Tryon Creek Wastewater Treatment Plant Lake Oswego P3 Partnership / - - PowerPoint PPT Presentation

tryon creek wastewater treatment plant lake oswego p3
SMART_READER_LITE
LIVE PREVIEW

Tryon Creek Wastewater Treatment Plant Lake Oswego P3 Partnership / - - PowerPoint PPT Presentation

Tryon Creek Wastewater Treatment Plant Lake Oswego P3 Partnership / Interim IGA Michael Jordan, Director B. Jonas Biery, Business Services Manager City of Portland Environmental Services SEPTEMBER 2020 Tryon Creek Wastewater Treatment Plant


slide-1
SLIDE 1

Tryon Creek Wastewater Treatment Plant Lake Oswego P3 Partnership / Interim IGA

Michael Jordan, Director

  • B. Jonas Biery, Business Services Manager

City of Portland Environmental Services

SEPTEMBER 2020

slide-2
SLIDE 2

Environmental Services l Tryon Creek Wastewater Treatment Plant 2

Tryon Creek Wastewater Treatment Plant

  • Constructed in 1964
  • Built/owned/operated by Portland,

but within Lake Oswego city limits

  • Outfalls to Willamette River under

Portland-managed NPDES permit

  • Treats wastewater from parts of SW Portland,

unincorporated areas of Multnomah and Clackamas counties, and the City of Lake Oswego

  • Managed under 1984 Intergovernmental

Agreement

  • Max/peak flow capacity of 37.5 mgd

(compared to 450 mgd at CBWTP)

  • Typical flow split is 35% from Portland / 65%

from Lake Oswego

slide-3
SLIDE 3

Environmental Services l Tryon Creek Wastewater Treatment Plant 3

Current Arrangement

Owns land Operates, maintains, and finances improvements Owns facility and equipment City of Portland (BES)

Bears majority of long-term risk

Pays share of costs (to Portland) City of Lake Oswego Existing IGA (1984) Design and build improvements (via contractors) Holds DEQ permit

slide-4
SLIDE 4

Environmental Services l Tryon Creek Wastewater Treatment Plant 4

Owns land City of Lake Oswego

Bears majority of long-term risk (and transfers to Private Party)

Owns facilities and equipment Holds DEQ permit City of Portland (BES)

Proposed / Future P3 Arrangement

Operates, maintains, and finances Improvements Pays share of costs (to Lake Oswego) Designs and builds Future IGA) Project Agreement Private Party (DBFOM)

slide-5
SLIDE 5

Environmental Services l Tryon Creek Wastewater Treatment Plant 5

Potential Benefits to Portland

  • Significantly reduces long-term risks:
  • Operations and maintenance
  • Capital reinvestment
  • Regulatory
  • Better aligns costs to actual usage of plant capacity
  • Improves effluent quality to Willamette River

(pending P3/technology capabilities)

  • Supports innovative technology and financial arrangement
  • Will be cost neutral – or better – to the City of Portland over the long-term
slide-6
SLIDE 6

Environmental Services l Tryon Creek Wastewater Treatment Plant 6

Overview of P3 vs. Existing Plant

P3 (Build New) Existing Plant

Rate Impact 0.10% average annual impact (or less) 0.10% average annual impact Operation & Maintenance Operated and maintained by P3 provider Operated and maintained by City of Portland Governance LO owns the Plant & leases to P3 provider for 30 years Portland owns the Plant Technology Updated/new technology (will meet/exceed DEQ standards) Plant built in 1965 requires major maintenance & upgrades to meet DEQ standards Footprint & Aesthetics Estimated at 6 acres and built to fit area Approximately 14 acres

slide-7
SLIDE 7

Environmental Services l Tryon Creek Wastewater Treatment Plant 7

Alternate / Fall-back Plan

  • Return to Existing 1984 IGA
  • Potential to re-align cost-share to match current usage of Plant capacity
  • Potential to extend term to another 30 years
  • Changes would require approval from City Councils (timing TBD, likely calendar 2021)
  • Lake Oswego responsible for costs of prior to RFP; costs shared 50/50

during/after RFP and Pre-Dev.

  • Continue/update Facilities Planning
  • Implement major multi-year reinvestment in existing Plant
  • Estimated capital costs of ~$250-350 million over next 30 years
  • Costs only partially reflected in current rate forecast
  • Will require permit renewals
slide-8
SLIDE 8

Environmental Services l Tryon Creek Wastewater Treatment Plant 8

Schedule – Interim IGA

MARCH Interim IGA Development Begins MAY/JUNE Council briefings JULY 14 Lake Oswego City Council Study Session SEPT 15 Lake Oswego City Council Action SEPT 16 Approval by Portland City Council SEPT 9 Interim IGA Ordinance to Portland City Council

slide-9
SLIDE 9

Environmental Services l Tryon Creek Wastewater Treatment Plant 9

Proposed Schedule – RFP & Project Development

SEPT 2020 Request for Proposals to P3 bidders DECEMBER 2020* Selection of P3 provider JANUARY 2021* Approval of Pre-Development Agreement SEPT 2021* Final pricing and approval

  • f Project Agreement

FY 2023-24* P3 treatment plant operational TBD Old/existing plant decommissioned

* Tentative/Projected

slide-10
SLIDE 10

Environmental Services l Tryon Creek Wastewater Treatment Plant 10

  • Key provisions in Interim IGA
  • Establish roles & responsibilities, process, and off-ramps for RFP and

Pre-Development Agreement

  • Cost responsibility shared 50/50 (as Project costs), or if “off-ramp” is used.
  • Establish criteria, process and off-ramps for P3 Project Agreement
  • Identify key concepts in Future IGA
  • Share of capital/operating costs based upon actual flow utilization
  • Caps Portland’s maximum annual financial commitment at amount identified as “rate neutral”
  • ver the 30-year term.
  • Ensures Portland retains compensation for amounts due under 1984/Existing IGA.
  • Assets and permit responsibility transferred to Lake Oswego

Proposed Council Action / Ordinance

slide-11
SLIDE 11

Environmental Services l Tryon Creek Wastewater Treatment Plant 11

Proposed Council Action / Ordinance

RFP & Pre-Dev

Portland participates Continued (minimal) capital investment

Future IGA & Project Agreement Existing/1984 IGA*

Project not feasible Project is feasible Councils approve Either Council disapproves

P3 Build & Transfer Operations (operational in FY2023-24)

1 2 3

Basic Deal Flow Structure

* Potential to renegotiate/modernize

1 2 3

Council Action (Interim IGA) Off-Ramp Options at Pre-Dev Agreement at 30% Design Council Action (Future IGA)

Decision Points: