pedestrian bridge and connecting trail over arizona
play

Pedestrian Bridge and Connecting Trail Over Arizona Avenue, NW Public Meeting #2 January 15 th , 2020 Agenda Project Purpose and Limits Timeline & Public Feedback Preliminary Design - Pedestrian Bridge - Sidewalks &

0 downloads 8 Views 2,68 MB Size Report
  1. Pedestrian Bridge and Connecting Trail Over Arizona Avenue, NW Public Meeting #2 January 15 th , 2020

  2. Agenda • Project Purpose and Limits • Timeline & Public Feedback • Preliminary Design - Pedestrian Bridge - Sidewalks & Pedestrian Crossings - Aesthetic Treatments – Ramp and Railings - Plantings - Trail • Final DDOT Recommendations • Next Steps • Questions

  3. Purpose and Project Area The purpose of the project is to rehabilitate the existing pedestrian bridge over Arizona Avenue NW and to improve the connecting trail to provide greater community connectivity to the Palisades Recreation Center. The project is needed because the existing pedestrian bridge is nearing the end of its service life.

  4. Timeline

  5. April 10, 2018 Public Meeting Feedback 6:30-8:00 PM Palisades Library • 124 total comments were received (23 at the meeting, 101 via email) – ~66% support at least some trail improvements – ~25% do not support any trail improvement • Of the 64 residents* who provided comments about the trail and surface: – 29 support some level of improvement and changes to trail surface • 14 support based on potential for improved drainage/runoff – 24 want no change to the trail – 9 stated that they don’t want “paving”/asphalt *residency only known for the 101 email comments

  6. ANC, PCA & Citizen Group Feedback • PCA “Middle Ground” draft letter supporting improvements (April 2019) • Trolley Trail Preservation Group letter opposing improvements (Fall 2019) • Palisades Family Network petition supporting improvements (Fall 2019) • ANC 3D letter supporting improvements (November 2019)

  7. Key Elements of Bridge and Trail Improvements Bridge and Pedestrian Multi-Use Trail Designed Ramp Rehabilitation and to Meet Accessibility Reconstruction Guidelines Stormwater Management Sidewalk & Crosswalk and Surface Drainage Safety Improvements Improvements Context Sensitive Design and Landscaping

  8. Pedestrian Bridge

  9. Existing Pedestrian Bridge • Constructed in Early 1980’s • Vertical Clearance – Existing Minimum = 14’-2” – AASHTO/DDOT Standard Minimum = 17’-6” • Structural Condition – Recent Inspection (2018) = 5 (Fair Condition) (0 to 9 scale) – Prestressed Concrete Box Beams

  10. Pedestrian Bridge • Main Span over Arizona Avenue – Prefabricated Steel "Box” Truss – Safety Handrails at 42” – Mesh Panels – Concrete Deck – Minimal Arch

  11. Prefabricated Steel Trusses • Parallel Chord “Box” Truss Example

  12. Pedestrian Bridge • Abutments – Modifications • Modify/Extend Abutment Using Lightweight Backfill • Evaluate Existing Foundations – Repair Existing Defects • Spalls and cracks

  13. Pedestrian Bridge • Pedestrian Access Ramp – Replace Existing West Ramp Structure – Design Follows Accessibility Guidelines – Raised Trail Profile = Longer Ramp – Evaluated New Ramp on East Side of Arizona Ave. Avenue

  14. Proposed Bridge & West Access Ramp

  15. Preliminary Design • View from South Side of Bridge

  16. Preliminary Design 63’-6” 34’-0” TOP OF CURB CAST-IN-PLACE TOP OF RAILING LANDING (TYP.) CONCRETE SLAB PALISADES TRAIL FINISHED GRADE EXISTING GROUND EXISTING 78” DIA. WATER MAIN WEST RAMP – ELEVATION

  17. Sidewalks & Pedestrian Crossings

  18. Proposed Sidewalks PROPOSED 5-FT WIDE SIDEWALK WEST ACCESS RAMP EXISTING 78” DIA. WATER (TO REMAIN ) PALISADES TRAIL PEDESTRIAN BRIDGE AND CONNECTING TRAIL PROPOSED 5-FT SIDEWALK B L ARIZONA AVENUE PROPOSED RETAINING WALL PROPOSED 5-FT SIDEWALK LEGEND : PROPOSED CONCRETE SIDEWALK

  19. Traffic & Pedestrian Signal Study

  20. Pedestrian and Bicycle Volumes THURSDAY 05-16-2019 14-HOUR COUNTS • 71 pedestrians and 5 bicyclists on pedestrian bridge • 34 pedestrians and 2 bicyclists on bridge ramp • 57 pedestrians and 16 bicyclists crossed over Arizona Avenue at Sherier Place • No pedestrians or bicyclists were observed crossing Arizona Avenue to access pedestrian bridge LEGEND: • AM/PM PEAK HOUR (14-HOUR) PEDESTRIAN VOLUMES • AM/PM PEAK HOUR (14-HOUR) BICYCLE VOLUMES

  21. Pedestrian and Bicycle Volumes SATURDAY 05-18-2019 14-HOUR COUNTS • 74 pedestrians and 9 bicyclists on pedestrian bridge • 48 pedestrians and 10 bicyclists on bridge ramp • 75 pedestrians and 19 bicyclists crossed over Arizona Avenue at Sherier Place • No pedestrians or bicyclists were observed crossing Arizona Avenue to access pedestrian bridge LEGEND: • AM/PM PEAK HOUR (14-HOUR) PEDESTRIAN VOLUMES • AM/PM PEAK HOUR (14-HOUR) BICYCLE VOLUMES

  22. Traffic Study Results • A fully signalized intersection of Arizona Avenue NW and Sherier Place NW does not meet the signal warrants. • HAWK pedestrian signal meets DDOT requirements. • Provide improved pavement markings and HAWK pedestrian signal at intersection of Arizona Avenue, NW and Sherier Place, NW.

