Waimea Community Dam Shareholders update June update 20/06/2019 - - PowerPoint PPT Presentation

waimea community dam shareholders update
SMART_READER_LITE
LIVE PREVIEW

Waimea Community Dam Shareholders update June update 20/06/2019 - - PowerPoint PPT Presentation

Waimea Community Dam Shareholders update June update 20/06/2019 Waimea Water Ltd 1 Waimea Community Dam is underway Fully funded TDC, WIL + CIIL WWL incorporated 27 Nov 2018 Financial close 21 Dec 2018 Construction


slide-1
SLIDE 1

Waimea Community Dam Shareholders update

June update

Waimea Water Ltd 20/06/2019 1

slide-2
SLIDE 2

Waimea Community Dam is underway

  • Fully funded TDC, WIL + CIIL
  • WWL incorporated 27 Nov 2018
  • Financial close 21 Dec 2018
  • Construction commenced 14 Jan 2019
  • Organisation in place early 2019
  • Dawn Blessing March 2019

Waimea Water Ltd 20/05/2019 2

slide-3
SLIDE 3

WWL Organisation

  • Strong experienced board meeting regularly
  • Experienced and highly skilled specialists
  • Environment & Sustainability
  • Design
  • Construction
  • Project Services
  • Business & Finances

Waimea Water Ltd 20/05/2019 3

slide-4
SLIDE 4

Design

  • Damwatch has been appointed as Designer and Construction-Reviewer
  • Currently focusing on opportunities to reduce costs, optimise design and de-risking
  • 257 Drawings revised and being reissued for construction

Waimea Water Ltd 20/05/2019 4

slide-5
SLIDE 5

Construction

Fulton Hogan Taylors Joint Venture is the main contractor building the Dam

  • Access Road: 3 km of road out of 6.5 km is complete. Right Hand Abutment access underway
  • Preparatory work: Constructed Sediment Retention Ponds, cleared Pig Flat, felling trees
  • Site Monitoring: Turbidity water quality monitoring

Waimea Water Ltd 20/05/2019 5

slide-6
SLIDE 6

Construction: July - August

  • Construction of access to right hand side abutment
  • River diversion left hand side
  • Commence vegetation clearance in reservoir footprint
  • Commence clearing and excavating left and right hand sides
  • Commence constructing temporary coffer dams
  • Compaction / Permeability trials

Waimea Water Ltd 20/05/2019 6

slide-7
SLIDE 7

Environment and Sustainability

  • 121 Resource Consent conditions
  • Working 98 action items
  • Sediment Retention Ponds (Pig Flat)
  • Construction Environmental Management Plans

approved and being audited

  • Biodiversity Management Plan approved with 8 sub-

management plans. BTAG support

  • 4 rare plant species being moved (BMP #2)
  • Planning Rough Island Wetland restoration (BMP #4)
  • Planning for Emission Trading Scheme (ETS)
  • Preparing Reservoir Management Plan

Waimea Water Ltd 20/05/2019 7

slide-8
SLIDE 8

Program

Waimea Water Ltd 20/05/2019 8

slide-9
SLIDE 9

Challenges and Risks

  • Geology to be better understood 4Q2019
  • Mechanical, electrical and surveillance design finalised 4Q2019
  • Flood risk with contractor but risk to schedule. 12 May 1:50 year 47 mm/hr = 250 m3/s
  • Force Majeure: Drought / Fire risk; Disturbances

Waimea Water Ltd 20/05/2019 9

In the News

Waimea Dam to aid eels on journey to Pacific – scientist, 11th December 2019, Radio New Zealand Construction of Waimea dam set to begin, 16th January 2019, Nelson Mail Waimea Water boss pumped to be part of 'legacy' dam project, 9th May 2019, Nelson Mail Waimea Water brings exec home, 9th May 2019, Farmers Weekly Waimea Water pumped and ready for more action, 7th June 2019, Waimea Weekly

slide-10
SLIDE 10

SOI: We are doing what we said we would do

 Implement Health and Safety Management System complementing Contractor’s system  Verify and audit Contractor compliance and track investigations  Track key leading and lagging indicators  Comply with Resource Consent conditions and Biodiversity Management Plan  Review and audit Construction Environmental Management and Vegetation Clearance Plans  Water quality monitoring ≈ Implement carbon offset (ETS) plan; and minimise carbon emissions  Optimise design for safe, reliable and efficient operation  Design (PS-1; PS-2) and construction (PS-4) certification ≈ Review and optimise schedule for practical completion Oct-2021

Waimea Water Ltd 20/05/2019 10

Health & Safety Sustainability Project Delivery

slide-11
SLIDE 11

SOI: We are doing what we said we would do

Waimea Water Ltd 20/05/2019 11

Risk Manage Funding Engagement

 Provide regular and transparent cost and funding forecasts to completion  Meet statutory and agreed financial deadlines with financial accounts. Audited  Operate an effective internal control environment ≈ Active engagement with our communities and stakeholders  Proportionate media and social media presence ≈ Engage Mana Whenua  Implemented small and specialised organisation of experienced professionals  Implemented a system to determine and mitigate risks  Governing the project to mitigate cost and schedule risk

slide-12
SLIDE 12

SOI: We are doing what was said we would do

Waimea Water Ltd 20/05/2019 12

Funding and Spend Forecast cost & schedule to complete

  • 20

40 60 80 100 120 Dec-18 Jun-19 Dec-19 Jun-20 Dec-20 Jun-21 Dec-21

Millions

Project Costs Budget Project Costs Actual

slide-13
SLIDE 13

8/04/2019 Waimea Water Ltd 13

Risk Management: 22% of Project Budget at Risk

SOI: We are doing what we said we would do

Compaction trials Further Borelogs M&E Design Refine Grout Spec FM Preparedness

Identify Ownership Assess Mitigate Portfolio

Risk Register (56)

slide-14
SLIDE 14

SOI: We are doing what we said we would do

Waimea Water Ltd 20/05/2019 14

Health and Safety Compliance and Audit Late or urgent compliance issues:

slide-15
SLIDE 15

Plan: Quarterly Update to Shareholders

Waimea Water Ltd 20/05/2019 15

August

1. Project Update 2. Annual report 3. Performance against Statement of Intent previous year

November February May

1. Project Update 1. Project Update 2. Interim (half yearly) report 3. Proposed Statement of Intent for next year 1. Project Update

slide-16
SLIDE 16

Governance

Waimea Water Ltd 20/05/2019 16