agenda
play

Agenda ESBN Meter Project Update RM259 Update Feedback on Atos - PowerPoint PPT Presentation

ESBN Presentation to the IGG John Bracken 3 rd May 2018 Agenda ESBN Meter Project Update RM259 Update Feedback on Atos Contract Smart Update (Elaine Sexton) I-SEM Update (Jim Long) 2 esbnetworks.ie ATOS Transition Atos contract is up and


  1. ESBN Presentation to the IGG John Bracken 3 rd May 2018

  2. Agenda ESBN Meter Project Update RM259 Update Feedback on Atos Contract Smart Update (Elaine Sexton) I-SEM Update (Jim Long) 2 esbnetworks.ie

  3. ATOS Transition Atos contract is up and running. Are Suppliers happy with Service? Comment @ January 2018 .. “As far as we are concerned, all is going well with any wrinkles hopefully addressed. I would however appreciate any feedback from suppliers in case there are issues that are causing concerns”. Gary McQuoid Client Executive Atos NI m: +44077333 12759 e: gary.mcquoid@atos.net 3 esbnetworks.ie

  4. Smart Metering Project – IGG Update Thursday 3 rd May 2018 Elaine Sexton, SMART Project

  5. Agenda • ESBN SMART Project o Phased Approach o Overview & Milestones • Market Release Schema v12.00.00 o Scope o Milestone Plan o Progress o Governance • Future IGGs SMART o Implementation Details o Cutover/Contingency Planning 5 esbnetworks.ie

  6. ESBN SMART - Phased Approach Phase 1 Phase 2 Phase 3 250K Smart Meters safely installed by 1 million Smart Meters Remaining Smart December 2020 installed by 2022 Meters installed by end of 2024 • Procure, build & test new solution • Enable remote operation • Two Market Schema releases to facilitate of the service switch in • Gas Meter integration Smart Metering (non -Smart MCRs also incl) Smart Electricity Meters • Daily collection & processing of interval data. • Commence installation of • Smart Pre-Payment • The opportunity for Suppliers to offer new gas smart meters services with secure • In-Home Channel (HAN) Time-of-Use based tariffs remote de- • In-Home Displays for real- energisation/energisation time customer information • Advanced meter alerts & events 2018 2024 2017 2019 2020 2021 2022 2023 Market Release 1 Market Release 2 Market Release 3 Market Release 4 (April 19) (December 20) (December) (December) 6 esbnetworks.ie

  7. ESBN SMART - Overview & Milestones Drop High Level Scope Planned Go-Live Comment Sunday 25 th April 2018 • 0 RMP Extranet: Successfully Delivered • MCR1176 • MCR1179 • 1 SAP IS-U Unicode Conversion August Bank Holiday 2018 No Market Design Changes • Market Assurance • 2 Deployment & Logistics Q4 2018 Updates provided at Smart ILG • 3 Market Release v12.00.00 Easter Weekend April 2019 Significant body of work • MCRs • • SMART Enablement for Meter Market Assurance Installation • • Technical Upgrades IPT • 4 AMI Procurement & Enablement Q4 2019 Updates provided at Smart ILG • 5 Deployment Contractor Q4 2020 Updates provided at Smart ILG • 6 Market Release v13.00.00 Dec 2020 Market Assurance SMART • SMART MCRs (TBC-Prioritisation Process) • Other Market Changes (TBC) • IPT * CoBLCR changes will be raised as required 7 esbnetworks.ie

  8. Market Release Schema v12.00.00 - Overview Element Changing Comment • Market Design ESBN SMART supporting RMDS in providing additions to the Retail Market Design: Documentation o 11 new Standard Profiles - (MCR1167) o 25 new Burn Hour Calendars - (MCR1167) o Effective wattage for every lamp type will be published by ESBN (MCR1167), CoBLCR changes as needed • TIBCO\Supplier EMMAs Schema changes in both jurisdictions Schema • ROI – Schema Changes 3 Data Codes are being modified to include additional or updated values: ‘ RejectReasonCode ’ - 9 new values (MCR0175) o ‘CustomerServiceDetailsCode’ - 3 new values for ROI CoBL – 2 of which o will be added to schema (MCR1173) ‘LoadProfileCode’ – 11 new values (MCR1167) o • NI – Schema Changes - Covered by ReMCoWG/CDA ROI Webforms • Webforms for ROI will need to be changed to accommodate the new Customer Service Special Needs Details. • ROI Webforms affected by these changes are those associated with the following MM: 010, 013, 016, 017 • ROI Extranet MCR1173,MCR1140 & MCR1167 • Downloadable Files 3 Downloadable files changing: DOM_CUST, COMM_CUST & UNMET_CUST (MCR1173, MCR1140, MCR1169 & MCR1167) * CoBLCR changes will be raised as required 8 esbnetworks.ie