  23. Aesthetic Treatments Ramp & Railings

  24. Aesthetic Treatments • West Ramp Existing Conditions

  25. Aesthetic Treatments • Railings

  26. Aesthetic Treatments • Railings: Potential Alternatives HORIZONTAL RAILS METAL INFILL VERTICAL RAILS

  27. Plantings

  28. Plantings • Planting Mix - Sun

  29. Plantings • Planting Mix - Shade

  30. Trail

  31. Trail Typical Section TYPICAL SECTION PALISADES TRAIL N.T.S.

  32. Trail Surface STABILIZED DECOMPOSED GRANITE (Vendor Photo)

  33. Final DDOT Recommendations & Next Steps

  34. Final DDOT Recommendations • Trail Limits – Galena Pl. to Sherier/Nebraska Ave. • Replace Pedestrian Bridge (Steel Box Truss) & West Access Ramp • Recommending to install HAWK Pedestrian Crosswalk Signal • Install Sidewalk Improvements on Arizona Avenue, Carolina Place and Sherier Place • Use Stabilized Decomposed Granite Trail Surface

  35. Next Steps • Proceed to Phase 2 - Final Design – 65%, 90%, Final Plan Submissions – Public Meeting at 90% Submission – Bid Advertisement and Construction

  36. Questions

  37. Thank you! Zahra Dorriz Zahra.dorriz@dc.gov 202-671-4584 Jennifer Koch jenniferk@rhiplaces.com 703-683-7447x134 Project Website: https://ddot.dc.gov/page/reconstruction-and- rehabilitation-pedestrian-bridge-and-connecting-trail- arizona-avenue-nw

Recommend Documents


temporary covered temporary drop off pedestrian bridge
Temporary Covered Temporary Drop Off

Temporary Covered Temporary Drop Off Pedestrian Bridge Pedestrian Bri

mockingbird bicycle pedestrian bridge
Mockingbird Bicycle & Pedestrian

Mockingbird Bicycle & Pedestrian Bridge Bicycle and Pedestrian Advisory

bridge rehabilitation replacement needs
Bridge Rehabilitation/Replacement Needs

Bridge Rehabilitation/Replacement Needs Redbud Trail Bridge Barton Springs Road

pillsbury pedestrian bridge minneapolis walkway over the
pillsbury pedestrian bridge,

pillsbury pedestrian bridge, minneapolis walkway over the hudson, poughkeepsie

us hwy 64 264 pedestrian crossing at the little bridge
US Hwy. 64/264 Pedestrian Crossing at

Town of Nags Head US Hwy. 64/264 Pedestrian Crossing at the Little Bridge

dexter area b2b segments c and d1 dexter area b2b
Dexter Area B2B segments C and D1

Dexter Area B2B segments C and D1 Dexter Area B2B segments C and D1 River

figg structural analysis presentation university city
FIGG Structural Analysis Presentation

FIGG Structural Analysis Presentation University City Prosperity Project

sanctuary scenic trail
SANCTUARY SCENIC TRAIL Bicycle &

MONTEREY BAY SANCTUARY SCENIC TRAIL Bicycle & Pedestrian Facilities

ucf alafaya trail pedestrian safety study campus
UCF/Alafaya Trail Pedestrian Safety

UCF/Alafaya Trail Pedestrian Safety Study & Campus Development Agreement

arizona memory project
Arizona Memory Project Connecting

Arizona Memory Project Connecting Arizonans to their government, their

sr 73 loudon county bridge sr73 bridge history
SR 73 Loudon County Bridge SR73 Bridge

SR 73 Loudon County Bridge SR73 Bridge History Several alternates were

study of parameters that influence i girder bridge
STUDY OF PARAMETERS THAT INFLUENCE

STUDY OF PARAMETERS THAT INFLUENCE I-GIRDER BRIDGE BEHAVIOR DURING FIRE

iowa accelerated bridge construction
IOWA ACCELERATED BRIDGE CONSTRUCTION

IOWA ACCELERATED BRIDGE CONSTRUCTION Norm McDonald, PE 2014 ASCE

author
Author: Jojok Widodo Soetjipto Tri

The 4 th International Conference on Rehabilitation and Maintenance in Civil

wearing surface replacem ent
WEARING SURFACE REPLACEM ENT Public

KINGFIELD CENTENNIAL BRIDGE #5852 WEARING SURFACE REPLACEM ENT Public Meeting

h igh e arly s trength c oncrete amp uhpc
H IGH E ARLY S TRENGTH C ONCRETE &

B RIDGE 1-438 N ICH OLAS D EAN D EL D OT B RID GE D ESIGN T IME IS OF THE E

los gatos creek bridge replacement project
Los Gatos Creek Bridge Replacement

Los Gatos Creek Bridge Replacement Project Oct 18. 2017 Agenda I. Project

sylvester power s bridge schedule b municipal class
Sylvester Powers Bridge Schedule B

Sylvester Powers Bridge Schedule B Municipal Class Environmental Assessment

update
Update 25 September 2019 Waimea

Waimea Community Dam Update 25 September 2019 Waimea Water; Damwatch

an awrel case presentation opportunity cost and value
An Awrel Case Presentation:

An Awrel Case Presentation: Opportunity Cost and Value Chain for Fabrication

sh16 st lukes great north road
SH16 St Lukes / Great North Road

SH16 St Lukes / Great North Road Upgrade Project Overview for the Community

acceptance and acceptance and commitment therapy
Acceptance and Acceptance and

Acceptance and Acceptance and Commitment Therapy Commitment Therapy (ACT)