update
play

Waimea Community Dam Update 25 September 2019 Waimea Water; Damwatch Engineering; Fulton Hogan Taylors 25/09/2019 Waimea Water Ltd 1 Waimea Dam is underway and progressing well Ground Breaking Ceremony 9 August 2019 24/09/2019 Waimea

0 downloads 10 Views 7,85 MB Size Report
  1. Waimea Community Dam Update 25 September 2019 Waimea Water; Damwatch Engineering; Fulton Hogan Taylors 25/09/2019 Waimea Water Ltd 1

  2. Waimea Dam is underway and progressing well Ground Breaking Ceremony 9 August 2019 24/09/2019 Waimea Water Ltd 2

  3. Agenda • Design • Construction update • Environmental update • Q&A 24/09/2019 Waimea Water Ltd 3

  4. Design • Concrete Faced Rockfill Dam Turitea Concrete Faced Rockfill dam. Palmerston North 3-D model overlaying existing site topography Constructed 1907, 1912, 1996 24/09/2019 Waimea Water Ltd 4

  5. Design Parameter ▪ Features: • 13 Mm 3 (13 billion litre) reservoir; 53m high; 220m crest length; 430,000 m 3 rock • Rockfill embankment selected as most robust to seismic loads and uses indigenous material • Concrete face membrane • Zoning of material in embankment allows for drainage paths to mitigate internal erosion • Grout curtain seals water migration around and beneath dam ▪ Earthquake: • Operating basis: No non-superficial damage and fully operational: 1:150 AEP (years) • Seismic evaluation basis: Retain reservoir & no-uncontrolled: 1:10,000 AEP (years) • GNS seismic assessment: 0.64g horizontal peak & 1.65g maximum spectral accelerations • Active faults 8 km and 12 km from site 24/09/2019 Waimea Water Ltd 5

  6. Design Parameter ▪ Flood: • Probable maximum flood (PMF): 1094 m3/s (18.6 Mm3 / 24 hour) • 100 year flood: 375 m3/s • 12 May 2019 1:50 year 250 m3/s (47 mm/hr) ▪ Operational flow • Operational flow: 2.2 m3/s • Environmental (min) flow and flushing flow: 0.5 m3/s and 5 m3/s • Maximum: 17 m3/s (1.5 mM3/d = 10% reservoir / day) ▪ Design Standards: NZSOLD / ANCOLD / ICOLD: Highest category (High PIC) 24/09/2019 Waimea Water Ltd 6

  7. Design • Damwatch supporting design enhancements and construction verification (PS-4) • Optimising zoning of rock fill materials to provide flexibility and robustness to geology • Optimised spillway design to de-risk construction and operations • Optimised plinth design and updated grout curtain specification • Mechanical and Electrical design progressing (hydropower compatible) 2009: 5-9 2012: 10-14 2017: 15-17 24/09/2019 Waimea Water Ltd 7

  8. Construction • Access Road: 5.5 km of 6.5 km complete. • Pig Flat bridges underway • Haul roads established • Concrete batching plant operational • Clearing Right Hand Abutment Inspected and mapped top exposed section • Cutting down for Left Hand Abutment • Excavating for Left Hand plinth Completed and cleaned for first 20m • River training to Left Hand side • Vegetation clearance, salvage and mulch underway 24/09/2019 Waimea Water Ltd 8

  9. Construction: Clearing LHS Abutment. As expected 24/09/2019 Waimea Water Ltd 9

  10. Construction: Clearing LHS Abutment. As expected 24/09/2019 Waimea Water Ltd 10

  11. Construction: Preparing for LHS Plinth. As expected 24/09/2019 Waimea Water Ltd 11

  12. Construction: Preparing for LHS Plinth. As expected 24/09/2019 Waimea Water Ltd 12

  13. Construction: Clearing RHS Abutment. As expected 24/09/2019 Waimea Water Ltd 13

  14. Construction: Clearing RHS Abutment. As expected 24/09/2019 Waimea Water Ltd 14

  15. Construction: Clearing RHS Abutment. As expected 24/09/2019 Waimea Water Ltd 15

  16. Construction: September to December 2019 • Clear the RHS and LHS abutments and plinth cut. Rock anchors and slope stabilisation • Commence forming plinth LHS and RHS • Construct diversion bunds to move river away from RHS for culvert construction • Excavate for and commence forming culvert in RHS of riverbed • Continue vegetation clearance in reservoir footprint 24/09/2019 Waimea Water Ltd 16

  17. Environment and Sustainability • 164 Resource Consent conditions; Working 98 action items • Biodiversity Management Plan approved with 8 plans. BTAG Onsite • 7/9 SCEMPS approved, implemented and being monitored • 4 Sediment Retention Ponds & 8 Decanting Bunds operating • Hydroseeding & mulching mitigates erosion and sedimentation • Fortnightly independent water quality monitoring complies • Continuous turbidity monitors guides river works • 2/4 rare plant species being moved (BMP #2) Offsite • Ordering 10,000 plants and weed control for Rough Island 24/09/2019 Waimea Water Ltd 17

  18. Program 12/09/2019 Waimea Water Ltd 18

  19. SOI: We are doing what was said we would do Funding and Spend Forecast cost & schedule to complete 24/09/2019 Waimea Water Ltd 19

  20. SOI: We are doing what we said we would do Risk Management: 22% of Project Budget at Risk Risk Register (56 27) Compaction trials Further Borelogs Embankment design M&E Design Refine Grout Spec FM Preparedness Identify Ownership Assess Mitigate Portfolio 24/09/2019 Waimea Water Ltd 20

  21. SOI: We are doing what we said we would do Health and Safety Compliance and Audit 0 Late or urgent compliance issues: 24/09/2019 Waimea Water Ltd 21

  22. More Information 12/09/2019 Waimea Water Ltd 22

  23. Q&A Questions? Waimea Water; Damwatch Engineering; Fulton Hogan Taylors 24/09/2019 Waimea Water Ltd 23

Recommend Documents


ooc general meeting june 5 2013
OOC General Meeting- June 5, 2013 BSEE

OOC General Meeting- June 5, 2013 BSEE Update Agenda Regulatory Update NTL

enrollment update
Enrollment Update 2 Enrollment Update

Enrollment Update 2 Enrollment Update K-12 3 Enrollment Update K-5 4

integrating user community content with systems management
Integrating User Community Content

Integrating User Community Content with Systems Management Aaron Prayther,

legal update legal update legal update legal update title
Legal Update Legal Update Legal

Legal Update Legal Update Legal Update Legal Update Title Issues

1 23 2014
1/23/2014 NWC Redevelopment Programme

1/23/2014 NWC Redevelopment Programme Update Procurement Update Demolition

spokesman s update contents
Spokesmans update: Contents: Update

K. Long, 12 December, 2013 Spokesmans update: Contents: Update Evolution of

ke dnssec update
.ke DNSSec Update Toilem Poriot Godwin

.ke DNSSec Update Toilem Poriot Godwin .ke DNSsec update Update on what .ke

agenda
Agenda 1. Update on Elder Selection /

12/2 Congregation Meeting Agenda 1. Update on Elder Selection / Chiller

nc f1rst covid 19 update
NC F1RST COVID-19 Update H. Tasaico

NC F1RST COVID-19 Update H. Tasaico April 24, 2020 NC F!RST COVID19 Update

arena renovation arena renovation arena renovation arena
ARENA RENOVATION ARENA RENOVATION

ARENA RENOVATION ARENA RENOVATION ARENA RENOVATION ARENA RENOVATION UPDATE

sylvester power s bridge schedule b municipal class
Sylvester Powers Bridge Schedule B

Sylvester Powers Bridge Schedule B Municipal Class Environmental Assessment

los gatos creek bridge replacement project
Los Gatos Creek Bridge Replacement

Los Gatos Creek Bridge Replacement Project Oct 18. 2017 Agenda I. Project

pedestrian bridge and connecting trail over arizona
Pedestrian Bridge and Connecting Trail

Pedestrian Bridge and Connecting Trail Over Arizona Avenue, NW Public Meeting

sr 73 loudon county bridge sr73 bridge history
SR 73 Loudon County Bridge SR73 Bridge

SR 73 Loudon County Bridge SR73 Bridge History Several alternates were

study of parameters that influence i girder bridge
STUDY OF PARAMETERS THAT INFLUENCE

STUDY OF PARAMETERS THAT INFLUENCE I-GIRDER BRIDGE BEHAVIOR DURING FIRE

iowa accelerated bridge construction
IOWA ACCELERATED BRIDGE CONSTRUCTION

IOWA ACCELERATED BRIDGE CONSTRUCTION Norm McDonald, PE 2014 ASCE

an awrel case presentation opportunity cost and value
An Awrel Case Presentation:

An Awrel Case Presentation: Opportunity Cost and Value Chain for Fabrication

sh16 st lukes great north road
SH16 St Lukes / Great North Road

SH16 St Lukes / Great North Road Upgrade Project Overview for the Community

acceptance and acceptance and commitment therapy
Acceptance and Acceptance and

Acceptance and Acceptance and Commitment Therapy Commitment Therapy (ACT)

fact
FACT Kirk Strosahl Ph.D. ASU DBH

3/11/2013 Brief Interventions for Radical Change: The Practice of Focused

exposure therapy supervision and training techniques for
EXPOSURE THERAPY: SUPERVISION AND

4/30/18 EXPOSURE THERAPY: SUPERVISION AND TRAINING TECHNIQUES FOR ADDRESSING

evaluation of a web based acceptance amp commitment
Evaluation of a web-based Acceptance

Evaluation of a web-based Acceptance & Commitment Therapy (ACT) program