washington d c
play

Washington, D.C. Penn State Architectural Engineering Senior - PowerPoint PPT Presentation

The Office Building Washington, D.C. Penn State Architectural Engineering Senior Capstone Project Brett Miller | Construction Option Advisor: Dr. Ed Gannon Brett Miller The Office Building Introduction Construction Washington, D.C.


  1. The Office Building Washington, D.C. Penn State Architectural Engineering Senior Capstone Project Brett Miller | Construction Option Advisor: Dr. Ed Gannon

  2. Brett Miller The Office Building Introduction Construction Washington, D.C. Analysis 2 | Neighboring Foundation Support Research| Retaining Structures Project Overview Analysis 1 | Foundation Walls Analysis 3 | Value Engineering

  3. Brett Miller The Office Building Project Overview Construction Washington, D.C. Presentation Outline Project Overview Project Size 108,000 SF Research | Retaining Structures Analysis 1 | Foundation Walls Height Above Grade 9 Stories Cost Schedule Contract Value $30.5 million Conclusion Dates of Construction March 2013 – March 2015 Analysis 2 | Neighboring Foundation Support Cost Occupant Undetermined Schedule Conclusion Primary Use Office Building Analysis 3 | Value Engineering Owner Mid Atlantic Realty Electrical Breadth | Sizing wire/Busway Cost General Contractor James G. Davis Construction Schedule Conclusion Architect Gensler Conclusion & Recommendations Acknowledgements

  4. Brett Miller The Office Building Research | Retaining Structures Construction Washington, D.C. Presentation Outline Project Overview Advantages Disadvantages Research | Retaining Structures Analysis 1 | Foundation Walls Costly Cost Sheet Piling (A) Watertight Excavation Time Consuming Schedule Conclusion Soldier Piles and Lagging Less Expensive Loud Installation Analysis 2 | Neighboring Foundation Support (B) Faster Not Watertight Cost Schedule Watertight Conclusion Extremely Costly Concrete Slurry Walls (C) Extreme Depths Analysis 3 | Value Engineering Time Consuming Foundation Walls Electrical Breadth | Sizing wire/Busway Cost Top Down Construction (D) Fast Schedule Geotech. Considerations Ground Stability Conclusion Conclusion & Recommendations Acknowledgements D C

  5. Brett Miller The Office Building Analysis 1 | Foundation Walls Construction Washington, D.C. Presentation Outline Project Overview Problem Identification Research | Retaining Structures Analysis 1 | Foundation Walls Cost Extensive support of excavation Schedule Conclusion Analysis 2 | Neighboring Foundation Support 60 Foundation wall box-outs Cost Schedule Formwork time/cost Conclusion Analysis 3 | Value Engineering Electrical Breadth | Sizing wire/Busway Potential Solutions Cost Schedule Conclusion Replace CIP with shotcrete to reduce formwork Conclusion & Recommendations Acknowledgements

  6. Brett Miller The Office Building Analysis 1 | Foundation Walls Construction Washington, D.C. Presentation Outline Cost Comparison Project Overview Total Cost $250,000.00 Research | Retaining Structures Cast-in-Place $314,943.96 Analysis 1 | Foundation Walls Cost Shotcrete $237,816.54 Schedule $200,000.00 Savings $77,127.42 Conclusion Analysis 2 | Neighboring Foundation Support Cost $150,000.00 Schedule Total Cost Savings Conclusion Cast-in-Place Analysis 3 | Value Engineering Shotcrete Electrical Breadth | Sizing wire/Busway $100,000.00 Cost Schedule 24.5% Savings Conclusion Conclusion & Recommendations $50,000.00 Acknowledgements $0.00 Material Labor Equipment

  7. Brett Miller The Office Building Analysis 1 | Foundation Walls Construction Washington, D.C. Presentation Outline Schedule Comparison Project Overview 30 Final Schedule Research | Retaining Structures Cast-in-Place 48 Days Analysis 1 | Foundation Walls Cost 25 Shotcrete 15 Days Schedule Savings 33 Days Conclusion Analysis 2 | Neighboring Foundation Support 20 Cost Schedule Days Total Schedule Savings Conclusion 15 Cast-in-Place Analysis 3 | Value Engineering Shotcrete Electrical Breadth | Sizing wire/Busway 10 Cost Schedule 68.8% Savings Conclusion 5 Conclusion & Recommendations Acknowledgements 0 P1 P2 P3 Level

  8. Brett Miller The Office Building Analysis 1 | Foundation Walls Construction Washington, D.C. Presentation Outline Project Overview Cast-in-Place Research | Retaining Structures $77,000 Analysis 1 | Foundation Walls Shotcrete 33 Days Cost Schedule Conclusion 60 Analysis 2 | Neighboring Foundation Support $350,000.00 Cost Schedule $300,000.00 45 Conclusion $250,000.00 Analysis 3 | Value Engineering $200,000.00 Electrical Breadth | Sizing wire/Busway 30 Cost $150,000.00 Schedule $100,000.00 Conclusion 15 Conclusion & Recommendations $50,000.00 Acknowledgements $0.00 0 Cost Schedule

