Waimea Community Dam Shareholders update
June update
Waimea Water Ltd 20/06/2019 1
Waimea Community Dam Shareholders update June update 20/06/2019 - - PowerPoint PPT Presentation
Waimea Community Dam Shareholders update June update 20/06/2019 Waimea Water Ltd 1 Waimea Community Dam is underway Fully funded TDC, WIL + CIIL WWL incorporated 27 Nov 2018 Financial close 21 Dec 2018 Construction
June update
Waimea Water Ltd 20/06/2019 1
Waimea Water Ltd 20/05/2019 2
Waimea Water Ltd 20/05/2019 3
Waimea Water Ltd 20/05/2019 4
Fulton Hogan Taylors Joint Venture is the main contractor building the Dam
Waimea Water Ltd 20/05/2019 5
Waimea Water Ltd 20/05/2019 6
approved and being audited
management plans. BTAG support
Waimea Water Ltd 20/05/2019 7
Waimea Water Ltd 20/05/2019 8
Waimea Water Ltd 20/05/2019 9
In the News
Waimea Dam to aid eels on journey to Pacific – scientist, 11th December 2019, Radio New Zealand Construction of Waimea dam set to begin, 16th January 2019, Nelson Mail Waimea Water boss pumped to be part of 'legacy' dam project, 9th May 2019, Nelson Mail Waimea Water brings exec home, 9th May 2019, Farmers Weekly Waimea Water pumped and ready for more action, 7th June 2019, Waimea Weekly
Implement Health and Safety Management System complementing Contractor’s system Verify and audit Contractor compliance and track investigations Track key leading and lagging indicators Comply with Resource Consent conditions and Biodiversity Management Plan Review and audit Construction Environmental Management and Vegetation Clearance Plans Water quality monitoring ≈ Implement carbon offset (ETS) plan; and minimise carbon emissions Optimise design for safe, reliable and efficient operation Design (PS-1; PS-2) and construction (PS-4) certification ≈ Review and optimise schedule for practical completion Oct-2021
Waimea Water Ltd 20/05/2019 10
Health & Safety Sustainability Project Delivery
Waimea Water Ltd 20/05/2019 11
Risk Manage Funding Engagement
Provide regular and transparent cost and funding forecasts to completion Meet statutory and agreed financial deadlines with financial accounts. Audited Operate an effective internal control environment ≈ Active engagement with our communities and stakeholders Proportionate media and social media presence ≈ Engage Mana Whenua Implemented small and specialised organisation of experienced professionals Implemented a system to determine and mitigate risks Governing the project to mitigate cost and schedule risk
Waimea Water Ltd 20/05/2019 12
Funding and Spend Forecast cost & schedule to complete
40 60 80 100 120 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21
Millions
Project Costs Budget Project Costs Actual
8/04/2019 Waimea Water Ltd 13
Risk Management: 22% of Project Budget at Risk
Compaction trials Further Borelogs M&E Design Refine Grout Spec FM Preparedness
Identify Ownership Assess Mitigate Portfolio
Risk Register (56)
Waimea Water Ltd 20/05/2019 14
Health and Safety Compliance and Audit Late or urgent compliance issues:
Waimea Water Ltd 20/05/2019 15
August
1. Project Update 2. Annual report 3. Performance against Statement of Intent previous year
November February May
1. Project Update 1. Project Update 2. Interim (half yearly) report 3. Proposed Statement of Intent for next year 1. Project Update
Waimea Water Ltd 20/05/2019 16