electronic copy submitted on USB

BI DDI NG MATERI AL Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-9
SLIDE 9

 The outside of the envelope shall show:

  • THE AMENDMENTS RECEIVED (lower left hand

corner). Failure to acknowledge all amendments may cause the Bid to be considered not responsive.

  • MARYLAND REGISTRATION NUMBER
  • HOUR and DATE specified in the IFB for receipt, the

IFB number, and the full legal name and address of the Bidder on the face of the envelope

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

BI DDI NG MATERI AL

slide-10
SLIDE 10

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

Proposals may be received prior to, but no later than 2:00 PM, May 8, 2013

BASIS FOR AWARD: The Authority will award a contract to the lowest responsive and responsible bidder whose bid conforms to this Invitation for Bids.

BI DDI NG MATERI AL

slide-11
SLIDE 11

AWARD

Apparent Low Bidder submits Pre- Award Information within 5 days after Bid Opening WMATA will have 90 calendar days to award the Contract

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-12
SLIDE 12

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

Disadvantaged Business Enterprises Disadvantaged Business Enterprise (DBE) 32%. $500,000

  • r more for a construction contract. Submit complete schedule of DBE

participation and Letters of Intent. All DBEs must have current WMATA DBE certifications.

It is the policy of WMATA, the Federal Transit Administration (FTA) and the U.S. Department of Transportation (US DOT) that Disadvantaged Business Enterprises (DBE’s) shall have an equal opportunity to receive and participate in performing federally -assisted contracts, including contractors and subcontractors at any tier.

slide-13
SLIDE 13

BIDDER QUALIFICATIONS

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

Pre-award Evaluation Data

Adequate financial resources.  Ability to comply with required performance schedule.  Satisfactory record of performance.  Satisfactory record of integrity  Necessary organization, experience and expert technical skills, including, quality assurance measures and safety programs applicable to the construction to be performed.  Affiliation with satisfactory subcontractors capable of meeting the above requirements.  Disadvantaged Business Enterprise data as set forth in Appendix B. The submittal of certain items with the bid is required.  Insurability.

slide-14
SLIDE 14

SCHEDULE EVENT DATE RFP Release April 9, 2013 Pre-Proposal Conference April 24, 2013 Site Visit April 24, 2013 Amendment 001 April 25, 2013 Deadline for Proposer Questions May 1, 2013 WMATA Response to Proposer Questions May 3, 2013 Bid Opening May 8, 2013 Award Date (estimated) June 14, 2013 Notice to Proceed (NTP) (estimated) June 28, 2013 Contract Completion NLT January 31, 2014

Dates Subject to Change

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-15
SLIDE 15

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

TECHNICAL SPECIFICATIONS & PROJECT OVERVIEW Dembo Singhateh, IRPG Karl Liebenberg, SAFE

slide-16
SLIDE 16

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-17
SLIDE 17

IFB-FQ12175 – Largo Water Treatment Facility North Face of Building

17

slide-18
SLIDE 18

IFB-FQ12175 – Largo Water Treatment Facility South Face of Building

18

slide-19
SLIDE 19

IFB-FQ12175 – Largo Water Treatment Facility West Face of Building

19

slide-20
SLIDE 20

IFB-FQ12175 – Largo Water Treatment Facility Mechanical Floor Plan

20

slide-21
SLIDE 21

IFB-FQ12175 – Largo Water Treatment Facility Process Equipment Interior South Wall

21

slide-22
SLIDE 22

22

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-23
SLIDE 23

23

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-24
SLIDE 24

24

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-25
SLIDE 25

25

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-26
SLIDE 26

26

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-27
SLIDE 27

27

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-28
SLIDE 28

28

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-29
SLIDE 29

29

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-30
SLIDE 30

30

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-31
SLIDE 31

31

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-32
SLIDE 32

32

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-33
SLIDE 33

33

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

slide-34
SLIDE 34

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

DBE Compliance, Appendix “B”

Teairra Swain, DBE & Compliance Specialist

slide-35
SLIDE 35

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

METRO TRANSIT POLICE DEPARTMENT (MTPD)

  • Lt. Derrick Wigglesworth
slide-36
SLIDE 36

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

QUESTIONS?

slide-37
SLIDE 37

Washington Metropolitan Area Transit Authority

I FB-FQ12175 Largo Water Treatment Facility

SITE VISIT

9450 Lottsford Road Landover MD, 20774 At 1:00 PM