  9. Market Release Schema v12.00.00 – Scope MCR Version Description Schema/ Number Non-Schema MCR0175 V5.0 New Reject Reasons for Address Change Rejection Schema MCR1173 V2.0 Vulnerable Customer Implementation in ROI of SI 463 Schema MCR1167** V3.0 Facilitate energy efficiencies in Local Authority Public Lighting Schema MCR1140 V3.0 Introduction of Eircodes into the Retail Market Design in Ireland Non-Schema MCR1169 V2.0 Addition of Postal Code to two Downloadable Meter Point Details Files Non-Schema MCR1175 V3.0 Provide Market Participant Business Reference (MPBusinessReference) for Reading Non-Schema MCR1180 V4.0 New Registration Default Supplier Non-Schema MCR1183 V2.0 010 Customer Validation Agreement (NI) Schema MCR1154 V2.0 New Unmetered Tariff for NI Schema Other Comment • Smart Enablement SAP IS-U Enhancement Pack (8.0) • SMART Enablement for Meter Installation • SAP Hana ** Pending IGG approval for re-versioning 9 esbnetworks.ie

  10. Market Release v.12.00.00 – Milestone Plan 2018 2019 Q1 Q2 Q3 Q4 Q2 Q3 Q1 16 th 7 th 7 th 4 th 3 rd 30 th 27 th 25 th 29 th 3 rd 8 th 5 th V.12.00.00 Schema Published Jan 28th Design/Build/Test CRU go/no Decision IPT Prep IPT Exec Go Live Easter 2019 Other Go live August 2018 Unicode Conversion Go Live Easter 2019 SAP Hana v SAP IS-U Enhancement Pack (8.0) Go Live Easter 2019 Smart Enablement for Meter Installation Go Live Easter 2019 Market Engagement Key IGG (Meetings & Calls) Key Milestone Go lives 10 esbnetworks.ie

  11. Market Release v12.00.00 – Status MCR Description Status MCR0175 New Reject Reasons for Address Change Rejection MCR1173 Vulnerable Customer Implementation in ROI of SI 463 MCR1167** Facilitate energy efficiencies in Local Authority Public Lighting MCR1140 Introduction of Eircodes into the Retail Market Design in Ireland MCR1169 Addition of Postal Code to two Downloadable Meter Point Details Files MCR1175 Provide Market Participant Business Reference (MPBusinessReference) for Reading MCR1180 New Registration Default Supplier MCR1183 010 Customer Validation Agreement (NI) ReMCoWG/CDA MCR1154 New Unmetered Tariff for NI ReMCoWG/CDA Other Comment Status • Smart SAP IS-U Enhancement Pack (8.0) • Enablement SMART Enablement for Meter Installation • SAP Hana ** Pending IGG approval for re-versioning, version numbers above will change 11 esbnetworks.ie

  12. Market Release Schema v12.00.00 – Governance • Existing Governance model will be used Topic Channel Frequency • Periodic Update IGG As per agreed schedule • Participant Queries RMDS Email/Phone Ad-hoc • Market Design RMDS Email/Web As Required • Market Release Timelines • Publications • Market Assurance RMDS/Gemserv As Required RMDS – Contact Details o E-Mail: info@rmdservice.com o Website: https://rmdservice.com o Phone: (01) 669 2410 esb.ie

  13. Market Release Schema v12.00.00 – Future IGGs Topic MCR# Description Topic IGG Meeting (Indicative Dates-TBC) Implementation MCR1167 Public Lighting ESBN Publication: Aug 2018 • Standard Profiles Details • Burn Hour Calendars • Effective Wattages MCR1140 Eircodes Upload mechanism and schedule Nov 2018 for circa 1.5 Million Eircodes ‘Work In Progress’ items will be MCR1180 New Registration Default Nov 2018 Supplier discussed MCR1173 Vulnerable Customers Reconciliation with suppliers for Nov 2018 new codes & Rejection Reasons MCR1140 Downloadable Meter Point Files Samples files Jan 2019 MCR1173 MCR1167 MCR1169 MCR1140 RMP Extranet screenshots Samples screenshots Jan 2019 MCR1173 MCR1167 MCR1167 700 Series MMs Samples 700MMs Feb 2019 Cutover & All Cutover & Contingency Planning Cutover & Contingency Approach Nov 2018 Contingency Planning esb.ie

  14. Appendix esb.ie

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend