Waimea Community Dam Update 25 September 2019 Waimea Water; Damwatch Engineering; Fulton Hogan Taylors 25/09/2019 Waimea Water Ltd 1
Waimea Dam is underway and progressing well Ground Breaking Ceremony 9 August 2019 24/09/2019 Waimea Water Ltd 2
Agenda • Design • Construction update • Environmental update • Q&A 24/09/2019 Waimea Water Ltd 3
Design • Concrete Faced Rockfill Dam Turitea Concrete Faced Rockfill dam. Palmerston North 3-D model overlaying existing site topography Constructed 1907, 1912, 1996 24/09/2019 Waimea Water Ltd 4
Design Parameter ▪ Features: • 13 Mm 3 (13 billion litre) reservoir; 53m high; 220m crest length; 430,000 m 3 rock • Rockfill embankment selected as most robust to seismic loads and uses indigenous material • Concrete face membrane • Zoning of material in embankment allows for drainage paths to mitigate internal erosion • Grout curtain seals water migration around and beneath dam ▪ Earthquake: • Operating basis: No non-superficial damage and fully operational: 1:150 AEP (years) • Seismic evaluation basis: Retain reservoir & no-uncontrolled: 1:10,000 AEP (years) • GNS seismic assessment: 0.64g horizontal peak & 1.65g maximum spectral accelerations • Active faults 8 km and 12 km from site 24/09/2019 Waimea Water Ltd 5
Design Parameter ▪ Flood: • Probable maximum flood (PMF): 1094 m3/s (18.6 Mm3 / 24 hour) • 100 year flood: 375 m3/s • 12 May 2019 1:50 year 250 m3/s (47 mm/hr) ▪ Operational flow • Operational flow: 2.2 m3/s • Environmental (min) flow and flushing flow: 0.5 m3/s and 5 m3/s • Maximum: 17 m3/s (1.5 mM3/d = 10% reservoir / day) ▪ Design Standards: NZSOLD / ANCOLD / ICOLD: Highest category (High PIC) 24/09/2019 Waimea Water Ltd 6
Design • Damwatch supporting design enhancements and construction verification (PS-4) • Optimising zoning of rock fill materials to provide flexibility and robustness to geology • Optimised spillway design to de-risk construction and operations • Optimised plinth design and updated grout curtain specification • Mechanical and Electrical design progressing (hydropower compatible) 2009: 5-9 2012: 10-14 2017: 15-17 24/09/2019 Waimea Water Ltd 7
Construction • Access Road: 5.5 km of 6.5 km complete. • Pig Flat bridges underway • Haul roads established • Concrete batching plant operational • Clearing Right Hand Abutment Inspected and mapped top exposed section • Cutting down for Left Hand Abutment • Excavating for Left Hand plinth Completed and cleaned for first 20m • River training to Left Hand side • Vegetation clearance, salvage and mulch underway 24/09/2019 Waimea Water Ltd 8
Construction: Clearing LHS Abutment. As expected 24/09/2019 Waimea Water Ltd 9
Construction: Clearing LHS Abutment. As expected 24/09/2019 Waimea Water Ltd 10
Construction: Preparing for LHS Plinth. As expected 24/09/2019 Waimea Water Ltd 11
Construction: Preparing for LHS Plinth. As expected 24/09/2019 Waimea Water Ltd 12
Construction: Clearing RHS Abutment. As expected 24/09/2019 Waimea Water Ltd 13
Construction: Clearing RHS Abutment. As expected 24/09/2019 Waimea Water Ltd 14
Construction: Clearing RHS Abutment. As expected 24/09/2019 Waimea Water Ltd 15
Construction: September to December 2019 • Clear the RHS and LHS abutments and plinth cut. Rock anchors and slope stabilisation • Commence forming plinth LHS and RHS • Construct diversion bunds to move river away from RHS for culvert construction • Excavate for and commence forming culvert in RHS of riverbed • Continue vegetation clearance in reservoir footprint 24/09/2019 Waimea Water Ltd 16
Environment and Sustainability • 164 Resource Consent conditions; Working 98 action items • Biodiversity Management Plan approved with 8 plans. BTAG Onsite • 7/9 SCEMPS approved, implemented and being monitored • 4 Sediment Retention Ponds & 8 Decanting Bunds operating • Hydroseeding & mulching mitigates erosion and sedimentation • Fortnightly independent water quality monitoring complies • Continuous turbidity monitors guides river works • 2/4 rare plant species being moved (BMP #2) Offsite • Ordering 10,000 plants and weed control for Rough Island 24/09/2019 Waimea Water Ltd 17
Program 12/09/2019 Waimea Water Ltd 18
SOI: We are doing what was said we would do Funding and Spend Forecast cost & schedule to complete 24/09/2019 Waimea Water Ltd 19
SOI: We are doing what we said we would do Risk Management: 22% of Project Budget at Risk Risk Register (56 27) Compaction trials Further Borelogs Embankment design M&E Design Refine Grout Spec FM Preparedness Identify Ownership Assess Mitigate Portfolio 24/09/2019 Waimea Water Ltd 20
SOI: We are doing what we said we would do Health and Safety Compliance and Audit 0 Late or urgent compliance issues: 24/09/2019 Waimea Water Ltd 21
More Information 12/09/2019 Waimea Water Ltd 22
Q&A Questions? Waimea Water; Damwatch Engineering; Fulton Hogan Taylors 24/09/2019 Waimea Water Ltd 23
OOC General Meeting- June 5, 2013 BSEE Update Agenda Regulatory Update NTL
Enrollment Update 2 Enrollment Update K-12 3 Enrollment Update K-5 4
Integrating User Community Content with Systems Management Aaron Prayther,
Legal Update Legal Update Legal Update Legal Update Title Issues
1/23/2014 NWC Redevelopment Programme Update Procurement Update Demolition
K. Long, 12 December, 2013 Spokesmans update: Contents: Update Evolution of
.ke DNSSec Update Toilem Poriot Godwin .ke DNSsec update Update on what .ke
12/2 Congregation Meeting Agenda 1. Update on Elder Selection / Chiller
NC F1RST COVID-19 Update H. Tasaico April 24, 2020 NC F!RST COVID19 Update
ARENA RENOVATION ARENA RENOVATION ARENA RENOVATION ARENA RENOVATION UPDATE
Sylvester Powers Bridge Schedule B Municipal Class Environmental Assessment
Los Gatos Creek Bridge Replacement Project Oct 18. 2017 Agenda I. Project
Pedestrian Bridge and Connecting Trail Over Arizona Avenue, NW Public Meeting
SR 73 Loudon County Bridge SR73 Bridge History Several alternates were
STUDY OF PARAMETERS THAT INFLUENCE I-GIRDER BRIDGE BEHAVIOR DURING FIRE
IOWA ACCELERATED BRIDGE CONSTRUCTION Norm McDonald, PE 2014 ASCE
An Awrel Case Presentation: Opportunity Cost and Value Chain for Fabrication
SH16 St Lukes / Great North Road Upgrade Project Overview for the Community
Acceptance and Acceptance and Commitment Therapy Commitment Therapy (ACT)
3/11/2013 Brief Interventions for Radical Change: The Practice of Focused
4/30/18 EXPOSURE THERAPY: SUPERVISION AND TRAINING TECHNIQUES FOR ADDRESSING
Evaluation of a web-based Acceptance & Commitment Therapy (ACT) program