Wastewater Treatment Plant Preliminary Engineering Contract - - PowerPoint PPT Presentation
Wastewater Treatment Plant Preliminary Engineering Contract - - PowerPoint PPT Presentation
Wastewater Treatment Plant Preliminary Engineering Contract Amendment No. 6 Purpose The purpose of this agenda bill is to seek City Councils approval of Amendment Number 6 to the Consultant Agreement with Carollo Engineers for
Purpose
The purpose of this agenda bill is to seek City Council’s
approval of Amendment Number 6 to the Consultant Agreement with Carollo Engineers for preliminary design
- f the new Wastewater Treatment Plant in the
Windjammer Vicinity.
3/19/2013 2
Project Need
3/19/2013 3
Existing treatment facilities are outdated and nearing
capacity.
Increasingly stringent water quality standards Both outfalls have major problems Marsh surrounding lagoons reclaimed in 2009 Requirement of National Pollution Discharge Elimination
System (NPDES) permit
Project Goals
3/19/2013 4
Provide reliable wastewater treatment Meet high water quality standards Phasing opportunities Deliver a plan that keeps on track to start the new
treatment plant by the end of 2017
Objective of Preliminary Design
3/19/2013 5
Complete
Value Engineering
Finalize Location of WWTP within the Windjammer
Vicinity
Procure Major Process Equipment
Membranes UV disinfection
30 % Design Delivery Method
Design / Bid / Build Design Build General Contractor / Construction Manager (GC/CM)
Project Team
3/19/2013 6
Subconsultant Role ESA Environmental / Cultural Enviroissues Public Meeting Support Michael Willis Architects Architectural GeoEngineers Geotechnical Design Bruce Dees & Assoc Landscape Design Webster Environmental Odor Control Cosmopolitan Engineering Outfall Design Harmsen Associates Survey
City Contract Responsibility
3/19/2013 7
City Retains Control Over the Following Contracts
Value Engineering Facilitator and T
eam
Property Acquisition Expert Cultural Resource Investigator Parks / Open Space Planner Transportation Planner Commercial Real Estate Advisor Charrette Facilitator GC/CM Advisor
Scope of Services
3/19/2013 8
Task 100 – Project Management
Management Plan Monitoring and Reporting Management Meetings
Task 200 –Value Engineering (VE) Support
Conceptual level design Participation in
VE workshop
Recommendations
Scope of Services
3/19/2013 9
Task 300 – Public Process Support
Participation in charrettes Workshops Working groups City Council
Task 400 – WWTP Preliminary Design
Major equipment procurement
Membranes UV Disinfection
30% design documents
Scope of Services
3/19/2013 10
Task 500 – Project Delivery Analysis
Provide comparison of delivery methods
Task 600 – Outfall Design
100% design of new outfall Permitting
Task 700 – Management Reserve
Allows City Engineer to make minor adjustments as needed 5% of contract amount
Summary by Task
3/19/2013 11
Task Cost Task 100 – Project Management $69,978 Task 200 –Value Engineering Support $289,417 Task 300 – Public Process Support $198,610 Task 400 – WWTP Preliminary Design $964,416 Task 500 – Project Delivery Analysis $14,498 Task 600 – Outfall Design $262,363 Carollo Fee $159,152 Subconsultant Markup $23,650 Subtotal $1,982,065 Task 700 – Management Reserve (5%) $99,103 T
- tal
$2,081,168
Summary by Activity
3/19/2013 12
Task Cost “Traditional” Preliminary Design $1,511,644 Additional Services
- Value Engineering
$60,698
- Public Process
$130,037
- Outfall Design and Permitting
$279,686 Subtotal $470,421 Management Reserve $99,103 T
- tal
$2,081,168
Project Schedule
3/19/2013 13
Project Schedule
3/19/2013 14
Preliminary Design Facilities Plan Final Design Construction Start up
Project Schedule
3/19/2013 15
Verification of Scope and Cost
3/19/2013 16
Industry Guidelines
Water Environment Federation (WEF) WA Office of Financial Management 2012 CA Multi-Agency CIP Benchmarking Study
Similar Projects
Other MBR treatment plants in our region
Other City Projects
Gun Club Road North Reservoir SE Pioneer Way
Verification of Scope and Cost
3/19/2013 17
Studies Typically Address Total Cost Preliminary Design = $2,081,168 Final Design = TBD Total = 10% of Total Construction Cost
Total Design Cost
3/19/2013 18
California Multi-Agency Benchmarking Study – 2012
San Francisco Sacramento Oakland San Jose Los Angeles Long Beach San Diego
Studies
3/19/2013 19
Total Design Cost
3/19/2013 20
Similar Projects
10.7% 10.9% 16.2% 6.6% 10.7% 8.0% 10%
0.0% 2.0% 4.0% 6.0% 8.0% 10.0% 12.0% 14.0% 16.0% 18.0% 20 40 60 80 100 120 140 160 180
% of Total Construction Cost (TCC) Millions of Gallons per Day (GPD)
Gallons per Day vs. % of Total Construction Cost (TCC)
Shelton Blaine King County Bellingham Everett Salem Oak Harbor
Summary of Design Costs
3/19/2013 21
Preliminary Design = $2,081,168 Total Costs
Estimated T
- tal Construction Cost = $60 to $67 million
Design Cost = ±10% of T
- tal Construction Cost
Design Cost = $6 to $6.7 million
Final Design Contract = $4 to $4.7 million
Approximately 1 year from now
Summary
3/19/2013 22
Tasks include “Traditional” and supplemental services Does not include contracts where it is in the City’s best
interest
Design cost is included in “$93.5 million” Design Effort Cost Timing Preliminary Design $2,081,168 Today Final Design $4 to $4.7 million 1Year Total $6 to $6.7 million
Funding
3/19/2013 23
Water Fund Included in current rate structure
Requested Action
A motion to authorize the Mayor to sign Consultant
Agreement Amendment Number 6 with Carollo Engineers in the amount of $2,081,168 for preliminary design related to a new wastewater treatment plant.
3/19/2013 24
3/19/2013 25