  9. Brett Miller The Office Building Analysis 2 | Neighboring Foundation Support Construction Washington, D.C. Presentation Outline Project Overview Problem Identification Research | Retaining Structures Analysis 1 | Foundation Walls Cost Historic building on West property line Schedule Conclusion Analysis 2 | Neighboring Foundation Support Foundation needs supported Cost Schedule Secant Wall duration Conclusion Analysis 3 | Value Engineering Electrical Breadth | Sizing wire/Busway Potential Solutions Cost Schedule Conclusion Replace Secant Wall with Slurry Wall Conclusion & Recommendations Acknowledgements

  10. Brett Miller The Office Building Analysis 2 | Neighboring Foundation Support Construction Washington, D.C. Presentation Outline Cost Comparison Project Overview $450,000 Total Cost Research | Retaining Structures Secant Wall $551,000 Analysis 1 | Foundation Walls $400,000 Cost 24” Slurry Wall $744,000 Schedule $350,000 Additional Costs $193,000 Conclusion Analysis 2 | Neighboring Foundation Support $300,000 Cost Schedule $250,000 Conclusion Secant Wall Analysis 3 | Value Engineering 24" Slurry Wall $200,000 Electrical Breadth | Sizing wire/Busway Cost $150,000 + Schedule Conclusion $100,000 Conclusion & Recommendations 35% Increase Acknowledgements $50,000 $0 Material Labor Equipment Mob/Demob

  11. Brett Miller The Office Building Analysis 2 | Neighboring Foundation Support Construction Washington, D.C. Presentation Outline Schedule Comparison Project Overview Final Schedule 12 Research | Retaining Structures Secant Wall 15 Days Analysis 1 | Foundation Walls Cost Slurry Wall 15 Days 10 Schedule Savings 0 Days Conclusion Analysis 2 | Neighboring Foundation Support 8 Cost Schedule Conclusion Total Schedule Savings Days Secant Wall 6 Analysis 3 | Value Engineering 24" Slurry Wall Electrical Breadth | Sizing wire/Busway Cost 4 Schedule Conclusion Conclusion & Recommendations 0% Savings 2 Acknowledgements 0 Mob/Demob Installation

  12. Brett Miller The Office Building Analysis 2 | Neighboring Foundation Support Construction Washington, D.C. Presentation Outline Project Overview Research | Retaining Structures Secant Wall $193,000 Analysis 1 | Foundation Walls 0 Days Cost 24” Slurry Wall Schedule Conclusion Analysis 2 | Neighboring Foundation Support 20 $800,000 Cost Schedule Conclusion 15 $600,000 Analysis 3 | Value Engineering Electrical Breadth | Sizing wire/Busway 10 Cost $400,000 Schedule Conclusion 5 $200,000 Conclusion & Recommendations Acknowledgements $0 0 Cost Schedule

  13. Brett Miller The Office Building Analysis 3 | Value Engineering Construction Washington, D.C. Presentation Outline Project Overview Problem Identification Research | Retaining Structures Analysis 1 | Foundation Walls Cost Unforeseen costs Schedule Conclusion Analysis 2 | Neighboring Foundation Support Over budget Cost Schedule Expensive copper feeder Conclusion Analysis 3 | Value Engineering Electrical Breadth | Sizing wire/Busway Potential Solutions Cost Schedule Conclusion Replace copper wiring with less expensive system Conclusion & Recommendations Acknowledgements

  14. Brett Miller The Office Building Analysis 3 | Value Engineering Construction Washington, D.C. Presentation Outline Sizing Aluminum Wiring Sizing Aluminum Busway Project Overview 2500 𝐵 Load per Switchboard 2500 𝐵 Load per Switchboard Research | Retaining Structures Analysis 1 | Foundation Walls Cost Table 310.15 B 16 GE Spectra Series Busway Schedule Conclusion ↳ 500 𝑙𝑑𝑛𝑗𝑚 → 310 𝐵 Table 8.1 Analysis 2 | Neighboring Foundation Support Cost ↳ 2 bars → 1 1 8 " Thick per Phase & Neutral 2500 𝐵 310 𝐵 = 8.06 → 9 𝑇𝑓𝑢𝑡 ∗ 310 𝐵 = 2790 𝐵 Schedule Conclusion Table 11.1 Analysis 3 | Value Engineering Table 250 − 66 Electrical Breadth | Sizing wire/Busway ↳ 4.5" × 15.0" 15.0” Cost 𝐵𝑋𝐻 𝐵𝑀 ↳ 500 𝑙𝑑𝑛𝑗𝑚 𝐵𝑀 → 1 0 Schedule Conclusion Table C. 1 4.5” Conclusion & Recommendations Acknowledgements ↳ 4 500 𝑙𝑑𝑛𝑗𝑚 + 1 1 0 → 4" Conduit

  15. Brett Miller The Office Building Analysis 3 | Value Engineering Construction Washington, D.C. Total Cost Presentation Outline Cost Comparison Copper Wiring $330,436.85 Project Overview $200,000.00 Aluminum Wiring $313,076.71 Research | Retaining Structures Analysis 1 | Foundation Walls Aluminum Busway $225,346.06 Cost Schedule $150,000.00 Conclusion Analysis 2 | Neighboring Foundation Support Aluminum Wiring Cost Savings Aluminum Busway Cost Savings Cost Schedule Copper Wiring Conclusion $100,000.00 Aluminum Wiring Analysis 3 | Value Engineering Aluminum Busway Electrical Breadth | Sizing wire/Busway Cost Schedule $50,000.00 Conclusion Conclusion & Recommendations Acknowledgements 5% Savings 32% Savings $0.00 Material Labor

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend